St Pauls Nursery School, 12 St Pauls Square, York, YO24 4BD [23/01129/LBC] (6.23 pm)

Approved Planning 3 papers

Planning Committee B approved this item on Wednesday 15 November 2023. Below is the council's own wording, with the papers it was decided on.

Item45

Resolved

That the application be approved. Reason: The proposal envisages the replacement of the existing side extension with a purpose-built extension using a more modern idiom to provide purpose-built provision for pupils with autism. The design has been amended since submission to address Conservation concerns. At the same time, it is proposed to construct fire escape provision from the upper floor kitchen and pupil dining area into the rear play area to enable the site to comply with modern safety standards. It is felt that the proposal would give rise to less than substantial harm to the significance of the Listed Building but that that harm would be balanced by the public benefit of the provision of purpose-built provision for younger children with autism otherwise no available in the wider City together with the removal of the existing detractor building. Having special regard to the desirability of preserving listed buildings and their setting in line with section 66(1) of the Planning (Listed Buildings and Conservation Areas) Act 1990 and giving considerable importance and weight to the identified harm, it is considered that the proposal would have an acceptable effect on th is designated heritage asset. Approval is therefore recommended.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Planning Committee B, 9 pages

COMMITTEE REPORT

Date: 15 November 2023 Ward: Holgate Team: West Area Parish: Holgate Planning Panel Reference: 23/01129/LBC Application at: St Pauls Nursery School 12 St Pauls Square York YO24 4BD For: Internal and external alterations including erection of annex following demolition of existing building, access alterations to front and internal alterations to nursery building. By: City Of York Council Application Type: Listed Building Consent Target Date: 17 November 2023 Recommendation: Approve

1.0PROPOSAL

1.1St Paul’s Nursery, St Paul’s Square comprises a Grade II Listed brick built terraced property dating to the early 19th Century set around a tree lined square to the west of the City Centre. Planning permission and a parallel planning application (ref: 23/01114/FUL) are sought for the demolition of an existing single storey block work extension and the erection of a replacement single storey annex with a series of internal alterations, a reconfigured access and the provision of a rear fire escape stair serving the kitchen and dining area. The new provision is designed to provide specialist accommodation for children with autism.

1.2The proposal has been amended since submission to address Conservation concerns and also to clearly reference the proposed construction site compound.

2.0POLICY CONTEXT

2.1Draft City of York Local Plan (2018) Policies:

- D4 Conservation Areas - D5 Listed Buildings

3.0CONSULTATIONS

INTERNAL

Application Reference Number: 23/01129/LBC Item No: 4d Design Conservation Sustainable Development (Conservation)

3.1Any comments will be reported verbally.

EXTERNAL

Historic England

3.2Make no comments in respect of the proposal, deferring to the Authority’s Conservation Officer.

Holgate Planning Panel

3.3No comments received.

National Amenity Bodies

3.4No comments received.

York Civic Trust

3.5Objected to the proposal prior to its amendment on the grounds that:

- That the internal alterations are uninspired and magnify the pre-existing harm from earlier alterations - The ground floor works would result in a loss of legibility and result in a further loss of floor plan and historic fabric. - The location of the extension would harm the legibility of the application site as the location of the former side garden and should be located to the rear of the site where the setting of the building has been effectively compromised. The play area can then be relocated to the site frontage. - The fire escape extension and associated route across the rear extension roof would also harm the setting of the host building.

4.0REPRESENTATIONS

4.1Seven letters of objection have been received raising the following issues below. A number of other issues have been raised which are not of relevance in consideration of the Listed Building Consent application, those are considered in the committee report for the planning application: - Concern that the proposed extension should have a consistent design treatment. - Objection to the contemporary design metaphor including the use of a glass balustrade and the removal of the internal dumb waiter.

Application Reference Number: 23/01129/LBC Item No: 4d 5.0 APPRAISAL

KEY CONSIDERATIONS:

5.1Preserving the Listed Building or any Special Features of Historical or Architectural Interest it Possesses.

NATIONAL PLANNING POLICY FRAMEWORK

5.2NPPF sets out the government's planning policies for England and how these are expected to be applied. Its planning policies are material to the determination of planning applications. The NPPF sets out that the purpose of the planning system is to contribute to the achievement of sustainable development (Paragraph 7). To achieve sustainable development, the planning system has three overarching objectives; economic, social and environmental objectives, which are interdependent and need to be pursued in mutually supportive ways (paragraph 8).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
St Pauls Nursery School, 12 St Pauls Square, York, YO24 4BD [23/01129/LBC] (6.23 pm)Report 9 pages DownloadRead as text
PDF
St Pauls Nursery School, 12 St Pauls Square, York, YO24 4BD [23/01129/LBC] PlanReport 1 pages Download
PDF
View item 45. as HTML 60 KBReport 60 KB Copy on its way

At this meeting

Whole meeting

On this subject at York

Search all
  1. St Pauls Nursery School, 12 St Pauls Square, York, YO24 4BD [23/01129/LBC] (6.23 pm)This decision
  2. St Pauls Nursery School, 12 St Pauls Square, York, YO24 4BD [23/01114/GRG3] (6.23 pm)Approved

More from York Planning Committee B

All decisions
MeetingDecisionOutcome
9 Sep 2025 Minutes (4.33 pm)That the minutes of the last meeting held on 15 July 2025 were approved as a correct record, subject to a correction ... Approved Open
9 Sep 2025 St Olaves School, Queen Annes Road, York, YO30 7AA [24/00703/FUL] (4.35 pm)That the application be approved, subject to the amendments outlined above. Reason: The proposal would provide sport ... Approved Open
9 Sep 2025 Hemplands Kids Club, Burnholme Youth Centre, Bad Bargain Lane, York, YO31 0LW [25/01168/GRG3] (5.15 pm)That the application be approved in principle, with the decision delegated to the Development Manager, in consultatio... Approved Open
15 Jul 2025 Minutes (5:06pm)That the minutes of the last meeting held on 12 June 2025 were approved as a correct record. Approved Open
15 Jul 2025 RSPCA, Landing Lane, York, YO26 4RH [24/00919/FULM] (7:10pm)That the application be approved. Reason: The property lies within Flood Zone 3 but comprises a less vulnerable use a... Approved Open