Economy and Place Policy and Scrutiny Committee, Wednesday 4 October 2017 at 5.30pm

Progress Update on Allerton Park Waste Recovery Treatment Centre

Noted Scrutiny 2 papers

Economy and Place Policy and Scrutiny Committee noted this item on Wednesday 4 October 2017. Below is the council's own wording, with the papers it was decided on.

Item19

Resolved

That the progress update on the AWRP be noted and members comments be taken into account. Reason: In order that Members are keep up to date in relation to developments at AWRP.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Economy and Place Policy and Scrutiny Committee, 9 pages

Allerton Waste Recovery Park update Economy & Place Scrutiny Committee October 2017 Background CYC entered into a Joint Waste Management Agreement (JWMA) with NYCC (December 2010)

This supported NYCC in entering into a contract with AmeyCespa (identified as preferred bidder in 2009) for the provision of a long term Waste management service.

The objective was to deliver a long term sustainable alternative to landfill for the treatment of residual waste

AmeyCespa were required to secure planning (February 2013) for Waste recovery facility (AWRP) at Allerton quarry before confirming final cost to the council (June 2014).

The final cost was presented in 2014 and NYCC agreed to financial close (September 2014) and CYC agreed to enter into the JWMA at the same time.

The contract enables CYC and NYCC to achieve in excess of 50% recycling and composting rate and a minimum of 95% of residual waste diverted from landfill Background Value is recovered from residual waste through •Additional recycling (target 5%) •And production of electricity (to power approx. 40,000 homes) •Recovery of heat (long term objective)

Greenhouse gas benefits (compared to landfill) are equivalent to removing 12,000 cars from the Highway

The Contract effectively fixes much of the council's long term waste management price risk from inflation and increases in landfill tax with long term average price to the Councils for treatment estimated to be below current costs of disposal.

Over £200m to the York and North Yorkshire economy over the lifetime of the contract (new jobs in construction and operation)

The proportion of waste in York and North Yorkshire at commercial close was approximately at a ratio of 79:21. It is assumed that all payments and benefits will be shared consistent with this ratio. Technology AWRP treats waste through a series of processes including mechanical separation of recyclable materials (known as mechanical treatment or MT), anaerobic digestion (AD) and thermal treatment through incineration and generation of electricity (known as Energy from Waste or EfW).

Tipping hall

The waste is delivered to AWRP into the tipping hall where it is tipped into bunkers. These are for Mechanical treatment or direct to EfW. Technology Cranes then lift the waste from the bunkers to start the Mechanical Treatment process.

Mechanical Treatment

The Mechanical Treatment plant (MT) separates metals, plastics and paper and is capable of sorting up to 408,000 tonnes per annum (tpa), although the planning consent limits the throughput of AWRP to 320,000 tpa. The MT plant also separates approximately 40,000 tpa of organic waste for treatment through the AD plant. Technology Anaerobic Digestion

The Anaerobic Digestion (AD) plant uses microbes to break down the organic waste in the absence of air to produce a gas and compost like output known as digestate.

Energy from Waste (EfW)

Remaining waste will be burnt in the Energy from Waste (EfW) incinerator. The heat from the EfW is used to produce steam and drive a turbine which produces electricity for export to the national grid. The capacity of the EfW is approximately 320,000 tpa. Transferring York’s waste Transfer station

In order to manage the transfer of waste from York and the other collection authorities to AWRP, a strategy around transfer stations has been developed.

This was to ensure that waste was delivered to AWRP in the most efficient way possible.

Currently CYC use the site at Harewood Whin to landfill residual waste. It was agreed that the waste transfer station to service, principally, City of York Council and Selby District council would be located at Harewood Whin

The Harewood Whin waste transfer station, that is managed by YorWaste, opened in the summer (2017) ready for use during the commissioning period. Construction and commissioning Construction

Construction is now nearing completion and is on schedule to complete on time for full service commencement at the beginning of February 2018.

Commissioning

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 5: Presentation: Allerton Park UpdateReport 9 pages DownloadRead as text
PDF
Progress Update on Allerton Park Waste Recovery Treatment CentreReport 9 pages Download

At this meeting

Whole meeting

More from York Economy and Place Policy and Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Mar 2023 Minutes [17.33]That; i. the minutes of the meeting held on 17 January 2023 and 30 January 2023 be approved and signed by the Chair a... Approved Open
8 Mar 2023 City Centre Café Licences [18.46]That; i. It be recommended that the Committee consider adding café licences to their workplan for the new municipal y... Noted Open
8 Mar 2023 Highways Maintenance, Capital Programme & Major Development Highways Impacts Update, Scheduling & Planning Report [19.13]That it be recommended that the Committee consider adding an quarterly update on highways and regular updates on the ... Decided Open
8 Mar 2023 Work Plan [20.01]That it be recommended that the Committee consider adding café licences, a quarterly update on highways and regular u... Decided Open
17 Jan 2023 Minutes [17.35]That; i. the minutes of the meeting held on 14 November 2022 be approved and signed by the Chair as a correct record.... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies