Business Sustainability Programme (5:32 pm)

Noted Scrutiny 5 papers

AI summaryCity of York councillors noted a report on the Business Sustainability Programme and asked that case study information be added to future applicant packs.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCase study info for future applicant packs
MoneyNot stated
What happens nextCase studies in future packsTo improve service provision
Who it affectsAll wards, future applicantsCitywide business support programme

What was decided

Members noted the report on the Business Sustainability Programme, which sits within the UK Shared Prosperity Fund work led by the Combined Authority. Report P2, P11

The committee added a recommendation that case study information be made available as part of any future applicant pack, to improve service provision. Report P2, P3

Why

The recommendation supports a continuous improvement approach to how the council and Combined Authority run business support programmes. Report P2, P3

No risks have been identified in connection with the report. Report P1

What happens next

Members' comments and the case study recommendation will be fed back to the Executive Member and the Combined Authority to shape future iterations of business support programmes. Report P2

The Head of Climate Change and Chief Strategy Officer are named as the report's authors and lead officers for further information. Report P4, P6

Options considered

  • Chosen: Note the report and feed comments to the Executive Member and Combined Authority. Continuous improvement approach to service provision Report P2, P3
  • Chosen: Add case study information to future applicant packs. To improve service provision

Implications

  • Risk: No known risks are identified in the report. Report P1
  • Other: The programme connects the council's climate change work with UK Shared Prosperity Fund business support activity run through the Combined Authority. Report P4, P11

Who and where

  • Businesses in York that apply or may apply to the Business Sustainability Programme Report P2, P9
  • Residents and businesses across all wards of the City of York area Report P5

Timeline

  • 16/02/2026: Report approved for submission to the committee. Report P4
  • 2026-03-02: Corporate Scrutiny Committee considered the report at its meeting.

Plain English for the jargon

  • BSP: Business Sustainability Programme.
  • CO2e: Carbon Dioxide equivalent, a standard unit for comparing greenhouse gas emissions.
  • HM Treasury: His Majesty's Treasury, the UK government's economic and finance ministry.
  • UKSPF: United Kingdom Shared Prosperity Fund, the main UK government fund for local business and community investment.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item50

Resolved

Members noted the report and recommended that case study information be made available as part of any future applicant pack. Reason: To improve service provision.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Corporate Scrutiny Committee

Corporate Scrutiny 2 March 2026

Report of the Chief Strategy Officer

Business Sustainability Programme Summary

1. The York and North Yorkshire Business Sustainability Programme (BSP) ran from May 2025 to March 2026. This report provides a summary of the programme in relation to activity in York.

2. The BSP is funded through UK Shared Prosperity Fund (UKSPF) and is a continuation of the previous Business Decarbonisation Programme, which provided fully funded energy audits and renewable feasibility studies to businesses across York. 3. The Programme has the ambition to increase the number of enterprises adopting new technologies or processes, to reduce greenhouse gas emissions and to improve businesses bottom-line.

4. A total capital fund of £1,524,393 was allocated, for business grants, with revenue funding provided to the Combined Authority and the Local Authorities to cover costs of administering the fund.

5. As of February 2026, 98% of funding has been allocated to businesses and farms across York and North Yorkshire. 6. Project Summary: Total Programme Value £1,524,393 of capital funding Application Window From May 2025 to September 2025. To maximise the delivery timeframe for what are often complex projects requiring external works, grant awards will be made on a rolling basis to projects approved at monthly decision panels, until such time as the fund is exhausted. Early applications are encouraged to avoid disappointment. Amount of Funding Grants from £2,000 to £49,950 Available Match Funding The Business Sustainability Programme can fund up to 60% Required of total project costs – businesses are expected to contribute 40% of project costs Delivery Window From July 2025 until February 2026 – projects must be completed by February 2026 Number of 85 Total (funding ask of £2,154,057) applications 63 Businesses received 22 Farms Projects funded 59 Total (funding allocated of £1,490,907) 41 businesses 18 farms Carbon Dioxide 390tCO2e total equivalent (CO2e) 180tCO2e businesses savings (per 110tCO2e farms annum)

7. Scrutiny Committee are invited to review the report and reflect on the delivery of the BSP, with feedback welcomed to inform future iterations of the programme. Background

8. The York and North Yorkshire Combined Authority allocated a proportion of its UKSPF allocation to deliver a Business Sustainability Programme. The programme, co-designed by York and North Yorkshire Combined Authority, North Yorkshire Council and City of York Council, builds on the success of previous UKSPF Business Sustainability programmes across the region.

9. In 2023-2025, City of York Council provided fully funded energy audits and renewable feasibility studies to businesses across the city. A total of 63 decarbonisation plans were completed for York businesses, identifying opportunities with a total implementation cost of over £3m and the potential to reduce carbon dioxide equivalent (CO2e) emissions by 935tonnes per year, with annual cost savings of £914,000.

10. The BSP was subsequently designed to support these businesses to implement the opportunities identified, delivering climate action and contributing to the economic growth of our region. All businesses and farms across the region that had received a decarbonisation/energy audit from a qualified assessor were eligible for the BSP.

11. Reflecting the value of informed decision making, the BSP also extended the offer of fully funded decarbonisation and energy audits to businesses and farms across the region. Programme Objectives

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Business Sustainability Programme (5:32 pm)Report 194 KB DownloadRead as text
PDF
Business Sustainability Programme: Annex AAppendix 208 KB Download
PDF
New Scrutiny Report_Business Sustainability Programme_March 2026_Report 13 KB Download
PDF
View as HTML (50./3) 14 KBReport 14 KB Copy on its way
PDF
View item 50. as HTML 77 KBReport 77 KB Copy on its way

At this meeting

Whole meeting

Who was there

9 of 9 attended
SF
Councillor Stephen FentonChair, present
DM
Councillor Dave MerrettVice-Chair, present
NA
Councillor Nigel AyreCommittee Member, present
AB
Councillor Anna BaxterCommittee Member, present
JC
Councillor Jo ColesCommittee Member, present
AP
Councillor Anna PerrettCommittee Member, present
KT
Councillor Kallum TaylorCommittee Member, present
RW
Councillor Richard WatsonCommittee Member, present
PW
Councillor Paula WiddowsonCommittee Member, present

On this subject at York

Search all
  1. Business Sustainability Programme (5:32 pm)This decision
  2. Directorate of City Strategy Service Plans 2008/09 (Covering April 2008 - March 2011) - City Development & Transport, Planning & Sustainability, and Resource & Business ManagementNoted

More from York Corporate Scrutiny Committee

All decisions
MeetingDecisionOutcome
9 Nov 2026 Minutes (5.41 pm)That the minutes be approved as a correct record for the meeting held on 7 September 2026. Approved Open
9 Nov 2026 Equity, Diversity and Inclusion (EDI) Strategy refresh (5.41 pm)That the report be noted and the comments of the Committee be included in the report to the Executive Member Decision... Noted Open
9 Nov 2026 Annual Complaints Performance and Service Improvement (6.16 pm)That the report be noted. Reason: To ensure scrutiny oversight of complaint handling performance and organisational l... Noted Open
9 Nov 2026 Council Motions (7.05 pm)That the contents of Annex A be noted and the motions listed above be closed. Reason: To ensure that the process for ... Noted Open
9 Nov 2026 Petitions Schedule (7.18 pm)That the schedule of petitions be noted, and those petitions listed above be closed. Reason: To ensure the Committee ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies