Resolved
That the report be noted. Reason: To ensure that the committee is kept updated on the latest finance and performance position.
Communities and Environment Policy and Scrutiny Committee noted this item on Monday 18 July 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted. Reason: To ensure that the committee is kept updated on the latest finance and performance position.
1. This report provides details of the 2015/16 outturn position for both finance and performance across services within City & Environmental Services and Communities and Neighbourhoods.
Analysis
Finance – General Fund
2. The services that relate to the Communities and Environment Policy and Scrutiny Committee cross two directorates (City and Environmental Services and Communities and Neighbourhoods). Service Plan variations which relate to services within this scrutiny are shown below:
Variance Budget Outturn £'000 £'000 £'000 City & Environmental Services Waste 9,248 9,510 +262 Communities and Neighbourhoods Housing General Fund 2,568 2,649 +81 Public Protection -215 -458 -243 Community Safety 961 779 -182 Smarter York 2,714 2,616 -98 Community Centres 99 98 -1 Communities and Equalities 1,844 1,814 -30 Note: „+‟ indicates an increase in expenditure or shortfall in income „-„ indicates a reduction in expenditure or increase in income 3. Details of the main variations by service plan are detailed in the following paragraphs.
Waste (+£262k)
4. Within waste collection, the main variances are £182k additional staffing costs, primarily the use of temporary staff, and increased transport costs of £221k for vehicle repairs and hire.
5. Waste disposal tonnages were broadly in line with budgets however there was an overspend of £200k on dealing with recycling due to the costs of processing co-mingled recyclates compared to a credit received for separated recyclates. Historically this was dealt with at zero cost however increased costs to Yorwaste of dealing with co-mingled material means this now equates to an additional cost of £70/tonne. This will need to be managed going forward by use of new vehicles and better working practices. These additional costs were offset by savings on general waste disposal (£53k) and additional income from the sale of landfill gas (£71k).
6. There was no Yorwaste Dividend received during the year following the companies change in status to a Teckal company however there were savings arising form waste procurement costs and loan interest and other miscellaneous budgets (£210k)
Housing General Fund (+£81k)
7. Within Housing General Fund there was an overspend of £68k within Travellers due to additional repairs costs and a shortfall on Travellers site income of £20k due to the Boxing Day floods leaving the site uninhabitable for part of the year.
Public Protection (-£243k)
8. Within Bereavement Services, the numbers of cremations performed during the year were significantly higher than expected. This as well as some cost savings and increases in other income resulted in a £187k underspend during the year.
Community Safety (-£182k)
9. The Community Safety service received several amounts of one- off funding during the year from a number of different sources resulting in an overall underspend of £182k. Neighbourhood Working (-£98k)
10. There was an underspend within Neighbourhood working of £98k due to a £51k saving from a restructure of senior management, and £42k savings in arboriculture due to reduced overtime and additional work on HRA trees.
Communities and Equalities (-£30k)
11. The new ward committee decision-making process is working well with all wards having held ward committee and ward team meetings. Wards are developing their spending plans in response to ward priorities and through engagement with their communities. Actual spend at year end totalled £85k compared to the devolved budget of £475k. The underspend of £390k has been added to a reserve to ensure that the wards retain those amounts on top of the new base 2016/17 budgets.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2015/16 Finance and Performance Outturn ReportReport | 6 pages | DownloadRead as text |
PDF |
Communities and Environment Scrutiny Scorecard 2015-16Appendix A | 4 pages | Download |
Follow Communities and Environment Policy and Scrutiny Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 May 2017 | MinutesThat approval of the minutes be deferred until the next appropriate scrutiny meeting. Reason: In order that additiona... | Approved | Open |
| 17 May 2017 | Six - Monthly Update Report from North Yorkshire Fire & Rescue ServiceThat Members note the report. Reason: In order that the Committee are up to date with North Yorkshire Fire & Rescue S... | Noted | Open |
| 17 May 2017 | Implementation Update - Housing Registrations Scrutiny ReviewThat; 1. Members note the implementation update information detailed in Annex A 2. Recommendations (ii) & (ix) be sig... | Noted | Open |
| 15 Mar 2017 | MinutesThat the minutes of the Communities and Environment Policy and Scrutiny Committee meeting held on 25 January 2017 be ... | Approved | Open |
| 15 Mar 2017 | 2016/17 Finance and Performance Monitor 3 ReportThat Members note the report. Reason: To update the Committee on the latest finance and performance position. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.