Resolved
That Members note the report. Reason: To update the Committee on the development of a five year flood plan for York.
Communities and Environment Policy and Scrutiny Committee noted this item on Wednesday 15 March 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That Members note the report. Reason: To update the Committee on the development of a five year flood plan for York.
1. Government have made funding available to improve the Foss Barrier and other flood defence assets in the city. The Environment Agency (EA) is leading on the development of a 5 year flood plan for York. City of York Council are working closely with the EA on the development of this plan. 2. An update to the plan is given at Annex 1 and a further presentation will be made at the meeting. Feedback and guidance is sought from Members on the progress of the plan to date and the way in which the plan should be developed through its next stages.
3. The flooding in late December 2015 followed an intense period of rainfall across November and December, due to the impact of Storms Desmond and Eva. Record river levels were observed in many river catchments across the north of England. More than 4000 homes and 2000 businesses flooded across Yorkshire with 453 properties and 174 businesses flooded in York.
4. A range of reviews and recovery programmes have been initiated by all relevant authorities and these have helped shape the development of the York 5 year flood plan and the delivery of Government funding that has been secured since the floods.
5. The latest quarterly newsletter relating to the flood risk improvements in the city is provided at Annex 1, giving details of the consultation events that were held in late 2016. This Scrutiny Committee was previously consulted at its September 2016 meeting and future updates can be provided at the Committee’s request. Options and Analysis
6. This report is for information only, but the Committee may choose to comment on the work undertaken to date and the planned work detailed in Annex 1.
Council Plan
7. Improved provision of flood defences supports a prosperous city for all through safer communities for residents, businesses and visitors. A wide range of consultation events will ensure this is in line with the needs and expectations of local communities.
Implications 8. Financial - Funding is allocated directly to the EA; the £60M funding is available to be directed towards key flood risk projects in the City in the short term. The extent of required works will likely require wider funding and Department for Environment, Food & Rural Affairs (DEFRA) funding bids will be developed. There are likely to be contribution requirements as part of this wider work. This will be developed further and consulted upon later in 2017.
9. There are no human resources, equalities, legal, crime & disorder, information technology, property or other implications associated with this report.
10. That the report be noted.
Reason: This report is for information only as there are no recommendations associated with the update provided at Annex 1 to this report. Contact Details
Author: Chief Officer Responsible for the report: Steve Wragg Neil Ferris Flood Risk and Asset Corporate Director - Economy & Place Manager Highways (01904) 553401 Report Approved Date 02/03/17 Wards Affected: All For further information please contact the author of the report
Annexes: Annex 1- EA York Spring 2017 Newsletter
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
York Spring 2017 NewsletterAppendix 1 | 4 pages | Download |
PDF |
Flood Risk in York: the York 5 Year Plan UpdateReport | 3 pages | DownloadRead as text |
Follow Communities and Environment Policy and Scrutiny Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 May 2017 | MinutesThat approval of the minutes be deferred until the next appropriate scrutiny meeting. Reason: In order that additiona... | Approved | Open |
| 17 May 2017 | Six - Monthly Update Report from North Yorkshire Fire & Rescue ServiceThat Members note the report. Reason: In order that the Committee are up to date with North Yorkshire Fire & Rescue S... | Noted | Open |
| 17 May 2017 | Implementation Update - Housing Registrations Scrutiny ReviewThat; 1. Members note the implementation update information detailed in Annex A 2. Recommendations (ii) & (ix) be sig... | Noted | Open |
| 15 Mar 2017 | MinutesThat the minutes of the Communities and Environment Policy and Scrutiny Committee meeting held on 25 January 2017 be ... | Approved | Open |
| 15 Mar 2017 | 2016/17 Finance and Performance Monitor 3 ReportThat Members note the report. Reason: To update the Committee on the latest finance and performance position. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.