City of York Council

Corporate Energy and Environmental Activity Update

Noted Executive 2 papers

Decision Session - Executive Member for Environment and Climate Emergency noted this item on Monday 9 April 2018. Below is the council's own wording, with the papers it was decided on.

Item37

Resolved

( i ) That the progress made in delivering the CRSM, the ongoing alignment with the emerging Leeds City Region Energy Plan, and the plans to refresh the carbon baseline in 2019/20, be noted. Reason: To confirm that the Executive Member is aware of the progress being made and able to scrutinise performance in this area. (ii) That a further report be brought to the Executive Member, providing detailed plans on targets and outcomes for carbon savings and plans for future work in this area, including reference to the work by the Leeds City Region’s Energy Accelerator. Reason: To ensure that the delivery of the council’s plans can be monitored and that York can benefit from the funding awarded to LCR for this work. (iii) That details be provided of how the council can support York Community Energy in schemes to increase renewable power in the city. Reason: To provide clarity to YCE in creating their business case for these schemes. (iv) That clearer reference be made to this work on the council’s website. Reason: So that residents can be fully informed. ( i ) That the progress made in delivering the CRSM, the ongoing alignment with the emerging Leeds City Region Energy Plan, and the plans to refresh the carbon baseline in 2019/20, be noted. Reason: To confirm that the Executive Member is aware of the progress being made and able to scrutinise performance in this area. (ii) That a further report be brought to the Executive Member, providing detailed plans on targets and outcomes for carbon savings and plans for future work in this area, including reference to the work by the Leeds City Region’s Energy Accelerator. Reason: To ensure that the delivery of the council’s plans can be monitored and that York can benefit from the funding awarded to LCR for this work. (iii) That details be provided of how the council can support York Community Energy in schemes to increase renewable power in the city. Reason: To provide clarity to YCE in creating their business case for these schemes. (iv) That clearer reference be made to this work on the council’s website. Reason: So that residents can be fully informed.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Environment and Climate Emergency, 10 pages

Summary

1. The report details progress delivering against the council’s Carbon and Resource Smart Management objectives (CRSM), with particular reference to carbon reduction, energy use and waste reduction.

2. The CRSM is designed to drive delivery towards a low carbon, resource smart ‘One Planet Council’ in line with Council Plan commitments to reduce emissions, be resource efficient and ‘put sustainability at the heart of everything we do’.

Recommendations

3. The Executive Member is asked to note:

I. Progress being made delivering the CRSM and ongoing alignment with the emerging Leeds City Region Energy Plan II. Plans to refresh the carbon baseline in 2019/20

Reason: So that the Executive Member is aware of the progress being made and are able to scrutinise performance in this area.

Headline messages: 4. In 2014/15 the council generated just over 15,0001 tonnes of carbon dioxide across our corporate estate and street lighting. This baseline

1 Excluding gas consumption (CYC has been unable to obtain gas consumption for 2014/15 from british

Gas due to errors on their side) will be fully updated again in 2019/20. The council spent over £5 million on energy, water, transport fuel and waste with over 35 per cent of this spend relating to corporate utilities (gas, electricity, water, waste).

5. Forty one of 91 short term projects in the CRSM have been completed. These projects in the areas of corporate utilities, street lighting and school utilities have contributed to a drop in carbon emissions, although quantifying the precise impact is difficult to quantify and some of the sites have since left the council’s estate. Four medium and nine long term projects as part of the CRSM are expected to contribute to a further decline in carbon emissions.

6. Since 2010/11, the council’s carbon footprint has declined 26% from 25,722 tonnes to 19,003 tonnes in 2016/17. The decline is largely attributed to street lighting refurbishments and changes to building, fleet transport, business travel and waste.

7. CO2 emissions from buildings utilities have declined 19.3% from 16,663,792 kg CO2e to 13,443,779 kg CO2e. This is due to retrofit works such as installation of LED lighting, new energy management systems, improved wall insulation and windows.

8. Electricity consumption has declined significantly. Between 2010/11 and 2016/17 consumption fell 34.3% from 8,755,397 kWh to 5,749,201 kWh. Because of this drop in consumption we are now spending £275,000 a year less than we otherwise would have done.

9. The council will work closely with Leeds City Region to ensure the CRSM is fully aligned to opportunities emerging out of the LCR Energy Review.

10. Total miles travelled by car declined 37.5% from 1,163,857 to 727,513 in 2015/16. Total kilometres travelled by rail declined 7% from 671,957km to 626,663.

11. Corporate waste has declined 20.3%

12. The following details progress within distinct service areas. Housing

Council homes

13. In 2017/2018 thirty nine properties were installed with glazing, loft insulation and cavity wall insulation and 235 doors were replaced improving the heat insulation in each property.

14. From February 2017 – April 2018 a total of 665 gas boilers were replaced and 29 oil heating systems were replaced with air source heat pumps.

15. In the next year there are projects in place to further improve the energy efficiency of homes. A total of £500k will be spent on various efficiency improvements, including upgrades of commercial boilers across some of our key sheltered housing schemes at Glen Lodge, Barstow House and Lincoln Court.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 2 pages Download
PDF
Corporate Energy and Environmental Activity UpdateReport 10 pages DownloadRead as text

At this meeting

Whole meeting
37Corporate Energy and Environmental Activity UpdateThis decision

Who was there

1 of 1 attended
AW
Councillor Andrew WallerCommittee Member, present

More from York Decision Session - Executive Member for Environment and Climate Emergency

All decisions
MeetingDecisionOutcome
20 May 2025 MinutesThat the minutes of the Decision Session held on 29 April 2025 be approved and signed by the Executive Member as a co... Approved Open
20 May 2025 North Yorkshire & York, Local Nature Recovery Strategy (LNRS) consultation draftThat the Executive Member: i. Noted the work that had been undertaken in relation to the North Yorkshire and York Loc... Noted Open
29 Apr 2025 Minutes (10:01am)That the minutes of the Decision Session held on 18 March 2025 be approved and signed by the Executive Member as a co... Approved Open
29 Apr 2025 Public Realm - Service Developments (10:14am)That the Executive Member: i. Considered the two petitions received by the Council and considered if the actions alre... Noted Open
18 Mar 2025 Minutes (10:00am)That the minutes of the Decision Session held on 19 November 2025 be approved and signed by the Executive Member as a... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies