To note the update report and the evidence presented by the Environment Agency. To recommend that officers prepare a report for Executive to review the strategic development issues relating to the flood defence schemes across the city. Reason: To update the Executive on work done to progress the five year flood plan for York. ( i ) That the update report and the information presented by the Environment Agency be noted. (ii) That Officers be recommended to prepare a report for Executive to review the strategic development issues relating to the flood defence schemes across the city. Reason: To update the Executive on work done to progress the five year flood plan for York.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Environment and Climate Emergency, 4 pages
Summary
1. The flooding in late December 2015 followed an intense period of rainfall across November and December due to the impacts of Storms Desmond and Eva. Record river levels were observed in many river catchments across the north of England. More than 4000 homes and 2000 businesses flooded across Yorkshire with 453 properties and 174 businesses flooded in York.
2. Funding has been allocated to the Environment Agency (EA) following the floods to renew existing and provide new flood defences across the city, £17m has been allocated to the Foss Barrier improvements and £45m to the wider flood defences across the city.
3. An update on progress has been supplied by the EA, this can be seen in Annex 1.
4. The Community Hub on Wellington Row opened before Christmas, the hub gives a base for co-working by EA, CYC and consultants and a drop in location for residents to visit to understand the work that we are developing across the city.
5. Formal consultation events have been held in the Clementhorpe, New Walk and Scarborough Bridge to Ouse Bridge flood cells.
6. CYC have developed and delivered a flood risk workshop for the Yorkshire and Humber Chief Executives Group and will lead on further actions. Recommendations
7. The Executive Member for the Environment is asked to note the update report and the evidence presented by the Environment Agency in the session, feedback is sought from the Executive Member on all content.
Background
8. Following the development and publication of the York Five Year Plan (https://www.gov.uk/government/publications/york-5-year-flood-plan) the EA have developed the Defra Strategic Outline Business Case and financial approvals have been sought and obtained from Defra.
9. The Environment Agency continue to work closely with City of York Council on all aspects of the York Five Year Plan, an update has been provided by the EA at Annex 1.
10. The Wellington Row Community Hub has been leased for the duration of the 5 Year Plan project, the hub is an opportunity for the EA, CYC and consultants to co-locate to ensure a joined up delivery of the works within the programme. The hub is open to the public Monday 10am-4pm, Wednesday 10am-6pm and Thursday 10am-4pm, EA and CYC officers are on hand to respond to questions and provide information on the schemes as they develop.
11. Formal consultation events have been held in the Clementhorpe, New Walk and Scarborough Bridge to Ouse Bridge flood cells. A wide range of attendees have provided detailed feedback on initial suggestions an we are working with individuals and flood groups in the flood cells to further refine options.
12. A flood risk management workshop was delivered by CYC on behalf of the Yorkshire & Humber Chief Executives Group in early December. The group have prioritised its approach to flood risk over the next financial year and CYC are leading on this initiative.
Consultation
13. Public consultation on the York Five Year Plan was held in late November 2016 and quarterly newsletters have been developed by the EA to further inform on progress. Regular formal updates will be provided to the Executive Member for Environment and the Economy & Place Scrutiny Committee at quarterly and six month frequencies respectively. 14. Consultation events have been held in the Clementhorpe, New Walk and Scarborough Bridge to Ouse Bridge flood cells were attended by approximately 150 people, further events are being set up to further include the communities in proposals as they are developed. Two additional meetings have been held by Rachael Maskell MP in the Clementhorpe and New Walk communities, both were attended by EA and CYC officers.
Options
15. The principal options open to the Executive Member for Environment are to comment on and review the work undertaken to date and the future work identified to date and the representations made by the Environment Agency.
Analysis
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Environment and Climate Emergency at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.