Decision Session - Executive Member for Housing and Safer Neighbourhoods noted this item on Thursday 18 March 2021. Below is the council's own wording, with the papers it was decided on.
i) That the successful application to BEIS for investment under their Local Authority Delivery 1B scheme, be noted and the grant allocation approach outlined in the report, be supported. ii) That the submission of a grant application under the Local Authority Delivery 2 scheme be supported and that the utilisation of this funding to support, 1) Council Housing Energy Retrofit Programme Phase 1 works as approved by Executive in December 2020; 2) an expansion of room in the roof and other insulation works being delivered as part of LAD1B project; and 3) to install solar PV on council homes utilising some of the remaining funds within the £1m allocated budget, alongside LAD2 funding, be approved. That delegated authority to the Executive Member of Housing and Safer Neighbourhoods to approve any reallocation of this grant funding in line with the capacity of the supply chain and the grant funding terms, be agreed. iii) That the scope of the retrofit strategy be approved and the timescales and resource implications for its completion be noted. Reason: To improve the energy performance of some of our poorer performing homes to both reduce residents’ energy bills and to support our ambition of York being carbon neutral by 2030.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Housing and Safer Neighbourhoods, 14 pages
Summary
1. Heating, lighting and powering our homes generates around a third of the total carbon emissions in York. In order to tackle fuel poverty and to meet the ambition of York being carbon neutral by 2030, it is imperative that significant work is undertaken to both reduce energy demand as well as switching to greener forms of energy in our homes. As a council, we own around 7500 homes with a third of these achieving an EPC rating of D or below. In the city as a whole, over 60% of homes may be an EPC D rating or worse.
2. In December 2020, Executive supported the establishment of the Housing Energy Retrofit Programme to start to address this challenge. The report set out an approach to delivering improvements to around 60 energy inefficient council houses, utilising £1m of allocated budget from the Housing Revenue Account (HRA) to bring these homes up to an EPC C rating. This work is to be delivered through a fabric first approach with a roadmap to guide further improvement works in the future. As well as improving the performance of these homes, this work will provide valuable lessons to support future works, boost the local supply chain, upskill tradespeople and housing staff, and support the green economy of the city.
3. Alongside the delivery of retrofit works, the December report committed to the delivery of a new strategy. This strategy will develop a deeper understanding of the extent of the retrofit challenge in the city and bring forward proposed solutions, both for council housing and within the private sector.
4. This update report outlines the level of progress on the Housing Energy Retrofit Programme since the December Executive approval. In summary, this progress consists of: securing grant funding from the Department of Business, Energy and Industrial Strategy (BEIS), completion of an application for a second round of BEIS grant funding, the advancement of plans to deliver the first phase of the council house retrofit works, and the development of a scope and timeline for the delivery of a retrofit strategy.
Recommendations 5. The Executive Member is asked to approve the following recommendations:
i) Note the successful application to BEIS for investment under their Local Authority Delivery 1B scheme and to support the grant allocation approach outlined in this report.
ii) Support the submission of a grant application under the Local Authority Delivery 2 scheme including the grant allocation and works delivery approach.
iii) Approve the scope of the retrofit strategy and note the timescales and resource implications for its completion
Reason: To improve the energy performance of some of our poorer performing homes to both reduce residents’ energy bills and to support our ambition of York being carbon neutral by 2030.
Background
6. On the 15 December 2020, Executive received a paper outlining the issues and challenges for landlords, homeowners and tenants in decarbonising their homes. It set out the need for investment in energy efficiency works, skills and training, and supply chain development to deliver carbon neutrality. A series of decisions regarding both strategic development and investment opportunities were made.
7. The scale of challenge is significant. In 2050, around 80% of all homes lived in will have been built before 2021. At present, it is considered that around 60% of these homes have an EPC rating of D or below. These energy inefficient homes contribute significantly to the carbon emissions of the city.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Housing and Safer Neighbourhoods at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.