Resolved
That the application be approved, subject to the conditions listed in the report. Reasons: i. The application site is located within the general extent of the York Green Belt and serves a number of Green Belt purposes. As such it falls to be considered under paragraph 143 of the NPPF which states that inappropriate development, is by definition, harmful to the Green Belt and should not be approved except in very special circumstances. Very special circumstances will not exist unless the potential harm to the Green Belt by reason of inappropriateness and any other harm are clearly outweighed by other considerations. National planning policy dictates that substantial weight should be given to any harm to the Green Belt. ii. National planning policy (para. 145) states that the construction of new building in the Green Belt should be regarded as inappropriate unless it falls within one of the exceptions to this outlined in paragraph 145 b of the NPPF. The proposal has been assessed to represent engineering operations as outlined in paragraph 146 (b) of the NPPF however, the development is inappropriate development because, for the reasons outlined above in this report, it fails to preserve the openness of the Green Belt and conflicts withthe purposes of including land within the Green Belt, namely parts C and D of policy 134 of the NPPF (assisting in safeguarding the countryside from encroachment and preserving the setting and special character of historic towns) , contrary to paragraph 145b of the NPPF. iii. The proposal, providing flood defence assets, cannot be located in land at lower risk of flooding as the level of protection would not be achieved. A sequential and exception test has been applied, and as the development is assessed as ‘Water Compatible’, this is appropriate development within any of the Flood Zones. iv. The application will lead to less than substantial harm to the significance on archaeological features and deposits which are situated within the Central Area of Archaeological Importance. Public benefits are considered to justify this harm. There are limited impacts in respect to landscape setting, ecology and any impacts can be mitigated by condition. v. This area has ... view the full minutes text for item 46a