Resolved
That the matters set out in the Mazars progress report at Annex A be noted. Reason: To confirm that Members are aware of Mazars’ progress in delivering their responsibilities as external auditors.
Audit and Governance Committee noted this item on Wednesday 4 December 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the matters set out in the Mazars progress report at Annex A be noted. Reason: To confirm that Members are aware of Mazars’ progress in delivering their responsibilities as external auditors.
Audit progress report City of York Council December 2019 CONTENTS 1. Audit progress
2. National publications
This document is to be regarded as confidential by City of York Council. It has been prepared for the sole use of the Audit and Governance Committee. No responsibility is accepted to any other person in respect of the whole or part of its contents. Our written consent must first be obtained before this document, or any part of it, is disclosed to a third party.
2 1. AUDIT PROGRESS Purpose of this report
This report provides the Audit and Governance Committee with an update on progress in delivering our responsibilities as your external auditor.
Audit progress
Our key audit stages are summarised in the diagram shown below.
We are currently at the planning stage. The outcome of this work will be communicated in our Audit Strategy Memorandum. We intend to present the Audit Strategy Memorandum for 2019/20 to the February 2020 Audit Committee.
There are no significant matters arising from our audit work that we are required to report to you at this stage.
• Final review and disclosure checklist of financial • Updating our understanding of the Council statements • Initial opinion and value for money risk • Final partner review assessments • Agreeing content of letter of representation • Development of our audit strategy • Reporting to Audit Committee • Agreement of timetables • Reviewing post balance sheet events • Preliminary analytical procedures • Signing our opinion Completion Planning • Walkthrough testing and system July 20 Nov 19-Feb 20 documentation
Fieldwork Interim • Review of draft financial statements • Controls testing, including general and June-July 20 Jan-April 20 • Reassessment of audit strategy, application IT controls revising as necessary • Early substantive testing of transactions • Delivering our planned audit testing • Early valuations testing • Continuous communication on emerging • Review of the group boundary assessment issues • Other substantive procedures • Clearance meeting
1. Summary 2. Housing Benefits 3. National publications
3 1. AUDIT PROGRESS - CONTINUED 2018/19 Teachers’ Pension Return The Council has engaged Mazars as Reporting Accountant to complete an agreed upon procedures engagement. The proposed fee for this work is £5,000 (plus VAT). At the time of drafting this report we have substantially completed the required procedures set out in the TP05 Reporting Accountant Guidance (dated 12 June 2019) and aim to finalise our agreed upon procedures report by the 29 November 2019 deadline.
2018/19 Housing Benefits subsidy assurance
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CYC Audit Progress Report Dec 19Report | 9 pages | DownloadRead as text |
PDF |
Mazars Audit Update ReportReport | 3 pages | Download |
Follow Audit and Governance Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Oct 2026 | Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna... | Decided | Open |
| 21 Oct 2026 | Minutes & Action Log (17:39)That the minutes of the meeting held on 22 July 2026 be approved and the minutes of the meeting held on 16 September ... | Approved | Open |
| 21 Oct 2026 | Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p... | Noted | Open |
| 21 Oct 2026 | Treasury Management 2026/27 Mid-Year (Quarter 2) report and review of Prudential Indicators (17:54)i. Noted the Treasury Management Mid-Year Report and Review of Prudential Indicators 2026/27 at Annex 1. Reason: That... | Noted | Open |
| 21 Oct 2026 | Suggested Constitutional Changes - Revised Article 13 (18:09)i. Endorsed the adoption of the changes to Article 13 of the Constitution and recommended to Full Council for approva... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.