That, on completion of a S106 legal agreement to secure a contribution towards the expansion of teaching and workshop facilities at St Nicholas Fields, delegated authority be given to the Assistant Director, Planning and Public Protection, to approve the application subject to the conditions listed in the report. 2. That, after discussion with the applicant, and approval by the Chair and Vice Chair of this Sub-Committee, an amendment be made to condition No11, in relation to electric vehicle charging points. 3. That a condition be added to retain the tree that is shown to be removed on the approved Reason: The revised scheme for the erection of a three storey building comprising 14 flats would provide homes within a sustainable and accessible location. The site was previously developed land, sustainably located close to the city centre. The principle of encouraging the effective use of land by reusing land that has been previously developed is supported by the NPPF. The development would accord with the NPPF, the Draft Local Plan 2005 and the Emerging Local Plan 2018. On balance, it was considered the proposal complied with the thrust of national and local planning policy.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Date: 7 June 2018 Ward: Heworth Team: Major and Parish: Heworth Planning Panel Commercial Team
Reference: 17/02576/FULM Application at: Thomas Dick Ltd Hallfield Road York YO31 7XQ For: Erection of three storey building comprising of 14 no. residential units with associated parking, external refuse storage and private amenity areas following demolition of existing building By: Helmsley Securities Ltd Application Type: Major Full Application (13 weeks) Target Date: 30 January 2018 Recommendation: Approve subject to Section 106 Agreement
1.0PROPOSAL
1.1Planning permission is sought for a three storey building providing 14 flats (9 x 1 bed and 5 x 2 bed). Vehicle and pedestrian access would be from Hallfield Road.
1.2The site was previously used as a workshop and the buildings have recently been removed. The site slopes down from north east to south west towards the enclosed cycle path which runs along the rear of the site. To the north west, north and north east is residential to the east and south east are industrial uses. To the south is the James Street Caravan Site; further west is James Street, Morrison's supermarket and the Brickworks student accommodation.
1.3There is a linear archaeological monument (Derwent Valley Light Railway) following the cycle track to the south west. The southern corner of the sit is within Flood Zone 3, just under half of the site is within Flood Zone 2, and the north eastern part of the site is Flood Zone 1. The part of the site fronting onto Hallfield Road and within the application site is adopted highway.
1.4Revised plans have been submitted altering the position of the cycle and refuse bin store and altering the position of the residential building,
2.0POLICY CONTEXT
2.1The City of York Draft Local Plan Incorporating the Fourth Set of Changes was approved for Development Management purposes in April 2005: CYGP1 Design CYGP3 Planning against crime CYGP4A Sustainability
Application Reference Number: 17/02576/FULM Item No: 4b CYGP6 Contaminated land CYGP10 Subdivision of gardens and infill devt CYGP13 Planning Obligations CGP15A Development and Flood Risk CYNE1 Trees, woodlands, hedgerows CYHE10 Archaeology CYT4 Cycle parking standards CYH4A Housing Windfalls CYE3B Existing and Proposed Employment Sites CYL1C Provision of New Open Space in Development
2.2The Publication Draft York Local Plan 2018: EC2 Loss of Employment Land H2 Density of Residential Development D1 Placemaking D2 Landscape and Setting D6 Archaeology GI4 Trees and Hedgerows GI6 New Open Space Provision CC2 Sustainable Design and Construction of New Development ENV1 Air Quality ENV3 Land Contamination ENV4 Flood Risk ENV5 Sustainable Drainage T1 Sustainable Access DM1 Infrastructure and Developer Contributions
3.0CONSULTATIONS
INTERNAL CONSULTATIONS
Highway Network Management
3.1No objections, Vehicular and pedestrian access is to be taken from Hallfield Road, modified from that of existing, with some extension to the existing verge. The frontage of the current site has a dropped kerb of which, other than the proposed access will require to be reconstructed to full height kerb and footway. These works may be done under Streetworks Special permission.
3.2Covered secure cycle parking has been secured within a separate building with reasonable access arrangement. The provision is to a level of 1 cycle space per unit. This meets our minimum standards. Local cycle links and routes serve the development well.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.