Review of June 2016 Surface Water Flood Event

Noted Executive 1 paper

Decision Session - Executive Member for Environment and Climate Emergency noted this item on Monday 5 September 2016. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

( i ) That the actions carried out by the Council in response to the surface water flood event in June 2016 as set out in paragraphs 6-15 of the Officer’s report be noted. (ii) That the future actions planned as set out at Paragraphs 16-18 of the Officer’s report be agreed. (iii) That Officers prepare the business case for a major capital investment project to the Executive for the delivery of significant improvements to the council operated drainage systems to form part of the Budget Process for the 2017/18 budget. (iv) That Officers review the enforcement process for building materials which end up blocking gulleys , and that there is a clear reporting system publicised to help prevent this from happening. Reason: To improve the management of York’s gulley assets and reduce the risk of future flooding. ( i ) That the actions carried out by the Council in response to the surface water flood event in June 2016 as set out in paragraphs 6-15 of the Officer’s be noted. (ii) That the future actions at Paragraphs 16-18 of the Officer’s report be agreed. (iii) That Officers prepare the business case for a major capital investment project to the Executive for the delivery of significant improvements to the council operated drainage systems to form part of the Budget Process for the 2017/18 budget. (iv) That Officers review the enforcement process for building materials which end up blocking gulleys , and that there is a clear reporting system publicised to help prevent this from happening. Reason: To improve the management of York’s gulley assets and reduce the risk of future flooding.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Environment and Climate Emergency, 6 pages

Decision Session - Executive Member for the 5 September 2016 Environment

Report of the Assistant Director (Communities, Culture & Public Realm)

Review of June 2016 Surface Water Flood Event

Summary 1. This report provides a report back, as requested by the Executive Member, on the Council‟s response to the surface water flooding that occurred in June this year. Recommendations 2. The Executive Member is asked to:  Note the actions carried out by the Council in response to the surface water flood event as set out in paragraphs 6 to 15.  Agree the future actions planned as set out in paragraphs 16 to 18. Reason: To improve the management of York‟s gulley assets and reduce the risk of future flooding. Background 3. Intense rainfall fell on York on 10 and 12 June 2016 (10mm and 13mm respectively were recorded during concentrated periods) leading to over 90 flooding complaints being received from a variety of sources and locations. A range of roads were badly affected by flood waters, 2 properties suffered from internal flooding and 2 garages were flooded.

4. Following these events the Council has carried out a thorough programme of work to address the issues. 64 individual reports of blocked gulleys/flooding were received. All work found to be necessary has been undertaken with 18 sites that proved more problematic having works ongoing to resolve outstanding issues. Further follow-up investigatory work involving parking suspensions is required at some of these sites. 5. Due to the intense nature of the rainfall involved in this event, highway and potentially property flooding would have been expected since the design capacity for drainage systems can be overwhelmed during intense, localised storms. National media sources indicate that issues were experienced across the country at that time. However, our investigations have shown that a lack of routine maintenance in past years has exacerbated the situation in York with around half the gulleys investigated found to be blocked with debris.

Summary of action taken in the worst effected locations - Heworth Ward: 6. Bell Farm Avenue – Almost all of the 23 gulleys in the street were found to be blocked or heavily silted up; the Yorkshire Water surface water sewer was also found to be blocked. All gulleys were cleansed. 6 require further work and Yorkshire Water are investigating their sewer.

7. Roache Avenue – Almost all of the 16 gulleys in the street were affected by blockages and the Yorkshire Water sewer requires further investigation. 2 gulleys require further work and contact has been made with Yorkshire Water.

8. Middleham Avenue – Builders‟ debris and hard debris was found in almost all of the 26 gulleys. All are now running after considerable works. The Yorkshire Water sewer requires further investigation. 9. Bad Bargain Lane – A surface water sewer, unrecorded by Yorkshire Water, was found to be blocked; this has been jetted by the Council to establish its route and cleanse it and the issue referred to Yorkshire Water. High levels of surcharge have been identified in the receiving surface water sewer and this has also been referred to Yorkshire Water. Half of the gulleys in the street were found to be blocked and these have been cleansed.

- Hull Road Ward 10. Etty Avenue – Two thirds of the gulleys were found to be blocked by litter, hard debris and building materials. These have been cleansed and all are now running.

11. Burlington Avenue – A third of the gulleys were blocked by litter and hard debris. The majority have been cleansed and the remainder will be cleansed following a parking suspension. 12. Wolfe Avenue – Almost all of the 13 gulleys were blocked. All have been cleansed. 13. Walney Road – The Yorkshire Water surface water sewer was found to be blocked and a length of un-recorded pipework has been investigated. All issues have been referred to Yorkshire Water for further investigation. Two thirds of the gulleys were found to be initially blocked.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Review of June 2016 Surface Water Flood EventReport 6 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
AW
Councillor Andrew WallerCommittee Member, present

More from York Decision Session - Executive Member for Environment and Climate Emergency

All decisions
MeetingDecisionOutcome
20 May 2025 MinutesThat the minutes of the Decision Session held on 29 April 2025 be approved and signed by the Executive Member as a co... Approved Open
20 May 2025 North Yorkshire & York, Local Nature Recovery Strategy (LNRS) consultation draftThat the Executive Member: i. Noted the work that had been undertaken in relation to the North Yorkshire and York Loc... Noted Open
29 Apr 2025 Minutes (10:01am)That the minutes of the Decision Session held on 18 March 2025 be approved and signed by the Executive Member as a co... Approved Open
29 Apr 2025 Public Realm - Service Developments (10:14am)That the Executive Member: i. Considered the two petitions received by the Council and considered if the actions alre... Noted Open
18 Mar 2025 Minutes (10:00am)That the minutes of the Decision Session held on 19 November 2025 be approved and signed by the Executive Member as a... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies