AI summaryCity of York Council Audit and Governance Committee noted the 11 key corporate risks and an in-depth review of the capital programme risk, and asked officers to re-score risks after mitigations.
Written from the decision and the officer reportPDF Pro
OutcomeNotedOfficers to review scoring after mitigations
MoneyNot stated
What happens nextCMT risk workshopFebruary 2026, to review KCRs
Who it affectsCouncil-wide risk managementAll directorates and key projects
What was decided
The committee noted the key corporate risks register and the in-depth review of KCR 7 (Capital Programme), which replaced KCR 5 (Safeguarding) for this monitor. Report P14, P46
The committee asked officers to review the scoring of risks once mitigations have been accounted for.
Why
To give assurance that the authority is effectively understanding and managing its key risks.
The committee has a standing role to receive assurance on the governance of risk, the up-to-date key corporate risk profile, and the effectiveness of risk management arrangements. Report P1, P2, P3, P4
What happens next
Council Management Team will hold a risk workshop in February 2026 to review existing and any new key corporate risks. Report P14
The in-depth review cycle continues, with the next monitor expected to examine a different KCR. Report P46
Options considered
Chosen: Note the key corporate risks register. Standing assurance role of the committee Report P1
Chosen: Note the in-depth review of KCR 7 (Capital Programme). Requested at the 30 July meeting; replaced KCR 5 (Safeguarding) for this monitor Report P14, P46
Chosen: Ask officers to re-score risks after mitigations. To reflect the effect of mitigation actions on net risk ratings Report P19
Implications
Risk: No new, increased, or reduced KCRs since the last monitor, but the committee wants scoring reviewed after mitigations are factored in. Report P23
Risk: KCR 2 (Governance) gained new cyber-related detail, including transition to new Cyber Assessment Frameworks for the NHS DSPT and PSN, and a rising risk of adverse cyber events. Report P25, P26, P27, P28, P29
Risk: KCR 3 (Effective and Strong Partnerships) notes financial pressure on Integrated Care System partners undergoing a restructure under a new DHSC-led blueprint, with impacts on the council not yet understood. Report P40, P41
Who and where
All council directorates, which feed risks into the corporate register Report P8, P11, P12
Council Management Team, which reviews and escalates KCRs Report P12, P14
Audit and Governance Committee members, who receive risk assurance Report P1, P2, P3, P4
Timeline
30 July (previous meeting): Members asked for the Capital Programme risk to be brought forward for review Report P14
November 2024: Committee agreed a cycle of in-depth reviews of one KCR per monitor Report P46
13/01/2026: Report approved by Debbie Mitchell Report P51
February 2026: CMT risk workshop to review existing and new KCRs Report P14
Plain English for the jargon
KCR: Key Corporate Risk: a significant risk to the council's objectives, held on the corporate risk register
CMT: Council Management Team
DMT: Directorate Management Team
CAF: Cyber Assessment Framework, referenced in relation to NHS DSPT and PSN compliance
DSPT: NHS Data Security and Protection Toolkit
PSN: Public Services Network
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item46
Resolved
i. Noted key corporate risks register; ii. Noted the in-depth review of KCR 7 (Capital Program); iii. Officers to review the scoring of risks after mitigations have been accounted for. Reason: To provide assurance that the authority is effectively understanding and managing its key risks.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
4. The role of Audit & Governance Committee in relation to risk management is to receive;
assurance with regards to the governance of risk, including leadership, integration of risk management into the wider governance arrangements of the council including CMT ownership and accountability
the up-to-date key corporate risk profile including the effectiveness of risk management actions; and
monitoring the effectiveness of risk management arrangements in supporting the development and embedding of good practice across the organisation
5. Risks are usually identified in three ways at the Council;
A risk identification workshop to initiate and/or develop and refresh a risk register. The risks are continually reviewed through directorate management teams (DMT) sessions.
Risks are raised or escalated on an ad-hoc basis by any employee
Risks are identified at DMT meetings
6. Due to the diversity of services provided, the risks faced by the authority are many and varied. The Council is unable to manage all risks at a corporate level. Best practice is to focus on the significant risks to the council’s objectives these are known as the key corporate risks (KCRs).
7. The corporate risk register is held digitally in ‘Magique’. The non KCR risks are specific to council directorates and consist of both strategic and operational risk. Operational risks are those which affect day to day operations and underpin the directorate risk register. All
Page 2 of 8 operational risk owners are required review their risks on a regular basis and inform the risk management service of any changes.
8. In addition to the current KCRs, in line with the RM policy, risks identified by any of the Directorates can be escalated to Council Management Team (CMT) for consideration as to whether they should be included as a KCR. KCRs are reported and discussed quarterly with CMT and Portfolio Holders. KCR’s can also be reduced to directorate level risk as part of this process.
Key Corporate Risk (KCR) update
9. There are currently 11 KCRs which are included at Annex A in further detail, alongside progress in managing the risks. 10. At A&G on 30th July A&G members asked for the Capital Programme risk to be brought forward and it has replaced KCR 5 ‘Safeguarding’ in this monitor (Monitor 3). There was also a discussion around whether subsequent risks arising from the implementation of the local plan may give rise to a further/new KCR’s. To date officers have not brought any forward however CMT are undertaking a risk workshop in February 2026 which will allow them to review and consider all existing and new KCR’s.
11. Annex B provides a one-page summary of all the KCR’s and their current gross and net risk ratings.
12. In summary the key risks to the Council are:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.