( i ) That the proposed projects, aimed at enhancing secondary shopping areas in Acomb and Haxby, be approved. (ii) That the remaining budget be used to fund a study which will guide future investment into our secondary shopping areas, with the objectives of enhancing economic growth and strengthening the local retail environment. Reason: To enhance economic growth in these targeted secondary shopping areas. ( i ) That the proposed projects, aimed at enhancing secondary shopping areas in Acomb and Haxby , be approved. (ii) That the remaining budget be used to fund a study which will guide future investment into our secondary shopping areas, with the objectives of enhancing economic growth and strengthening the local retail environment. Reason: To enhance economic growth in these targeted secondary shopping areas. CLLR C Runciman, Executive Member [The meeting started at 2.00 pm and finished at 2.15 pm ].
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Economy and Strategic Planning, 7 pages
Summary
1. The draft Local Plan for York defines two secondary shopping areas in York on Acomb Front Street and The Village, Haxby. A programme to enhance economic growth in these areas was agreed by Executive decision in 2017 and a capital budget of £100,000 was set aside for this purpose.
2. Executive has agreed at its meeting of 21st June 2018 to translate this capital budget into a combined £75k revenue £25k capital budget, to better meet the objectives of the funding.
3. This paper proposes that the £100k is divided equally between immediate measures to improve footfall and the street scene and a study to consider physical improvements to the public realm, designed to make a longer term impact.
4. The allocation of £50,000 to be targeted at projects which promote footfall and improve the street scene in the two secondary shopping areas is matched to a programme of specific projects resulting from local consultation.
5. A proposed brief for external consultants sets out the objectives to be achieved with the remaining budget.
Recommendations 6. That the proposed list of projects aimed at enhancing secondary shopping areas is agreed. 7. That the remaining budget be used to fund a study which will guide future investment into our secondary shopping areas with the objectives of enhancing economic growth and strengthening the local retail environment. Reason: To deliver the Executive decision taken in May 2017 to enhance economic growth in secondary shopping areas.
Background 8. On the 18 May 2017the Executive agreed a Highways Funding Overview Report which included a proposed project ‘Enhancing Economic Growth for Secondary Shopping Areas’. The project was outlined as “A review of the layout of the Acomb and Haxby shopping areas and ways to achieve additional economic growth in these shopping areas will be undertaken and costed interventions proposed, following local consultation. A further report will be taken to the Deputy Leader (Executive Member for Economic Development) to consider proposed interventions.” The total budget was set at £100,000 of capital.
9. Consultation with local residents in Acomb through the Westfield Ward Committee, local traders through the Acomb Alive group, Ward Councillors and the Executive Member has identified a list of potential projects in Acomb Front Street.
10. In Haxby, the current lack of a traders group presents a challenge in how the Council can work with local businesses to improve the business environment. It is proposed to allocate some of the funding to pay for community/place making consultants to work with traders and businesses in the village with the aim of establishing such a traders group.
11. The original project outline – a review of the physical layout of both secondary shopping areas and the development of proposals to enhance growth – will be achieved using half of the original budget. It is proposed that this work will be delivered by specialist consultants who will be procured through open competition.
12. It is proposed that the remaining £50,000 be spent in both Haxby and Acomb on small-scale projects designed to have an immediate impact on these areas, trialling ideas or solutions which might then form part of the longer-term work. This £50,000 comprises £25,000 of revenue and £25,000 of capital. These projects are set out below.
Consultation 13. A public consultation was carried out at the Westfield Ward committee held on the 17th July 2017. Acomb Alive and the Acomb and Westfield Neighbourhood Forum carried out public consultations seeking ideas for improving the secondary shopping areas and are committed to the further development of the project.
Proposed projects – short term measures
14. It is proposed that three strands of work are taken forward.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Economy and Strategic Planning at York and we tell you when its next papers are published, before the meeting rather than after it.
Hull Road Verges Status (16:09)i. That the Planning Authority’s position on the status of the Hull Road verges, located between Nursery Gardens and ...
Quarterly Economic Update (16:09)That the contents of the report are noted. Reason: To support York’s ongoing economic work and monitor how York is pe...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.