Decision Report: Acomb Front Street - Phase 2 Design and Costings (10:08am)

Approved Executive 8 papers

Decision Session - Executive Member for Economy and Culture approved this item on Tuesday 24 September 2024. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

To approve the designs and costings, set out in the Decision Report, for key elements of the Acomb Front Street Phase 2 and instruct officers to commence construction work and undertake implementation of the scheme. Reason: In July 2024, Executive delegated authority for this decision to the Executive Member for Economy and Culture, recognising the tight timescales involved in UKSPF funding and to enable the scheme design and costings to be finalised in time for a planned start on site by the end of September 2024. The designs presented in this report have been informed by extensive public engagement and have been developed and prioritised in line with the feedback received. To delegate authority to approve the remaining elements of the Phase 2 scheme to the Interim Director for City Development; noting that work is still ongoing to finalise some elements (including public artwork and future approach to markets). Reason: Due to tight funding timescales, some elements of Phase 2 still require further officer work in order to finalise design and/or costings. Delegated authority to the Interim Director for City Development will allow these elements to be finalised and implemented without the need for a further written report. To approve the making of the Traffic Regulation Order (TRO) for the proposed new disabled parking area at York Road layby and 20mph speed restriction in main shopping area of Front Street noting that no representations were received during the TRO consultation period. Reason: Authority for this decision was delegated by Executive in July 2024 to the Executive Member for Economy and Culture (in consultation with Executive Member for Transport). No representations were received during the statutory TRO consultation period; therefore, it is recommended to proceed with making of the order. Consultation has been undertaken with the Executive Member for Transport prior to this decision being formally made. i . To approve the designs and costings, set out in the Decision Report, for key elements of the Acomb Front Street Phase 2 and instruct officers to commence construction work and undertake implementation of the scheme. Reason: In July 2024, Executive delegated authority for this decision to the Executive Member for Economy and Culture, recognising the tight timescales involved in UKSPF funding and to enable the scheme design and costings to be finalised in time for a planned start on site by the end of September 2024. The designs presented in this report have been informed by extensive public engagement and have been developed and prioritised in line with the feedback received. ii. To delegate authority to approve the remaining elements of the Phase 2 scheme to the Interim Director for City Development; noting that work is still ... view the full minutes text for item 3.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Economy and Culture, 1 pages

Good Morning from the ‘What a Load of Bollards’ campaign group and thanks for reading this out.

Yes, we’re still here and we still believe, passionately, that the best use of this enormous amount of time and money would have been simply levelling Front Street – not literally, you know what we mean ! – removing the cars that never needed to be there in the first place and letting the lovely things people asked for evolve naturally as things tend to do when there is plenty of space and an empowered community. We still feel that filling it up with unnecessary clutter is a backward step and those bollards!…… Almost 50 will remain as a constant reminder of that dreadful day when Acomb woke to find itself surrounded by steel and became a laughing stock, making it onto the hallowed pages of the Sun newspaper and even Wikipedia where our entry still reads: “Acomb is famous in York for having a very high concentration of street bollards. These were installed in an upgrade in 2023 and have since prompted great controversy among local residents due to their vast numbers and variance from the original proposed plans for the area.” We went to extremes to fight back. Trying to walk up the stairs to a council meeting encased entirely in cardboard, dressed as a giant bollard is no mean feat I can tell you – but we found allies. And realised pretty quickly that most of the members of what was then the challenging party – you people – agreed with us. Then we came up against the bureaucratic solidity of the highways and planning department. We know they tried hard to be brave and think outside what is a pretty impenetrable box. We couldn’t get through this. Small compromises were made but to us, they remain placatory and lacking in long term sustainable vision. If our hopes that one day sense will prevail and this little street does become pedestrianised, they will have to remove all the expensive signs and humps and benches, yes and those ghastly 50 bollards, and the 500k, twice spent, will once again, largely have been a waste. But here we are. While a “feasibility study” falls so far from what we wanted and feels as though it is possibly just a gesture to get us to back away – where would the money come from anyway? – we realise this is the end of the line for this stage of Front Street’s chequered evolution. We leave you with this (for now!):

1: Please share dates for the results of the feasibility study and intentions resulting from these. Can you assure us that councillors support pedestrianisation in principle and will be pushing for meaningful progress with this? That it won’t fade away and leave us stuck with our cluttered street where local people still have to dodge round traffic - but now have signposts and gateways and more bins and benches to negotiate their wheelchairs and prams around? And 50 bollards… 2: Anything you can do to reduce, deter or dissuade those cars would be wonderful. We asked that parking is entirely disabled-only. Please think carefully on that one, it could be a speedy solution to the problem that started all this: parking on the pavement. 3: Those murals. Please can you promise you will commission one of the many very talented Acomb-based artists and not buy in from somewhere else. This goes for all the other fancy trimmings. Think creatively about who installs these and which materials they use.

4: Our thanks to those who agreed with us and listened. We take some satisfaction from hearing that we have taught the council a few things and if nothing else, ensured that while the opinions of local people can be loud and bothersome, they really are where the process of change must begin – and end.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2. Annex A: Phase 2 CostingsAppendix 1 pages Download
PDF
3. Annex B: Equalities Impact AssessmentAppendix 27 pages Download
PDF
4. Annex C- You Said We didAppendix 2 pages Download
PDF
5. Annex D: Wayfinding, seating and Planter visualsAppendix 6 pages Download
PDF
6. Annex E: General Arrangement PlansAppendix 3 pages Download
PDF
7. Supplement 1: Written Submission Item 4.supplement 1: written submissionReport 1 pages DownloadRead as text
PDF
Decision Report: Acomb Front Street: Phase 2 Design and Costings (10:08am)Decisions 26 pages Download
PDF
View as HTML (3./7) 7 KBReport 7 KB Copy on its way

At this meeting

Whole meeting
3Decision Report: Acomb Front Street - Phase 2 Design and Costings (10:08am)This decision

More from York Decision Session - Executive Member for Economy and Culture

All decisions
MeetingDecisionOutcome
25 Mar 2025 Minutes (11:01am)That the minutes of the Decision Session held on 27 January 2025 be approved and signed by the Executive Member as a ... Approved Open
25 Mar 2025 Creation of infrastructure to be able to support the collection of donations to support the conservation of the City Walls (11:02am)T o approve Option 1, namely: a) The creation of donation points, “tap” and QR code (for in person events) based for ... Approved Open
27 Jan 2025 Minutes (10:02am)That the minutes of the Decision Session held on 22 October 2024 be approved and signed by the Executive Member as a ... Approved Open
27 Jan 2025 York Learning Self Assessment ReportTo approve the 2023/24 Self-Assessment Report, subject to any suggested changes. Reason: This helps monitor the servi... Approved Open
22 Oct 2024 Minutes (11:02am)That the minutes of the previous meeting held on 24 September 2024 be approved and then signed as a correct record by... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies