Resolved

That the application be approved subject to the conditions and informatives listed in the report, amended conditions 2, 3, 10, 12 and 13 and two additional conditions below: Condition 2: Plans The development hereby permitted shall be carried out in accordance with the following plans:- Drawings 2015-037 - Location Plan 101 Site Plan 102D Floor plans / roof plan - 200D, 201D, 202E, 203D Elevations - 210D, 211D Sections - 103C, 214D Site levels - 802H Landscape layout - 901F Reason: For the avoidance of doubt and to ensure that the development is carried out only as approved by the Local Planning Authority. Condition 3 : CEMP Prior to commencement of the development, a Construction Environmental Management Plan (CEMP) for minimising the creation of noise, vibration and dust during the demolition, site preparation and construction phases of the development shall be submitted to and approved in writing by the Local Planning Authority. All works on site shall be undertaken in accordance with the approved scheme, unless otherwise agreed in writing by the Local Planning Authority. For noise details are required on the types of machinery to be used, including consideration of use of quieter/silenced machinery, use of acoustic barriers, prefabrication off site etc. Where particularly noisy activities are expected to take place then details should be provided on mitigation i.e. by limiting especially noisy events and their duration. Details of any monitoring may also be required, in certain situation, including the location of positions, recording of results and identification of mitigation measures required. For vibration details are required on any activities which may results in excessive vibration, e.g. piling, and how the risk of ... view the full minutes text for item 51.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Planning Main, 17 pages

COMMITTEE REPORT

Date: 19.12.2018 Ward: Guildhall Team: Major and Parish: Guildhall Planning Panel Commercial Team

Reference: 18/01935/FULM Application at: 11 Redeness Street York YO31 7UU For: Erection of a 4-5 storey student accommodation building consisting of 98no. bed spaces with car parking spaces, access, landscaping and associated works. By: Maple Grove Developments Application Type: Major Full Application (13 weeks) Target Date: 24 December 2018 Recommendation: Approve

1.0PROPOSAL

APPLICATION SITE

1.1The application lies within Layerthorpe, in an area which has seen a number of schemes recently for residential development of former industrial and commercial sites. The site currently accommodates a single storey warehouse type building and car parking. There are similar industrial/warehouse buildings along Redeness Street. To the south-east of the site is The Brickworks, a recently completed 4 storey development providing purpose built student accommodation. The land to the immediate north-east is currently subject to an application (17/03027/FULM) for 4/5 storey apartments (permission will be granted when a legal agreement is concluded). The land to the north-west, on the opposite side of Redeness Street, is allocated for housing in the 2018 Publication Draft Local Plan.

1.2In the 2018 Publication Draft Local Plan the city centre boundary has been extended north-east to include this area of Layerthorpe.

PROPOSALS

1.3This application is for student accommodation, providing 98 bedrooms, including fully accessible rooms, and ancillary facilities. The proposed building would be parallel to Redeness Street and predominantly 4 storey in height, with a further floor setback and covering part of the building footprint. There would be landscaped space at the rear and the intent is this development would provide an extension to the Brickworks student accommodation next door.

1.4The existing landowner (who has premises at 10 Redeness Street opposite) would retain 8 car parking spaces within the site; otherwise this would be a car free development. Application Reference Number: 18/01935/FULM Item No: 4b 2.0 POLICY CONTEXT

2.1Development Plan Allocation:

Contaminated Land GMS Constraints:

2.2Relevant Local Plan Policies:

2018 Publication Draft Local Plan

DP2 Sustainable Development DP3 Sustainable Communities DP4 Approach to Development Management SS1 Delivering Sustainable Growth for York EC2 Loss of Employment Land H2 Density of Residential Development H3 Balancing the Housing Market H7 Student Housing D1 Placemaking D2 Landscape and Setting ENV1 Air Quality ENV3 Land Contamination ENV5 Sustainable Drainage

2005 Draft Local Plan

SP6 Location Strategy SP8 Reducing Dependence on the Car GP1 Design GP3 Planning Against Crime GP4a Sustainability GP6 Contaminated Land GP7 Open Space GP9 Landscaping GP15a Development and Flood Risk H4a Housing Windfalls ED10 Student Housing

3.0CONSULTATIONS

DESIGN, CONSERVATION AND SUSTAINABLE DEVELOPMENT

3.1Officers recommend development not exceeding 4-storey in this location.

Application Reference Number: 18/01935/FULM Item No: 4b FLOOD RISK MANAGEMENT TEAM

3.2The drainage layout proposed (in appendix F) is of acceptable design. However, it is disappointing that no consideration has been given to the usage of the amenity open space for accommodating SuDS which could have delivered an environmental and place making enhancement and potentially led to reduced maintenance complexity.

3.3Officers concur with the comments made by Yorkshire Water that although the applicant has provided good information on future impermeable areas and the calculations of required storage they have not adequately considered the pre- development surface water connectivity and officers would support the request for further information in this respect.

PUBLIC PROTECTION

3.4Officers have noted some of the maximum noise levels recorded at the north side of the site and have queried whether there will be appropriate noise attenuation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
York Dance Works, 11 Redeness Street Site PlanPlan 1 pages Download
PDF
York Dance Works, 11 Redeness Street, York [18/01935/FULM]Report 17 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. York Dance Works, 11 Redeness Street, York [18/01935/FULM]This decision
  2. Dispensation of the Six Month Rule for City of York Councillors and Attendance at MeetingsDecided
  3. Attendance of Chair of York@LargeNoted
  4. Attendance of North Yorkshire Fire & Rescue Service and Update on the Fire AuthorityNoted
  5. Attendance of York Business Improvement District (BID) ManagerNoted
  6. Attendance of Chair of York@LargeNoted

More from York Planning Main

All decisions
MeetingDecisionOutcome
5 May 2022 MinutesThat subject to the addition of Cllrs Melly and Ayre to the list of apologies, the minutes of the last meeting held o... Approved Open
7 Apr 2022 Minutesi. That the minutes of the meeting held on 3 February 2022 be approved and then signed by the chair as a correct reco... Approved Open
3 Mar 2022 MinutesThat the minutes of the last meeting held on 3 February 2022 be approved at the next meeting. Approved Open
3 Mar 2022 Lindum Group Limited, York Road, Elvington, York YO41 4EP [21/01709/REMM]That the application be approved subject to the conditions listed in the report and the addition of an informative in... Approved Open
3 Feb 2022 MinutesThat, subject to the amendment stated above, the minutes of the last meeting held on 6 January 2022 be approved and s... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies