Heritage Estate Programme (10:03)

Approved Executive 7 papers

AI summaryCity of York Council approved a Heritage programme and confirmed its Heritage Champion [D]. Initial capital investment is £250k, and the programme will develop a plan covering 10 years [P2] [P17] [P47] [P60].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedWill develop a strategic plan covering 10 years [P2] [P47].
Money£250k initial capital investment [P17] [P60].Taken from the 2025/26 capital contingency [P60].
What happens nextConvene the Strategic Partnership [P53].Refine programme outcomes and actions [P53].
Who it affectsNot stated

What was decided

The council approved a Heritage programme focused on getting the most from and for York's heritage assets [D].

The Executive confirmed the Deputy Leader and Executive Member for Economy & Culture as the council's Heritage Champion [D].

The programme will provide governance for all later council heritage projects, including partner led schemes [D] [P20]. Report P20

Why

York's heritage can support economic growth and longer term financial resilience [P3] [P6]. Conservation, sustainability and community engagement practices can be shared nationally and celebrated globally [D]. Report P3, P6

Partnership and governance arrangements will support a city response based on shared approved priorities and give the Executive greater oversight [D] [P19]. Report P19

Doing nothing would guarantee no change, heritage decline, and increased maintenance and business liabilities [P9]. Report P9

What happens next

Convene the proposed Strategic Partnership and further refine programme outcomes and actions [P53]. Report P53

Use partnership workshops to develop a 10 year Heritage Strategic Delivery Plan and attract investment [P47]. Report P47

Receive York Museum Trust's capital development options in December 2025 and the World Heritage Steering Group's detailed next steps in January 2026 [P33] [P37] [P49]. Report P33, P37, P49

The money

  • £250k Initial capital investment from the 2025/26 capital contingency [P60]. The programme fund was approved at September's Executive for over two years, with the intention of attracting enough investment to self fund after 24 months [P17]. Report P17, P60
  • £7m Capital investment identified for the Yorkshire Museum, including a new roof to prevent water ingress and damage to collections [P40]. Report P40
  • around £15m Likely cost of replacing the Female prison roof within a 10 year time horizon [P40]. Report P40
  • £70m Amount sought in the unsuccessful 2019 National Lottery Heritage Fund bid for Castle Museum [P40]. Report P40
  • £1.1m Previous York Museum Trust funding level before the reduction [P29]. Report P29
  • £300k Reduced York Museum Trust funding level [P29]. Report P29
  • £2.1bn Reported Gross Value Added for York's heritage [P22]. Report P22

Options considered

  • Chosen: Initiate the programme as set out in Annex A. It would position the council to gain investment and economic and social benefits while conserving historical collections [P57]. Report P55, P56, P57
  • Rejected: Initiate a programme with a different vision Report P55, P56
  • Rejected: Do not initiate the programme. Doing nothing would guarantee no change, heritage estate decline, and continued maintenance and business liabilities with no mitigation [P9]. Report P9, P55, P56

Implications

  • Financial: The £250k initial investment comes from the 2025/26 capital contingency [P17] [P60]. If urgent capital issues arise, funding could be insufficient [P60]. Report P17, P60
  • Financial: There is no immediate impact on council finances and no contribution to closing the forecast three year budget gap [P15]. Report P15
  • Risk: The council cannot guarantee that the programme will attract investment [P9]. Without action, the heritage estate may decline and maintenance and business liabilities may increase [P9]. Report P9
  • Legal: There are no legal implications specific to this report at this stage [P64]. Any lease negotiations or funding bids will be considered separately by the relevant team [P64]. Report P64
  • Equalities: An equalities impact assessment has been completed and will be reviewed regularly [P73]. The programme should improve equitable access through digital innovation [P73]. Report P73
  • Climate: There are no climate implications at this stage [P69]. Heritage buildings are difficult to retrofit or add renewable energy technologies, so sensitive conservation management is required [P83]. Report P69, P83
  • Staffing: City Development will lead with input from existing specialist officers, with no human resource implications at this stage [P62]. Report P62
  • Other: Future consultancy work must follow the Procurement Act 2023 and the Council's Contract Procedure Rules [P65]. A coordinated communications campaign will need resourcing and funding throughout the programme [P77]. Report P65, P77

Who and where

  • Residents across all wards Report P71, P85
  • Council custodians of heritage buildings and artefact collections Report P26, P39
  • York Museum Trust Report P20, P29
  • World Heritage Steering Group Report P20, P35
  • City heritage partners and stewards Report P7, P45, P84
  • Heritage and conservation sector employers and workers Report P3, P79
  • Businesses seeking uses for vacant heritage premises Report P11, P27
  • Potential public and private funders Report P4, P47

Timeline

  • Tuesday, 2 September 2025, 4.30 pm: The £250k programme fund was approved at this Executive meeting [P17] [P90]. Report P17, P90
  • October 2025: A formal UNESCO response, including a report, was expected [P37]. Report P37
  • 4 November 2025: The council approved the Heritage programme and confirmed its Heritage Champion [P1] [D]. Report P1
  • Once approved: The Strategic Partnership will convene and programme outcomes and actions will be refined [P53]. Report P53
  • December 2025: York Museum Trust's capital development options will be presented to Executive [P33] [P49]. Report P33, P49
  • January 2026: The World Heritage Steering Group is expected to provide a detailed view of next steps to Executive [P37]. Report P37
  • 2030: The final nomination is then expected to be submitted for a decision by the UNESCO World Heritage Committee [P37]. Report P37
  • after 24 months: The programme was intended to attract enough investment to self fund [P17]. Report P17

Plain English for the jargon

  • Heritage Champion: The Executive member responsible for taking the programme forward [P21].
  • Heritage Strategic Delivery Plan: A partnership plan covering 10 years to attract investment and develop a strategic narrative for York's heritage [P2] [P47].
  • Strategic Partnership: The partnership to convene after approval and refine programme outcomes and actions [P53].
  • GVA: Gross Value Added. York's heritage has a reported GVA of £2.1bn [P22].
  • UNESCO World Heritage Site: A proposed designation for York being progressed by the independent World Heritage Steering Group [P35].
  • YMT: York Museum Trust [P92].
  • WHSG: World Heritage Steering Group [P92].
  • DPIA: Data protection impact assessment. No DPIA is required at this time, but the position will be reviewed [P75].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item43

Resolved

i. Approved the establishing of the Heritage programme which will be focused on making the most from and for York’s heritage assets. ii. Confirmed that Cllr Kilbane the Deputy Leader and Executive Member for Economy & Culture was appointed by the Executive as the Heritage Champion for the Council. Reason: By harnessing the opportunities from York’s heritage assets, the benefit will stretch far beyond York’s boundaries as new conservation, sustainability and community engagement practices are shared nationally and celebrated globally. Initiating the programme now is to enable the council to put in place the partnership and governance arrangements that would ensure a city response based on shared and approved priorities – providing Executive with greater oversight. This programme would act as the governance arrangements for all subsequent heritage-related projects which involve the council, including those led by partners such as the York Museum Trust or World Heritage Steering Group. i. Approved the establishing of the Heritage programme which will be focused on making the most from and for York’s heritage assets. ii. Confirmed that Cllr Kilbane the Deputy Leader and Executive Member for Economy & Culture was appointed by the Executive as the Heritage Champion for the Council. Reason: By harnessing the opportunities from York’s heritage assets, the benefit will stretch far beyond York’s boundaries as new conservation, sustainability and community engagement practices are shared nationally and celebrated globally. Initiating the programme now is to enable the council to put in place the partnership and governance arrangements that would ensure a city response based on shared and approved priorities – providing Executive with greater oversight. This programme would act as the governance arrangements for all subsequent heritage-related projects which involve the council, including those led by partners such as the York Museum Trust or World Heritage Steering Group.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Combined Executive Member Decision Session, 13 pages

Meeting: Combined Executive Member Decision Session Meeting date: 4 November 2025 Report of: Director of City Development Portfolio of: Leader, Portfolio Holder Strategy, Policy and Partnerships

Decision Report: Heritage Programme Subject of Report 1. This report invites the Leader to consider initiating a programme to develop a 10-year Heritage Strategic Delivery Plan – focused on maximising the social, economic and sustainability outcomes from York’s world-renowned heritage assets.

2. It sets out how the council proposes drawing on arguably York’s greatest strength to introduce more well-paid jobs to the city, as well as establishing opportunities for residents to develop pioneering sustainable heritage skills, build community pride and local engagement and strengthen research and innovation focused on our heritage assets and every day historical artefacts.

3. At the heart of the programme will be attracting significant investment in York’s heritage, whether through public sector grants, private sector investment or planned disposals.

4. Benefits and Challenges

5. By harnessing the opportunities from York’s heritage assets, the programme will inform local and regional ambition and national opportunity to explore new conservation, sustainability and community engagement practices that support York’s economic growth and longer-term financial resilience. 6. By setting out a clear strategic narrative and delivery plan to protect and enhance York’s heritage assets, the council will be better placed to mitigate expensive unplanned maintenance liabilities, inherent in the custodianship of heritage buildings, and maximise occupational efficiencies and benefits, to make sites more viable and financially self-sustaining.

7. It will structure and embed how the council works in partnership with key city stewards to unlock innovation, opportunity and investment, providing a more compelling narrative to funding and investment decisions greater oversight for the administration and budget planning.

8. In the absence of council capacity to lead a strategic approach to attracting investment in the heritage estate, city partners have initiated their own programmes to attract more investment, creating a risk that partners who have the capacity to corral around a single purpose are dominating the discussion, rather than taking a city- wide perspective to make sure the highest priorities get due attention.

9. There is no guarantee that by initiating a heritage programme the council will attract the investment the city needs. However, by doing nothing there is a guarantee that nothing will change, the heritage estate will decline, and the council will continue to have increased maintenance and business liabilities with no plans to mitigate.

Policy Basis for Decision 10. The Economic Strategy 2022-2032 and Cultural Strategy 2020- 2025 both recognise York’s place with global strengths. York’s heritage is of global significance and York was placed on the UK’s UNESCO World Heritage tentative list1 in 2023.

11. The Council Plan, One city for all, 2023-2027, reflects York’s heritage assets and 2,000-year history as a key strength, attracting over 9m visitors a year. In addition, the council plan sets an action to help business to thrive by repurposing vacant premises and council spaces to encourage meanwhile or alternative uses.

12. The Local Plan, adopted in February 2025, ensures future developments respect the unique historical status and heritage of York, in particular reflecting the character and setting of the city and the permanence of the Green Belt. Supplementary Planning

1 DCMS reviews and publishes the UK tentative list roughly every 10 years. Documents required as a result of the Local Plan include sustainability and heritage which could be informed by this approach.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 8 pages Download
PDF
EqIA_Heritage Programme_Draft_1-0Appendix B 13 pages Download
PDF
Heritage Programme DPIA screening_1-0Appendix C 3 pages Download
PDF
Heritage Estate Programme (10:03)Report 13 pages DownloadRead as text
PDF
View as HTML (43./3) 92 KBAppendix 92 KB Copy on its way
PDF
View as HTML (43./4) 28 KBAppendix 28 KB Copy on its way
PDF
View item 43. as HTML 79 KBReport 79 KB Copy on its way

At this meeting

Whole meeting

Who was there

2 of 2 attended
CD
Councillor Claire DouglasCommittee Member, present
JK
Councillor Jenny KentCommittee Member, present

More from York Decision Session - Combined Executive Member Decision Session

All decisions
MeetingDecisionOutcome
3 Nov 2026 Appointing a Chair (10:05)That arrangements for Chairing the meeting were confirmed as follows: · Councillor Lucy Steels Walshaw, Executive Mem... Decided Open
3 Nov 2026 Procurement of an Inclusion Health Service (10:10)The delegated authority be given to the Director of Public Health in conjunction with the Director of Governance and ... Decided Open
3 Nov 2026 Public Realm Service Update (10:14)i. That the outcomes of the weed treatment programme in 2026 be noted and that approval be given to the recommended a... Noted Open
3 Nov 2026 To Consider and Approve for Publication Planning Guidance (10:27)i. That approval be given for the publication of the draft non-statutory planning guidance at Annexes C-E ( Annex C –... Approved Open
3 Nov 2026 ‘Strategic Housing Needs Assessment: People with learning disabilities and autistic people' for North Yorkshire Council, City of York Council and Humber and North Yorkshire Integrated Care Board (10:41)That the Needs Assessment Annex A be endorsed and adopted as part of the council’s Local Plan evidence base. Reason: ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies