Internal Audit Progress Report 2025/26 (6:40pm)

Noted Finance 3 papers

AI summaryCity of York Council's Audit and Governance Committee noted 2025/26 internal audit progress, results and remaining plans. [D][P2] The internal audit service conformed to the GIAS UK Public Sector during 2025/26, and one significant control weakness was relevant to the Annual Governance Statement. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedOne significant control weakness was identified [D]
MoneyNot stated
What happens nextRemaining 2025/26 audit work [D][P2]Delivery is planned over the remainder of the year [D][P2]
Who it affectsAnnual Governance Statement preparation [D]One significant control weakness was considered relevant [D]

What was decided

The committee noted progress in delivering the 2025/26 internal audit work programme and plans for delivery over the remainder of the year. Report P2

It noted the internal audit results and the Head of Internal Audit's opinion on whether the council's governance, risk management and internal control were adequate and effective.

It noted the outcome of Veritau's quality assurance and improvement programme, including confirmation that the internal audit service conformed to the GIAS UK Public Sector during 2025/26. It also noted the one significant control weakness relevant to preparing the Annual Governance Statement.

Why

Members can consider what the internal audit findings mean and review planned activity for the remainder of 2025/26.

The notes enable members to consider the Head of Internal Audit's opinion.

The significant control weakness is relevant to preparing the Annual Governance Statement.

What happens next

Progress and audit results must be reported periodically to the committee by the Head of Internal Audit. Report P2

The internal audit work programme is planned for delivery over the remainder of 2025/26. Report P2

Work no longer programmed for 2025/26 is currently prioritised for delivery in 2026/27. The update also reports outcomes from following up actions agreed in previous audit reports. Report P2

Implications

  • Risk: Failure to report internal audit results to senior management and the committee would mean the council did not meet proper practice for internal audit. External scrutiny and challenge could follow. Report P6
  • Other: One significant control weakness is relevant when preparing the Annual Governance Statement.
  • Risk: The Head of Internal Audit gave an opinion on whether the council's governance, risk management and internal control were adequate and effective.
  • Other: Committee members can consider what the internal audit findings mean and review planned activity for the remainder of 2025/26.
  • Other: Senior council officers and the committee were consulted while the work programme was developed. The progress report did not require consultation. Report P4

Who and where

  • Audit and Governance Committee members Report P4, P6
  • Senior council officers Report P4
  • Senior management Report P6
  • The council Report P6
  • Annual Governance Statement
  • The internal audit service

Timeline

  • 17 March 2025: The Audit and Governance Committee approved the 2025/26 internal audit work programme. Report P1
  • 27/01/2026: The report was approved. Report P10
  • during 2025/26: Internal audit work was undertaken and one significant control weakness was identified.
  • during 2025/26: The internal audit service conformed to the GIAS UK Public Sector.
  • the remainder of 2025/26: Delivery of the internal audit work programme is planned. Report P2
  • 2026/27: Work no longer programmed for 2025/26 is currently prioritised for delivery. Report P2
  • 2026-05-06: The Audit and Governance Committee noted the programme update, audit findings, quality assurance outcome and significant control weakness.

Plain English for the jargon

  • Internal audit work programme: The approved programme of internal audit work for 2025/26. [P1] Progress and planned delivery are reported to the committee. [P2]
  • Quality assurance and improvement programme: Veritau's programme, whose outcome the committee noted. [D]
  • GIAS UK Public Sector: The internal audit service conformed to it during 2025/26. [D]
  • Annual Governance Statement: The statement for which one significant control weakness is considered relevant. [D]
  • Proper practice for internal audit: The council must report internal audit results to senior management and the Audit and Governance Committee to comply with it. [P6]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item72

Resolved

That the Audit and Governance Committee: · Noted the progress made in delivering the 2025/26 internal audit work programme and plans for delivery over the remainder of the year. Reason: To enable members to consider the implications of internal audit findings, and to review planned activity for the remainder of 2025/26. · Noted the results of internal audit work undertaken and the opinion of the Head of Internal Audit on the adequacy and effectiveness of the Council’s framework of governance, risk management, and internal control. Reason: To enable members to consider the implications of internal audit findings. · Noted the outcome of Veritau’s quality assurance and improvement programme, including the confirmation that the internal audit service conformed to the GIAS UK Public Sector during 2025/26. Reason: To enable members to consider the opinion of the Head of Internal Audit. · Noted the one significant control weakness identified by internal audit during the year which is considered relevant to the preparation of the Annual Governance Statement. Reason: To enable the Annual Governance Statement to be prepared.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Audit and Governance Committee, 3 pages

Background

5. The 2025/26 internal audit work programme was approved by the Audit and Governance Committee at its meeting on 17 March 2025.

6. To conform with professional standards, and the council’s audit charter, the Head of Internal Audit must report periodically to the committee on the progress made against the internal audit work programme, and on the results of audit activities undertaken. 7. Annex 1 to this report provides an update on progress made in delivering the internal audit work programme. This includes a summary of completed work, work currently in progress, and work no longer programmed for 2025/26 but currently prioritised for delivery in 2026/27. It also reports on outcomes from the follow-up of actions agreed in previous audit reports.

Consultation Analysis

8. Senior council officers and this committee were consulted during the development of the 2025/26 work programme on which this progress report is based. However, no consultation was required in the preparation of this report.

Risks and Mitigations

9. The council will not comply with proper practice for internal audit if the results of internal audit work are not reported to senior management and the Audit and Governance Committee. This could result in external scrutiny and challenge.

Contact details

For further information please contact the authors of this Report.

Author

Name: Connor Munro Job Title: Head of Internal Audit Service Area: Veritau Limited Telephone: 01904 553512 Report approved: Yes Date: 27/01/2026

Background papers

 72. Internal Audit Work Programme

Annexes

 Annex 1: Internal audit progress report 2025/26  Exempt annex 2: ICT disaster recovery  Exempt annex 3: Follow-up audit – risk management  Exempt annex 4: School themed audit: governance  Exempt annex 5: Service and role-specific training  Exempt annex 6: Sundry debtors  Exempt annex 7: Main accounting system  Exempt annex 8: Danesgate Community School

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal audit progress report (March 2026)Appendix 1 22 pages Download
PDF
Internal Audit Progress Report 2025/26 (6:40pm)Report 3 pages DownloadRead as text
PDF
View item 72. as HTML 28 KBReport 28 KB Copy on its way

At this meeting

Whole meeting

Who was there

10 of 10 attended
AH
Councillor Andrew HollyerChair, present
JB
Councillor Jane BurtonVice-Chair, present
TF
Councillor Tony FisherCommittee Member, present
DM
Councillor Dave MerrettCommittee Member, apologies, sent representative
JR
Councillor Jason RoseCommittee Member, present
JC
Councillor Jo ColesCommittee Member, present
CV
Councillor Christian VassieCommittee Member, present
MB
Myles BinneyIndependent Person, present
MW
Matt WilliamsIndependent Person, present
KT
Councillor Kallum TaylorSubstitute, present as substitute

On this subject at York

Search all
  1. Internal Audit Progress Report 2025/26 (6:40pm)This decision
  2. Internal Audit Progress Report 2026/27 (19:19)Noted
  3. Internal Audit Progress Report 2026/27 (19:47)Noted
  4. Internal Audit Work Programme 2026/27 (20:05)Approved
  5. Internal Audit Progress Report 2025/26 (20:23)Noted
  6. Internal Audit Work Programme Consultation Report 2026/27 (19:41)Decided

More from York Audit and Governance Committee

All decisions
MeetingDecisionOutcome
21 Oct 2026 Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna... Decided Open
21 Oct 2026 Minutes & Action Log (17:39)That the minutes of the meeting held on 22 July 2026 be approved and the minutes of the meeting held on 16 September ... Approved Open
21 Oct 2026 Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p... Noted Open
21 Oct 2026 Treasury Management 2026/27 Mid-Year (Quarter 2) report and review of Prudential Indicators (17:54)i. Noted the Treasury Management Mid-Year Report and Review of Prudential Indicators 2026/27 at Annex 1. Reason: That... Noted Open
21 Oct 2026 Suggested Constitutional Changes - Revised Article 13 (18:09)i. Endorsed the adoption of the changes to Article 13 of the Constitution and recommended to Full Council for approva... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies