Community Led Local Development - 4CommunityGrowth York: Local Development Strategy and Accountable Body
AgreedPlanning2 papers
Decision Session - Executive Member for Economy and Strategic Planning agreed this item on Tuesday 16 August 2016. Below is the council's own wording, with the papers it was decided on.
That the Executive Member agrees to: (i) Endorse the draft 4CommunityGrowthYork Local Development Strategy (contained in Annex A) (ii) Provide confirmation that City of York Council will act as Accountable Body for the duration of the 4CommunityGrowthYork project. Reason: To meet the contractual requirements for funding and to support the submission of the 4CommunityGrowthYork Local Development Strategy as the next required milestone in the bid for European Structural and Investment Fund (ESIF) Community Led Local Development Funding. That the Executive Member agrees to: (i) Endorse the draft 4CommunityGrowthYork Local Development Strategy (contained in Annex A) (ii) Provide confirmation that City of York Council will act as Accountable Body for the duration of the 4CommunityGrowthYork project. Reason: To meet the contractual requirements for funding and to support the submission of the 4CommunityGrowthYork Local Development Strategy as the next required milestone in the bid for European Structural and Investment Fund (ESIF) Community Led Local Development Funding.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Economy and Strategic Planning, 9 pages
Decision Session – Executive Member for 16 August 2016 Economic Development & Community Engagement (Deputy Leader)
Report of the Assistant Director (Communities, Culture and Public Realm)
Community Led Local Development - 4CommunityGrowth York: Local Development Strategy and Accountable Body
Summary 1. This report provides: A draft of the 4CommunityGrowthYork Local Development Strategy for endorsement /comment to ensure that all parties have had an opportunity to contribute prior to the submission deadline on the 31st August 2016. Information on the results of the consultation activities which have informed and supported the drafting of the Local Development Strategy. Feedback on progress on the activities required under the stage 1 funding agreement.
Recommendations 2. The Executive Member is asked to: Endorse the draft 4CommunityGrowthYork Local Development Strategy (contained in Annex A) Confirm that City of York Council will act as Accountable Body for the duration of the 4CommunityGrowthYork project. Reason: To meet the contractual requirements for funding and to support the submission of the 4CommunityGrowthYork Local Development Strategy as the next required milestone in the bid for European Structural and Investment Fund (ESIF) Community Led Local Development Funding. Background 3. City of York Council first considered an expression of interest in the (ESIF) 2014 – 2020 Community Led Local Development in 2013. Executive member support and Accountable Body status was confirmed at an Executive Member Decision session on 17 December 2013.
4. There have been a number of required revisions since the original Expression of Interest. The original project area has been revised in line with advice from the two Managing Authorities (the Departments of Communities and Local Government and Work and Pensions). The total pot applied for has increased slightly in line with an increase in the required minimum project budget and the total project budget is now £2.58 million (50% match funded), so potentially drawing down £1.29 million ESIF funding into York.
Progress since the last review 5. City of York Council’s bid for preparatory stage 1 funding under the ESIF Community Led Local Development programme was successful and this was confirmed in February 2016 following approval of required amendments. Since receipt of the contracts from both of the Managing Authorities, work has been going on to meet all of the required activities within the funding contract including: Resident and stakeholder engagement Establishing a Local Action Group made up local residents, voluntary and community sector, business and public sector representatives. (N.B. to be made up of no more than 49% public sector representatives) Creation of a Local Development Strategy Confirmation of the Accountable Body
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Economy and Strategic Planning at York and we tell you when its next papers are published, before the meeting rather than after it.
Hull Road Verges Status (16:09)i. That the Planning Authority’s position on the status of the Hull Road verges, located between Nursery Gardens and ...
Quarterly Economic Update (16:09)That the contents of the report are noted. Reason: To support York’s ongoing economic work and monitor how York is pe...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies