CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of York Council

Centre of Excellence for Disabled Children and their Families in York

Approved Executive 1 paper

Decision Session - Executive Member for Children Young People and Education approved this item on Tuesday 18 June 2019. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

( i ) That an increase of £250,000 to the budget, to be funded by a virement from uncommitted resources within the Education Basic Need capital budget, be approved. Reason: To ensure that there is adequate contingency and reduce the risk of costs exceeding the agreed budget in the construction phase. (ii) That authority to appoint a Contractor to carry out the works be delegated to the Director of Children, Education and Communities, subject to the project being deliverable within the available budget. Reason: In order to align the programme with that of the Lincoln Court development and enable a shared contractor to deliver both projects concurrently, thus achieving cost efficiencies. ( i ) That an increase of £250,000 to the budget, to be funded by a virement from uncommitted resources within the Education Basic Need capital budget, be approved. Reason: To ensure that there is adequate contingency and reduce the risk of costs exceeding the agreed budget in the construction phase. (ii) That authority to appoint a Contractor to carry out the works be delegated to the Director of Children, Education and Communities, subject to the project being deliverable within the available budget. Reason: In order to align the programme with that of the Lincoln Court development and enable a shared contractor to deliver both projects concurrently, thus achieving cost efficiencies.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Children Young People and Education, 5 pages

Summary

1. The report will provide an update of the current cost and budget position for the Centre of Excellence for Disabled Children and their families in York.

2. The budget for the new Centre was agreed at City of York Council Executive on January 2018 and revised at the Executive in April 2018.

3. A Contractor has been procured early, via a Pre Contract Service Agreement, to work with existing design team to identify efficiencies, build ability issues and develop a detailed cost submission.

4. Initial cost submission exceeded the agreed budget. A value engineered exercise has been undertaken, in order to reduce cost without compromising the co- produced design and outcomes for disabled children.

5. The costs are now within budget, but further funds are required to ensure there is an adequate client contingency throughout the construction phase. This extension to the budget needs to be agreed in order to ensure the requirements of the external health funding are met and the project aligns with the development of Lincoln Court, therefore delivering shared cost efficiencies. Recommendations

6. That the Executive Member for Children, Young People and Education:

a. Agree an increase to the budget by £250 000 in order to ensure there is adequate contingency, to be funded by a virement from uncommitted resources within the Education Basic Need capital budget.

b. Agree to delegate authority to the Director of Children, Education and Communities, to appoint a Contractor to carry out the works, subject to the project being deliverable within the available budget.

Background

7. The budget which was agreed and then revised at City of York Council Executive is £4.274m. External health funding of £1 073 650 has been secured from a Transforming Care Capital Grant, which has been added to overall budget.

8. Early Contractor Involvement via a Pre Contractor Service Agreement has enabled a preferred Contractor to develop a detailed cost submission for the project. The initial cost submission exceed the agreed budget so a value engineering exercise has been undertaken alongside the existing design team, with consultation with front line practice and parent carers.

9. There were 3 reasons why the initial cost submission was over budget; 1. Lack of competitiveness of quotes within the work packages, 2. Some areas of design were overly complex which increased the construction costs 3. There were some areas that were not factored into the original cost estimate completed by the Independent Cost Consultants recruited by the Council.

10. The value engineering process has been completed with Cost Consultants, Contractor, Architects and Internal Council experts. Areas of design have been simplified, additional more competitive quotes have been obtained for all work packages and areas that were over specified have been reduced. 11. Independent Cost Consultants have worked closely with the Contractor to scrutinise and challenge the cost submission. Each cost has been benchmarked against the external market, in order to ensure the project achieves and demonstrates value for money for the Council.

12. All value engineered changes and proposals have been consulted on and agreed with front line practice and parent / carers. This continues the co production approach of working alongside key stakeholders in every stage of the design and implementation.

13. All agreed value engineered proposals represent non material changes from a planning perspective. All changes will not compromise the outcomes that the new building will deliver for disabled children and their families.

14. A summary of the current cost position against agreed budget is contained within exempt Annex A.

Options and analysis

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Centre of Excellence for Disabled Children and their Families in YorkReport 5 pages DownloadRead as text

At this meeting

Whole meeting
2Exclusion of Press and PublicDecided 3MinutesApproved
5Centre of Excellence for Disabled Children and their Families in YorkThis decision

On this subject at York

Search all
  1. Centre of Excellence for Disabled Children and their Families in YorkThis decision
  2. Developing a Centre of Excellence for Disabled Children and their families in YorkDecided
  3. Developing a Centre of Excellence for Disabled Children and their families in YorkApproved
  4. Developing a Centre of Excellence for Disabled Children and their Families in YorkApproved
  5. Developing a Centre of Excellence for Disabled Children and their FamiliesApproved

More from York Decision Session - Executive Member for Children Young People and Education

All decisions
MeetingDecisionOutcome
15 Mar 2023 Minutes [10.02]That the minutes of the Decision Session held on 7 February 2023 be approved and signed by the Executive Member as a ... Approved Open
15 Mar 2023 School term dates for the 2024/2025 school year [10.04]That approval be given to the term dates as in Annex B to the published report for the 2024-2025 school year. Reason:... Approved Open
7 Feb 2023 Minutes [10.02]That the minutes of the Decision Session held on 10 January 2023 be approved and signed by the Executive Member as a ... Approved Open
7 Feb 2023 Annual Childcare Sufficiency Report [10.04]That the content of the report be noted and agreed before it is shared with elected council members in line with stat... Noted Open
7 Feb 2023 Early Years Strategy [10.22]That the Early Years strategic plan and monitoring of the operational delivery of the strategic plan through the work... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies