Scoping Report for Corporate Project Management Approach
AgreedScrutiny2 papers
Customer and Corporate Services Scrutiny Management Committee agreed this item on Monday 9 December 2019. Below is the council's own wording, with the papers it was decided on.
i. That Councillors Fenton and Wann would explore the Quality Assurance process with officers and report back to the Chair and Vice Chair; ii. That Councillor Barnes would explore the Change Management process with officers and report back to the Chair and Vice Chair; iii. That Councillor Crawshaw would explore the Risk Management process with officers and report back to the Committee if required; iv. That a scoping report on York Central be brought to the Committee, for a date to be agreed between Officers and the Chair. Reason: To ensure that the committee was satisfied with how key and project activity have been undertaken.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Customer and Corporate Services Scrutiny Management Committee, 8 pages
Summary
1. The purpose of this report is to further development the discussion around Corporate Project Management with the Customer and Corporate Services Scrutiny Management Committee after the update report in October 2019 on the approach to Project Management across City of York Council.
2. The areas of interest highlighted in the previous meeting were: - How projects are managed; - Risk management; - How projects are challenged; - Lessons learned; - Quality assurance of project management; and - Change control;
Background
3. The council undertakes a complex and wide-ranging portfolio of projects that reaches from major regeneration projects to smaller in service/community based projects. The successful delivery of projects is key to the delivery of change across the Council and the City.
4. The corporate project management framework, All About Projects (AAP), is designed to provide parameters within which project managers can work whilst still fitting in with the overarching operating framework of the Council as guided by the constitution. Areas to Scope
How projects are managed
5. Council projects are managed within the corporate project management AAP framework. This provides tools for project managers to apply project management methodology proportionate to the size of the project (this is determined at the beginning of the project through the project assessment matrix).
6. The AAP framework covers the lifecycle of the project starting with Discovery, which is about identifying problems, researching and generating ideas that can be taken forward as a project. This is an important stage because it encourages reflection and challenge on current practices and culture in the context of political, environmental, social, technological, legal, financial and economic landscape and focuses on a human centered design (HCD) approach to solving the problem. This approach ensures that, as the project develops, the attention is always on the person/people who would benefit from the project and they play a key role in developing products within the project.
7. This process is designed to be iterative, with prototyping, to ensure that all avenues have been investigated and the idea is ready to be launched as a project. The real benefit of this phase is that the project is well thought out and developed before initiation, which can lead to saved time, cost and a much reduced chance of project failure.
8. After the Discovery phase, when an idea has been identified to take forward as a project, the basics of the project are developed in order to receive a mandate to proceed with the development of a project. The work then starts on the development of the business case. In the AAP framework this happens in three stages:
i) The Strategic Outline Case (SOC);
The high level financials, outcomes, risks and options are developed;
ii) The Outline Business Case (OBC);
A further level of detail is applied in terms of costs, benefits, risks and a short list of options are developed with a recommended option. The recommended option is likely to include the selection of a supplier if there is a procurement process;
iii) The Full Business Case (FBC);
Once the preferred option is selected, the final detail is applied and, where appropriate a procurement process is completed to attain cost certainty and contracts are signed to enable the start to the delivery;
9. These stages are consistent with Treasury green book guidance on business case development (and procurement) and reflects how organisations like West Yorkshire Combined Authority (WYCA) operate their business case development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Customer and Corporate Services Scrutiny Management Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.