Customer and Corporate Services Scrutiny Management Committee approved this item on Monday 5 October 2020. Below is the council's own wording, with the papers it was decided on.
That the minutes of the meeting held at 5:30pm on 5 October 2020 be approved as a correct record; subject to the following amendments: i. That minute 27. that the minutes of the meeting held at 2:00pm on 10 August 2020. Be approved as a correct record, be amended to 5:30pm on 10 August 2020 be approved as a correct record. ii. That minute 29. discussions took place regarding the for the council review project governance arrangements with the partnership and Members were advised by the Corporate Director Economy and Place that the Terms of Reference would be part of the oversight for the York Central Partnership. Be amended to read, discussions took place regarding the council review of project governance arrangements with the partnership and Members were advised by the Corporate Director Economy and Place that the Terms of Reference would be part of the oversight for the York Central Partnership. iii. That minute 29. Members considered the options in detail and Cllr Pearson proposed Option 5. This was seconded by the Chair and following a unanimous vote was carried. Be amended to read, Members considered the options in detail and Cllr Hollyer proposed Option 5. This was seconded by the Chair and following a unanimous vote was carried. The Chair then noted the view expressed by several Members of the Committee that when options relating to the car park are considered in due course, this should not be undertaken in isolation. He accepted that whilst there may be revenue implications associated with not proceeding with a replacement car park, this should not in and of itself be a reason to proceed as there are other costs associated with cars coming into the city centre that will need to be fully considered and taken into account.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Customer and Corporate Services Scrutiny Management Committee, 4 pages
City Of York Council Committee Minutes
Meeting Customer and Corporate Services Scrutiny Management Committee Date 7 September 2020 Present Councillors Crawshaw (Chair), Fenton (Vice- Chair), S Barnes, Hunter, Hollyer, Rowley, Musson, Pearson and Mason
26. DECLARATIONS OF INTEREST
Members were asked to declare, at this point in the meeting, any personal interests, not included on the Register of Interests, or any prejudicial or disclosable pecuniary interests they may have in respect of business on the agenda. None were declared.
27. MINUTES
Resolved: That the minutes of the meeting held at 2:00pm on 10 August 2020 be approved as a correct record and be signed by the Chair at a later date.
Further to the minutes, however, where there was an apparent lack of reference to written reports being considered at meetings, he reminded Members of the importance of the statutory function of scrutiny committees and the need for such reports to enable Members to adequately fulfil their role. As a result, he proposed that he and Cllr Fenton (Vice Chair) seek a meeting with the Leader to discuss commitment to scrutiny. This was seconded by Cllr Rowley and following a unanimous vote in favour it was:
Resolved: That the Committee explicitly support Councillors Crawshaw and Fenton as Chair & Vice Chair in seeking a meeting with the Executive Leader, Cllr Aspden, such that they may convey Committee’s frustration at the lack of reports in advance of meetings and request that sufficient resources be made available to ensure that the Scrutiny function is appropriately supported to carry out its statutory role.
28. PUBLIC PARTICIPATION
It was reported that there had been no registrations to speak under the Council’s Public Participation Scheme.
29. KEY MAJOR PROJECTS UPDATE
The Head of Corporate Finance & Commercial Procurement gave an update on the review methodology for the 5 year approved capital programme from 2020/21 – 2024/25 totalling £600.615m, which had been has been reviewed and split into four categories: major projects, medium/smaller projects, routine maintenance/rolling programmes and projects nearing completion or substantially complete except for retention payments. It was noted that schemes in categories 1 and 2 with a value of over £1m were reviewed.
The evaluation methodology for major projects had been agreed in consultation with Executive Members in line with COVID Emergency decision making powers and each review considered the Strategic Business case, the financial Business Case, delivery and an assessment of future options when deciding whether to continue, pause, review or stop the projects.
Members were asked to consider the review process for Guildhall and York Central and their input was sought on the review of Castle Gateway to feed into Executive decision making at the Executive meeting on 1 October 2020.
Guildhall The Assistant Director Regeneration & Asset Management outlined the strategic review, financial business case, status review, and progress review of the Guildhall project.
Following her update she was asked and confirmed that: Soft research on the office market had been undertaken with agents for restaurants and commercial contracts for office space. This indicated that a more agile and flexible approach to office space may need to be taken. The information on the contracts for a third party managing the space were commercially sensitive and would be included in the report to Executive. Officers were in the process of substantiating the risk associated with the restaurant space. There would be a revised financial protection if there was no interest in the restaurant.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Customer and Corporate Services Scrutiny Management Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.