Decision Session - Executive Member for Environment and Climate Emergency noted this item on Monday 8 January 2018. Below is the council's own wording, with the papers it was decided on.
( i ) That the following be noted: a) The fire risk mitigation measures in place; b) The key Health & Safety (H&S) risks, and the council’s response to managing and responding to those risks; c) The progress made in embedding the H&S shared service. (ii) That Officers be requested to: a) Ensure that future H&S reports contain statistical analysis of the work of the team, identifying performance against targets; b) Provide a report on the analysis of any changes required to car parks, following the fire in Liverpool Echo Arena on 2 January; c) Keep the City of York Council’s website updated with information on the activities of the Shared Service. Reason: To provide assurance to the Executive Member and York residents that H&S services are appropriately managed and resilient and that the council has proper arrangements in place for managing and responding to H&S risks. ( i ) That the following be noted: a) The fire risk mitigation measures in place; b) The key Health & Safety (H&S) risks, and the council’s response to managing and responding to those risks; c) The progress made in embedding the H&S shared service. (ii) That Officers be requested to: a) Ensure that future H&S reports contain statistical analysis of the work of the team, identifying performance against targets; b) Provide a report on the analysis of any changes required to car parks, following the fire in Liverpool Echo Arena on 2 January; c) Keep the City of York Council’s website updated with information on the activities of the Shared Service. Reason: To provide assurance to the Executive Member and York ... view the full minutes text for item 30.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Environment and Climate Emergency
Summary
1) This report gives an overview of the performance of Health & Safety (H&S) shared service formed by North Yorkshire County Council (NYCC) and City of York Council (CYC) and operating under a partnership agreement. It also provides an update on the ongoing fire mitigation measures in place following the Grenfell Tower fire in London.
Recommendations
2) The Executive Member is asked to:
a) note the fire risk mitigation measures in place and the key H&S risks together with the council’s response to managing and responding to those risks; and b) note the progress made in embedding the H&S shared service.
Reason: To ensure the Executive Member and residents are assured that H&S services are appropriately managed and resilient and the council has proper arrangements in place for managing and responding to H&S risks.
Background and Summary Conclusions
3) The H&S governance arrangements are the main driver for the council’s improvements in health and safety management, and continue to come from the commitment of the Chief Executive, supported by the Corporate Management Team (CMT) and Heads of Service. Integral to this is the work undertaken by colleagues across the council to ensure services are delivered in a safe and healthy manner.
4) This is further improved by elected member oversight of the management of health and safety undertaken by the Portfolio Holder for the Environment, and the Audit and Governance Committee who have requested reports in the past year in order to effectively scrutinise the activities of the council in relation to health and safety.
Fire Safety 5) The Portfolio Holder for the Environment, along with residents and the wider public, has been particularly concerned about the fire safety arrangements across the council following the tragic event, in June 2017, at Grenfell Tower fire in West London which killed 71 residents. This was covered briefly in the report to the Portfolio Holder on 3rd July 2017 and a further more detailed report on 2nd October 2017. 6) The October 2017 report outlined a number of actions to which the council was committed and one of the aims of this report is to provide an update on this activity. This is to reassure the Portfolio Holder and residents as to current status of the risk mitigation arrangements and further planned improvements.
7) The council had already a strong commitment to mitigating the risk from fire, however following the Grenfell tragedy a review was undertaken, across the organisation, of fire prevention and mitigation measures. The main way this was/is done is through fire risk assessments with particular attention to where there is sleeping risk. This review identified that some risk assessments had not been completed for communal areas of residential blocks. This was addressed as a priority and is now complete.
8) In addition this review identified 307 follow up reviews needed of fire risk assessments (FRAs) that were not of the same standard of recent FRAs and were up to three years old. The requirement within the Regulatory Reform (Fire Safety) Order 2005 is a regular review and is not specific, however three years is the CYC recommendation for review of properties of this type. Housing staff have been trained to identify and report any fire issues in the interim time. An appropriate framework contract was identified and the contract is currently being finalised with a suitably qualified contractor with target date (subject to contract) for completion by March 2018.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Environment and Climate Emergency at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.