Decision Session - Executive Member for Economy and Strategic Planning noted this item on Monday 20 January 2020. Below is the council's own wording, with the papers it was decided on.
i. That the contents of the report be noted. ii. That a report on the draft Planning Enforcement Plan be brought to a future decision session in autumn 2020, following a consultation with all Members. Reason: So that all Members are given sufficient opportunity to feed into the Planning Enforcement Plan. i. That the contents of the report be noted. ii. That a report on the draft Planning Enforcement Plan be brought to a future decision session in autumn 2020, following a consultation with all Members. Reason: So that all Members are given sufficient opportunity to feed into the Planning Enforcement Plan.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Economy and Strategic Planning
Recommendation
2. The Executive Member is asked to note the contents of the report.
Background 3. A breach of planning control is defined in section 171A of the Town and Country Planning Act 1990 as:
The carrying out of development without the required planning permission; or
Failing to comply with any condition or limitation subject to which planning permission has been granted.
Any contravention of the limitations on, or conditions belonging to, permitted development rights, under the Town and Country Planning (General Permitted Development) (England) Order 2015, constitutes a breach of planning control against which enforcement action may be taken.
4. The National Planning Policy Framework para 58 deals with planning enforcement and states that “Effective enforcement is important to maintain public confidence in the planning system.” 5. The City of York Council Planning Enforcement team responds to and investigates complaints about breaches of planning control. Planning enforcement complaints can be extremely complex and time consuming. The investigation process can involve Enforcement Officers working alongside both colleagues across the Planning Service and other departments within the Council and externally. This complexity serves to add to the time taken to resolve an issue. Some cases are best resolved quickly through working in partnership with other agencies and departments.
6. In order to make most effective use of the Councils resources, the cases are dealt with in order of priority with the greatest urgency given to cases causing the greatest levels of harm or where such harm would be irreversible
7. The Council’s Enforcement Team have a number of ways of enforcing planning breaches and these include:
•Enforcement Notice •Planning Enforcement Order
•Stop Notice
•Temporary Stop Notice •Breach of Condition Notice
* Section 215 Notice (untidy land) 8. The actions outlined above can be used by the Local Planning Authority (LPA) in order to rectify planning breaches. The report below outlined the number of Enforcement notices and section 215 notices that have been served. 9. Enforcement notices clearly outline what in the LPA view constitutes the breach of planning control and what steps the local planning authority require to be taken or what activities are required to cease to remedy the breach.
10. Section 215 notices provides a LPA with the power, in certain circumstances, to take steps requiring land to be cleaned up when its condition adversely affects the amenity of the area. If it appears that the amenity of part of their area is being adversely affected by the condition of neighbouring land and buildings, they may serve a notice on the owner requiring that the situation be remedied. These notices set out the steps that need to be taken, and the time within which they must be carried out 11. In terms of enforcement cases received by the service Members receive updates on the number of outstanding enforcement cases on a quarterly basis through a report which is referred to the Planning Sub Committee. This has occurred since July 1998.
12. A list of enforcement cases for their Ward are also sent to each Councillor by email as agreed by the Chair of the Planning Committee. This list also contains a synopsis of progress made on each case.
Current Position 13. During 2019, 592 new planning enforcement investigation cases were received and 712 cases were closed. A total of 467 investigations remain open. 13 Enforcement Notices were served.
14. By comparison: In 2015 - 483 cases opened 352 closed 2 Enforcement Notices were served
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Economy and Strategic Planning at York and we tell you when its next papers are published, before the meeting rather than after it.
Hull Road Verges Status (16:09)i. That the Planning Authority’s position on the status of the Hull Road verges, located between Nursery Gardens and ...
Quarterly Economic Update (16:09)That the contents of the report are noted. Reason: To support York’s ongoing economic work and monitor how York is pe...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.