CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of York Council
Decision Session - Executive Member for Transport, Tuesday 11 March 2025 at 10.00am

Riverside Path Improvement Scheme (10:37am)

Approved Executive 8 papers

Decision Session - Executive Member for Transport approved this item on Tuesday 11 March 2025. Below is the council's own wording, with the papers it was decided on.

Item45

Resolved

To approve Option 2, progressing a separately resourced and funded project to identify and confirm the remedial works required to improve Riverside Embankment stability, as set out within the “Options Analysis and Evidential Basis – Riverside Embankment Stability” section of this report and Annex B, and provide recommendations to a future Executive Member Decision Session and progress the Riverside Path Improvement scheme to detailed design based on the scheme proposals and preliminary design inclusions set out within the “Options Analysis and Evidential Basis - Affordable Scheme” section of this report (beginning at paragraph 91) but delay construction until the dependency on the Riverside Embankment Stability issue is fully determined and resolved. Also to approve the following delegations of authority: · To Approve the procurement of a Principal Contractor and Principal Designer for the Riverside Path Improvement scheme and delegate authority to the Director of Environment, Transport & Planning (in consultation with the Director of Governance and the Head of Procurement) to take such steps as are necessary to procure, award and enter into the resulting contracts and the identification of the remedial works required results in the construction costs being in excess of the Key Decision threshold, a further report will be presented to a future Executive meeting. · To delegate authority to the Director of Environment, Transport and Planning to proceed with all necessary technical work, including preparation of a detailed design, investigation and conduct of diversions of statutory-undertakers apparatus to enable the works in regard of the Riverside Path Improvement Scheme. · To delegate authority to the Director of Environment, Transport and Planning to approve the final design to be delivered for the Riverside Path Improvement scheme unless the scheme objectives or cost tolerances cannot be met without significant alteration to the preliminary design in which case a further report will be submitted to a future Executive Member Decision Session · To Delegate authority to the Director of Environment, Transport, and Planning, in consultation with the Director of Finance, to carry out any necessary value engineering to ensure the Riverside Path Improvement scheme remains within budget. · To approve the submission of any relevant planning application(s) required to deliver the Riverside Path Improvement Scheme affordable solution and delegate authority to the Director of Environment, Transport and Planning to do so. · To approve the advertisement of an amendment to the Traffic Regulation order to introduce ‘Prohibition of cycling’ restrictions on the Aldborough Way access ramp to the Riverside Path as part of the Riverside Path Improvement Scheme. · To introduce ‘No waiting at any time’ restrictions on Jubilee Terrace as part of the Riverside Path Improvement Scheme in respect of traffic management and to approve any statutory consultation which may be required for this option. Also regarding Scheme Design: · To approve Option 1, proceeding with the affordable scheme as presented during the public consultation. Advertise no waiting at any time restrictions (double yellow lines) to the length of Jubilee Terrace outside the church as part of a formal Traffic Regulation Order process. This option meets ... To approve Option 2, progressing a separately resourced and funded project to identify and confirm the remedial works required to improve Riverside Embankment stability, as set out within the “Options Analysis and Evidential Basis – Riverside Embankment Stability” section of this report and Annex B, and provide recommendations to a future Executive Member Decision Session and progress the Riverside Path Improvement scheme to detailed design based on the scheme proposals and preliminary design inclusions set out within the “Options Analysis and Evidential Basis - Affordable Scheme” section of this report (beginning at paragraph 91) but delay construction until the dependency on the Riverside Embankment Stability issue is fully determined and resolved. Also to approve the following delegations of authority: · To Approve the procurement of a Principal Contractor and Principal Designer for the Riverside Path Improvement scheme and delegate authority to the Director of Environment, Transport & Planning (in consultation with the Director of Governance and the Head of Procurement) to take such steps as are necessary to procure, award and enter into the resulting contracts and the identification of the remedial works required results in the construction costs being in excess of the Key Decision threshold, a further report will be presented to a future Executive meeting. · To delegate authority to the Director of Environment, Transport and Planning to proceed with all necessary ... view the full minutes text for item 45.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Transport

Meeting: Executive Member for Transport Decision Session Meeting date: 11/03/2025 Report of: Director of Environment, Transport & Planning Portfolio of: Cllr Kate Ravilious, Executive Member for Transport

Decision Report: Riverside Path Improvement Scheme Subject of Report 1. The riverside path is a key route on the York cycle network and is well used by pedestrians and cyclists, connecting the west of the city with the city centre and the Scarborough Bridge river crossing. The Riverside Path Improvement Scheme focuses on the section of the path that runs from the junction of Kingsland Terrace and Jubilee Terrace to Scarborough Bridge.

2. This report outlines the preliminary scheme proposed for the Riverside Path Improvement Scheme, providing an overview of its key features and objectives.

3. This report provides a detailed summary of the feedback and insights gathered during the public engagement process. It highlights the concerns, suggestions, and general sentiment of stakeholders.

4. This report aims to outline the necessary steps and approvals required to advance the Riverside Path Improvement Scheme to the next stages of the project governance process. It seeks to secure authorisation to proceed to detailed design and construction, planning permissions, and any other essential resources or endorsements needed to move forward with the project implementation. 5. In addition, this report will also report the findings of a key dependency to this project with regards to the Riverside Embankment Structural Review (Annex B), which evaluates the current condition of the embankment and outlines the potential risks and challenges, not only to the future of the embankments ongoing stability, but also any associated impact to the Riverside Path Improvements Scheme. This report seeks to facilitate a decision on the embankment's future maintenance plan and any impact/interaction with the proposed Riverside Path improvements.

Benefits and Challenges 6. The benefits of delivering the Riverside Path Improvement Scheme are that it aligns with Council Local Transport Strategy Vision for 2024 as indicated in the “Policy Basis for Decision” section of this report. This alignment supports several key documents, including York Council’s Local Transport Strategy 2024-2040, York Council’s Local Cycling and Walking Infrastructure Plan (2024), the Council Plan for 2023-27, the York Climate Change Strategy (2022-2032), and the Health and Wellbeing Strategy (2022-2032).

7. Delivery of the scheme aligns with the bid made by City of York Council to the Active Travel England Funding Tranche 4 Grant Funding submission which was successful in May 2023.

8. At present, flooding across the area leaves the riverside path impassable for an average of 9 days each year, resulting in abandoned journeys and additional journey times for users who must seek an alternate route. End to end users will experience a journey time delay depending on their end destination. With 2,500 daily users impacted by these flooding events, the affordable scheme intends to increase the number of days the route is passable by an average of 4 days (with an average of 5 days remaining impassable).

9. The scheme looks to enhance provision for pedestrians and cyclists along the existing Riverside Path, catering for all users including those with mobility impairments. The scheme will upgrade and improve the layout for cyclists and pedestrians, not just along the Riverside Path but also the existing highway extent of Jubilee Terrace which leads to and from the Leeman Road area. Key areas for consideration include widening and segregating the existing path; lighting improvements; additional seating; improved surfacing; and reduction of the impact of flooding events by raising the path at its lowest points. These improvements will provide an enhancement that enables use of the route all year round.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Equalities Impact Assessment (EIA)Appendix A 593 KB Download
PDF
Riverside Embankment Stability Report, November 2024Appendix B 35 MB Download
PDF
Riverside Path Improvement Scheme Public Consultation Report December 2024Appendix C 644 KB Download
PDF
Active Travel ReviewAppendix D 537 KB Download
PDF
Riverside Path Improvement Scheme General Arrangement DrawingAppendix E 3.6 MB Download
PDF
Riverside Path Improvement Scheme Public Consultation November 2024Appendix F 21 MB Download
PDF
Riverside Path Improvement Scheme (10:37am)Report 674 KB DownloadRead as text
PDF
View item 45. as HTML 283 KBReport 283 KB Copy on its way

At this meeting

Whole meeting

Who was there

1 of 27 attended
AB
Alistair BriggsOfficer, expected
TC
Tony ClarkeOfficer, expected
EC
Eddie Coates-MaddenOfficer, expected
PD
Phil DelaneyOfficer, expected
CD
Claire DugglebyOfficer, expected
KF
Katherine FinnieOfficer, expected
IF
Ian FloydOfficer, expected
JG
James GilchristOfficer, expected
DG
David GladdersOfficer, expected
DG
Derek GrantOfficer, expected
DH
Darren HobsonOfficer, expected
MH
Michael HowardOfficer, expected

All 27 on the meeting page

More from York Decision Session - Executive Member for Transport

All decisions
MeetingDecisionOutcome
17 Nov 2026 Minutes (10:12am)That the minutes of the Decision Session held on Thursday, 22 October be approved and signed by the Executive Member ... Approved Open
17 Nov 2026 Consideration of results received from the informal consultation to introduce residents' priority parking restrictions within the Dodsworth Avenue and Pottery Lane area (10:03am)That no further action be taken and the area removed from the residents parking waiting list. The proposed restrictio... Decided Open
22 Oct 2026 Minutes (11:00am)That the minutes of the Decision Session held on Tuesday , 22 September 2026 be approved and signed by the Executive ... Approved Open
22 Oct 2026 Consideration of representations received during the Statutory Consultation for proposed restrictions on Murton Way, Osbaldwick Link Road, Osbaldwick Village and Osbaldwick Lane (11:17am)Osbaldwick Link Road: Decided Open
22 Oct 2026 Consideration of representations received during the Statutory Consultation for proposed restrictions on Front Street, Naburn (11:50am)To implement a lesser restriction than first advertised. Reason: The introduction of the double yellow lines will red... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies