Decision Session - Executive Member for Transport noted this item on Tuesday 21 October 2025. Below is the council's own wording, with the papers it was decided on.
i. To note that a procurement process for the award of a contract for all of the works is currently underway, and the works programme is to be delivered as laid out in the report. ii. To delegate authority to the Director of Environmental and Regulatory Services, in consultation with the Director of Governance and the Head of Procurement, to take such steps as are necessary to award and conclude the Contract for the works and to determine the provisions of any subsequent modifications and/or extensions thereto post award and to seek Executive approval for the re-prioritisation of Highways and Transportation funding to deliver the Additional Works programme. Reason: Without completion of the works the risk of the biennial bridge inspection process identifying further deterioration is heightened considerably, this could lead to weight restrictions being enforced causing considerable impact on movement in the city centre. i. To note that a procurement process for the award of a contract for all of the works is currently underway, and the works programme is to be delivered as laid out in the report. ii. To delegate authority to the Director of Environmental and Regulatory Services, in consultation with the Director of Governance and the Head of Procurement, to take such steps as are necessary to award and conclude the Contract for the works and to determine the provisions of any subsequent modifications and/or extensions thereto post award and to seek Executive approval for the re-prioritisation of Highways and Transportation funding to deliver the Additional Works programme. Reason: Without completion of the works the risk of the biennial bridge inspection process identifying further deterioration is heightened considerably, this could lead to weight restrictions being enforced causing considerable impact on movement in the city centre.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport, 9 pages
Meeting: Transport Executive Decision Session Meeting date: 21 October 2025 Report of: Dave Atkinson, Director for Environmental and Regulatory Services Portfolio of: Executive Member for Transport
Decision Report: Lendal Bridge Major Refurbishment
Subject of Report
1. This report outlines the proposed major maintenance works to Lendal Bridge, which is a critical transport link in central York and a Grade II listed structure. An investment of £1.9m has been agreed as part of the Highways Capital programme to fund the essential maintenance works.
2. Additional works to extend the longevity and improve the aesthetic of the bridge will be delivered as a concurrent phase of works subject to funding and future programming.
Essential Maintenance Works
3. Lendal Bridge has significant corrosion and deterioration, including life-expired surfacing and failed waterproofing. The below works will directly address the following urgent issues: Resurfacing the carriageway and footpaths Re-waterproofing the structure Urgent structural metalwork repairs (extent confirmed upon commencement) These essential works will: Protect the bridge’s long-term load carrying capacity Eliminate frequent emergency repairs Minimise the risk of more costly future interventions
Programme of works: Design currently progressing To be tendered from December 2025 Contract to be awarded in February 2026 Works to commence in April 2026 Works to be completed within 8 weeks of commencement with 24/7, 7 days a week working pattern
This phase is funded with a confirmed budget of £1.9 million, a 6% contingency has been factored into the costs and the scheme will be delivered with minimal risk to exceeding this value.
Additional Works
4. To maximise the Essential Works investment, and avoid future return visits, we are recommending that the Council provides additional funding to deliver a comprehensive £1.3m package of improvements concurrently. These additional works would include: Full repainting of all metalwork, including decorative features Coating of troughing, parapets, and elevation treatments Extended scaffolding and site access to deliver works to a high standard The works would be undertaken over a 38-week period commencing from the start of the main closure for the Essential Works. The works would not require a full road closure following completion of the 8-week Essential Works programme, but a single footway closure will be required to deliver these works.
5. The Lendal Bridge works have been programmed to ensure they support and reinforce the emerging city centre sustainable travel corridor improvements. This will ensure maximum outcomes and benefits for all users. The project is currently under development and will soon be going to public consultation. Following this, a report will be taken to a decision session in early 2026. If approved, the construction phase will immediately follow the Lendal Bridge Essential Works.
Policy Basis for Decision
6. The proposals within this report are consistent with the 10-Year Plan for the city, known as “York 2032”, which recognises transport as a key priority for the city, setting the goal that York’s transport networks will be inclusive and sustainable, connecting neighbourhoods and communities. 7. In October 2023, the Executive approved a vision, objectives and Policy Focus area for a Local Transport Strategy. This project will support the following proposed objectives: “Support delivery of the Climate Change Strategy” – Maintenance of an existing asset has a far lower carbon cost than allowing it to deteriorate and then replacing it. “Enhance the reliability of the transport system” by reducing the need for emergency repairs. “Protect the city’s heritage and enhance public spaces.” remedial works will safeguard the structure from dilapidation. “Future-proof our city” by ensuring that this vital transport link remain serviceable for future generations.
Equalities and Human Rights
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.