(i) That the progress made to date be noted. (ii) That communication to all suppliers be issued as soon as possible. (iii) That officers liaise with the Council Management Team and Executive Member for Finance to consider the barriers and ways to improve. (iv) That the Chair and Principal Accountant consider when an appropriate time would be for the committee to receive an updated report. Reason: To gain assurance that the council was taking proper action to respond to the agreed audit actions and improvements to purchasing processes are being made where necessary.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting: Audit & Governance Meeting date: 28/02/2024 Report of: Debbie Mitchell, Chief Finance Officer Portfolio of: Executive Member for Finance, Performance & Major Projects
Audit and Governance Committee Report: Update on Action Plan - No Purchase Order No Pay Subject of Report 1. The report provides an update to members of Audit & Governance Committee about the ongoing review of No Purchase Order No Pay processes. It details the progress made since the report to members in November 2023.
2. Progress is being made against all the agreed actions and an improvement in invoice data in terms of retrospective orders being placed has been seen.
Policy Basis 3. The report and the recommendation support the Financial Strategy of the Council, by providing assurance to Members that financial regulations are followed, orders are raised with the proper authorisation and budgetary control is adequate.
Recommendation and Reasons 4. Audit & Governance are asked to note and comment on the progress to date.
Reason: To gain assurance that the Council is taking proper action to respond to the agreed audit actions and improvements to purchasing processes are being made where necessary. Background 5. Recent internal audits have found control issues from retrospective purchase orders (POs) being raised. Several audit recommendations have been made and an action plan was presented to members of this committee in November 2023 as a response to these actions.
6. The Creditors internal audit report issued by Veritau in March 2023 identified that the retrospective raising of purchase order continues to take place; an issue that they had identified in the previous audit in 2021/22. The most recent audit found that 55% of invoices in 2022 were dated on or before the PO date.
7. The action plan focussed on 4 areas to mirror the recommendations of the internal audit reports: Review of policy and processes Training Role of Business Support Exemptions to the policy
8. The action plan was discussed by members of Audit & Governance committee, and it was agreed that a progress report would be provided at a future meeting.
Progress to date
9. Since November, a significant amount of work has been undertaken to analyse the issues across Purchase to Pay. This has involved Business Support and Procurement colleagues as well as Finance. A large proportion of the work has been fact-finding in nature, to understand why different users and departments are raising purchase orders retrospectively. As such there has been no direct effect on the statistical data. The issues vary across departments and there are not obvious ‘quick fixes’ in most cases. A common theme that has been established is the need for training to improve the efficiency of the processes and adherence to the policy.
10. We have also engaged with other local authorities to get an insight into how they have made improvements to their purchasing processes and will be making use of their experience moving forward.
11. The action plan has been updated and is provided at Annex A. Progress against each area is described in the following paragraphs.
Review of the Policy
12. In December 2023, the Council implemented spend controls in order to limit the extent of the in-year overspend. As a result, the number of POs raised across the Council has significantly reduced, although not directly linked to the this review it does mean that spend is being scrutinised more closely and it is expected that users of the purchasing system will be more aware of commitments being made.
13. In terms of progress against the actions; firstly, the policy remains under review by Finance, Business Support and Procurement. The benefits of the policy still apply today, however adherence to it is not consistent. A number of services have been reviewed so far and each one has differing issues. The solutions explored include:
Training to ensure adherence Use of call off orders Use of emergency orders Applying an exemption to the policy
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.