i. Noted the finance and performance information; ii. Requested that officers share additional detail on the ability to use solar technology to power street lighting; iii. Requested that officers provide additional detail regarding how much would need to be spent in year to prevent the highways maintenance backlog from increasing. Reason: to ensure expenditure is kept within the approved budget.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Economy, Place, Access and Transport Scrutiny Committee, 13 pages
Meeting: Economy, Place, Access and Transport Scrutiny Committee Meeting date: 24/10/2023 Report of: Patrick Looker Head of Service Finance Portfolio of Cllr. P. Kilbane – Deputy Leader of the Council and Executive Member for Economy and Transport Cllrs J. Kent and K Ravilious – Executive Members for Environment and Climate Change Cllr M. Pavlovic – Executive Member for Housing Planning and Safer Communities Cllr K. Lomas – Executive Member for Finance, Performance, Major Projects, Human Rights, Equality and Inclusion
2023/24 Finance and Performance Monitor 1 Subject of Report 1. This report sets out the projected 2023/24 financial position and the performance position for the period covering 1 April 2023 to 30 June 2023, together with an overview of any emerging issues. This is the first report of the financial year and assesses performance against budgets, including progress in delivering the Council’s savings programme.
2. This report outlines the Council’s serious financial position with a forecast overspend for 2023/24 of £11.4m. This is a significant overspend that is of serious concern and it is very clear that the Council cannot afford to keep spending at this level. The general reserve is £6.9m and, whilst we have other earmarked reserves that we could call on if required, continued spending at this level would quickly see the Council exhaust its reserves.
Page 1 of 13 3. Given the scale of the forecast overspend, immediate action is needed to bring spending down to an affordable level, both within the current financial year and over the next 4 years, to safeguard the Council’s financial resilience and stability.
4. This report outlines the actions we need to take and identifies areas for further work. If we take immediate action and make these difficult decisions now, this will ensure the future financial stability of the Council and that we can continue to provide services for our residents. It is vital that the mitigations are delivered, and the forecast overspend is reduced.
Benefits and Challenges 5. This report is mainly to note the latest financial projections and current performance. The main challenge is delivering on agreed savings whilst also identifying further reductions in expenditure. The main benefit of approving the recommendations will be the ongoing financial stability of the Council.
Policy Basis for Decision
6. This report is mainly to note the latest financial projections and current performance. The ongoing financial resilience and stability of the Council will be essential to ensuring that Council priorities can continue to be achieved.
Financial Strategy Implications
7. This report sets out the projected financial position and identifies a range of actions that are necessary in order to reduce expenditure, both within the current financial year and over the next 4 years to safeguard the Council’s financial resilience and stability.
Recommendation and Reasons 8. The Committee is asked to: Note the finance and performance information.
Reason: to ensure expenditure is kept within the approved budget.
Page 2 of 13 Background
Financial Summary and Mitigation Strategy
9. The current forecast is that there will be an overspend of £11.4m. This is despite action being taken by managers across the Council to try and reduce expenditure. If the Council continues to spend at the current level, and no action is taken, then we will continue to overspend and will exhaust our reserves and any other available funding. The current level of expenditure is unaffordable and therefore we must take immediate action to reduce expenditure.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Economy, Place, Access and Transport Scrutiny Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.