City of York Council
Corporate Scrutiny Committee, Monday 6 July 2026 at 5.30pm

Local Net Zero Accelerator (City Leap Accelerator) - Strategic Energy Partnership Options Appraisal (5:35pm)

Noted Scrutiny 7 papers

AI summaryCity of York Council's scrutiny committee noted the Local Net Zero Accelerator options appraisal and approved its approach, retaining oversight of proposals for five shortlisted energy delivery models [D] [P17].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedReport noted to provide scrutiny oversight [D]
MoneyNot stated
What happens nextFurther appraisal and engagement [P17] [P18]Formal senior engagement plan remains outstanding [P17]
Who it affectsRegional net zero delivery [P7]York and North Yorkshire energy projects [P5] [P7]

What was decided

The committee noted the detailed options appraisal report and approved the approach [D].

The report said further work was required to inform the preferred model decision and presented a shortlist of five delivery models [P17] [P18]. Report P17, P18

The organisational appetite ranking put the Strategic Partner Led Contractual Joint Venture first with 148, then Combined In House Model with 137, Regional Company with 132, and Strategic Partner Led Corporate Joint Venture with 126, although the report said scores could be adjusted [P98]. Report P98

Why

The stated reason was to ensure scrutiny oversight of proposals for the proposed Local Net Zero Accelerator programme [D].

The options were tested against shared requirements for governance, capacity, project funding, delivery, finance, community benefit, economic opportunity and carbon reduction [P5] [P13] [P14] [P15] [P16]. Report P5, P13, P14, P15, P16

The programme aims to accelerate regional energy independence, economic transformation and healthy communities, with York and North Yorkshire becoming England's first carbon negative region [P4] [P7]. Report P4, P7

What happens next

Undertake the formal senior stakeholder engagement plan, which had not yet been undertaken [P17]. Report P17

Define the core partner offering, assess core and wider projects, create bundles and complete robust financial and commercial modelling [P20]. Report P20

Co-design joint decision making and governance across YNYCA, CYC and NYC, including model specific structures, control mechanisms and risk and reward allocation [P20]. Report P20

Options considered

  • Chosen: Further appraise the Strategic Partner Led Contractual Joint Venture. It ranked first for organisational appetite with 148 and uses a contract rather than a separate entity [P78] [P98]. Report P78, P98
  • Chosen: Further appraise the Combined In House Model. It combines in house and private sector capacity and can cover small initiatives through large scale developments [P33]. Report P33
  • Chosen: Further appraise the Regional Company. It ranked third for organisational appetite with 132 and is retained for comparative appraisal [P17] [P98]. Report P17, P98
  • Chosen: Further appraise the Strategic Partner Led Corporate Joint Venture. It tests whether the Bristol City Leap model can be replicated and would use a separate legal entity [P103] [P105]. Report P103, P105
  • Chosen: Further appraise Business As Usual (Do Nothing). It is included under the HM Treasury Green Book as a benchmark for comparison, baseline and value for money [P21]. Report P21

Implications

  • Financial: Before the preferred model decision, the programme needs assessment of affordability, fundability, returns, public capital and blended finance routes [P18] [P20]. Report P18, P20
  • Legal: Joint governance and decision agreements are needed across YNYCA, CYC and NYC, with model specific structures and control mechanisms [P20]. Report P20
  • Risk: Under the Combined In House Model, YNY would remain exposed to delivery risk and the model would require significant cornerstone investment [P75] [P76]. Report P75, P76
  • Risk: The Contractual Joint Venture reduces authorities' financial exposure but depends on robust contracts and risk and reward negotiation [P101] [P102]. Report P101, P102
  • Staffing: If used, the Combined In House Model would require increased FTE, a pooled team and procurement capacity [P50] [P52]. Report P50, P52
  • Climate: The programme's stated aim is to accelerate decarbonisation and make York and North Yorkshire England's first carbon negative region [P4] [P7] [P16]. Report P4, P7, P16
  • Equalities: The framework includes tackling fuel poverty, warmer homes, lower energy bills, local supply chains, community ownership and wider social benefits [P15] [P16]. Report P15, P16
  • Other: Model choice will affect strategic control, delivery pace, scale and the split between public and private delivery [P64] [P89] [P95]. Report P64, P89, P95

Who and where

  • City of York Council Report P20
  • North Yorkshire Council Report P20
  • York and North Yorkshire Combined Authority Report P20
  • Prospective strategic energy partners Report P78, P103
  • Local communities Report P16
  • Regional energy businesses and supply chains Report P15, P16
  • Residents facing fuel poverty Report P16

Timeline

  • February 2025: EY completed the initial options appraisal report [P2]. Report P2
  • Thus far: Shortlisted models had received brief socialisation in CYC and the CA, but formal senior engagement had not been undertaken [P17]. Report P17
  • In progress: Work on the Delivery Mode Commercial Assessment Tool was in progress [P17]. Report P17

Plain English for the jargon

  • Business As Usual (Do Nothing): The benchmark option used to compare proposals, measure improvement and assess value for money [P21].
  • Combined In House Model: A joint governance board with a centralised team based in one place, pooled resources and private expertise obtained as needed [P50].
  • Strategic Partner Led Contractual Joint Venture: A collaboration where partners agree terms through a contract without creating a separate entity [P78].
  • Strategic Partner Led Corporate Joint Venture: A jointly owned company allowing a partner to operate public assets or services for a set period under a concession agreement [P103].
  • Organisational appetite: The assessment of each authority's willingness and ability to undertake each delivery model, including control, risk, reward, time and resources [P16].
  • Investment Readiness Facility: A dedicated regional development fund that establishes project readiness but has no route to market [P38].
  • Limited Partner Fund: A fund using cornerstone investment to attract private investment and finance commercially investable regional projects [P50].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

That the report be noted and the approach approved. Reason: To ensure that scrutiny had oversight of the proposals for the proposed Local Net Zero Accelerator programme.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Corporate Scrutiny Committee, 90 pages

Strategic Energy Pilot

Detailed Options Appraisal Contents 1. Options Appraisal Process 5. Strategic Partner-Led Corporate Joint Venture Summary Justification of Inclusion SEP Long-List Model Summary Strategic Aim, Objectives, & Outcomes Typical Project Route Strategic Objectives Analysis Other Notable Considerations Organisational Appetite Appraisal Strategic Objectives Analysis Stakeholder Engagement Organisational Appetite Analysis SEP Short-List & Synergies Risk / Reward Analysis Next Steps Qualitative SWOT Analysis 2. Business As Usual (Do Nothing) 6. Regional Company (Do Maximum) Justification of Inclusion Justification of Inclusion Drivers and Considerations Model Summary Strategic Objectives Analysis Typical Project Route 3. Combined In-House Model Other Notable Considerations Justification of Inclusion Strategic Objectives Analysis Model Summary Organisational Appetite Analysis Typical Project Route Risk / Reward Analysis Other Notable Considerations Qualitative SWOT Analysis Strategic Objectives Analysis 7. Summary Organisational Appetite Analysis Strategic Objectives Analysis Overview Risk / Reward Analysis Organisation Appetite Analysis Ranking Qualitative SWOT Analysis Risk / Reward Analysis Summary 4. Strategic Partner-Led Contractual Joint Venture Recommendations Justification of Inclusion 8. Appendix Model Summary Longlist Options Appraisal Content Typical Project Route Community Energy & Community Benefit Analysis Summary Other Notable Considerations Strategic Objectives Analysis Organisational Appetite Analysis Risk / Reward Analysis Qualitative SWOT Analysis Options Appraisal Process Summary & Longlist identification Identification of Strategic Energy An initial options appraisal report was completed by consultants EY in February 2025. The process involved initial engagement of key stakeholders within the CA, CYC, and NYC and consulting Bristol Pilot Longlist City Leap to identify lessons learnt and practical insights. The report identified several potential delivery models to accelerate the pace of decarbonisation development and delivery, providing a high-level evaluation of each model. Crucially, the report highlighted a series of key considerations and next steps. Definition of Strategic Aim, The project team utilised this report to develop this work package forward, undertaking further Objectives, & Outcomes exploratory research, multiple key stakeholder workshops and further analysis according to defined criteria, aim, objectives and intended outcomes of the programme.

The first outcome of this process identified multiple potential model options in addition to those of EY’s initial report to analyse. It was also recognised that the combination or variation within models Strategic Objectives Analysis resulted in the multiplicity of options demonstrated in the following list. (Note: not all were considered in the longlist due to initial filtering of requirements)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A_-_LNZA_SEP_Detailed_Options_Appraisal_Report[1]Report 90 pages DownloadRead as text
PDF
B_-_Options_Assessment_Themes[1]Report 6 pages Download
PDF
C_-_Strategic_Objectives_&_Appraisal[1]Report 38 pages Download
PDF
D: Appetite Appraisal ScoringReport 21 pages Download
PDF
E_-_Dimensional_Appraisal_Scoring[1]Report 2 pages Download
PDF
Local Net Zero Accelerator (City Leap Accelerator): Strategic Energy Partnership Options Appraisal (5:35pm)Report 21 pages Download
PDF
View item 12. as HTML 153 KBReport 153 KB Copy on its way

At this meeting

Whole meeting
12Local Net Zero Accelerator (City Leap Accelerator) - Strategic Energy Partnership Options Appraisal (5:35pm)This decision
13City of York Council Boundary Commission – Phase 2 Ward Boundaries Council Submission (6:12pm)Decided 14Draft Scrutiny Annual Report (6:16pm)Approved 15Work Plan (6:34pm)Noted

Who was there

9 of 11 attended
SF
Councillor Stephen FentonChair, present
DM
Councillor Dave MerrettCommittee Member, present
NA
Councillor Nigel AyreCommittee Member, present
AB
Councillor Anna BaxterVice-Chair, apologies
JC
Councillor Jo ColesCommittee Member, present
EN
Councillor Emily NelsonCommittee Member, apologies
KT
Councillor Kallum TaylorCommittee Member, present
RW
Councillor Richard WatsonCommittee Member, apologies, sent representative
PW
Councillor Paula WiddowsonCommittee Member, apologies, sent representative
TF
Councillor Tony FisherSubstitute, present as substitute
PH
Councillor Paul HealeySubstitute, present as substitute

On this subject at York

Search all
  1. Local Net Zero Accelerator (City Leap Accelerator) - Strategic Energy Partnership Options Appraisal (5:35pm)This decision
  2. Local Cycling and Walking Infrastructure Plan: Networks & PrioritisationDecided
  3. Biodiversity Net Gain (including information on Local Nature Recovery Strategy) (19:36)Noted
  4. Thanet Road Local Safety SchemeApproved
  5. Application for Community Right to Bid under the Localism Act 2011 - Lord Nelson Public House, Nether PoppletonApproved
  6. LINks (Local Involvement Network) Statutory Stakeholder GroupNoted

More from York Corporate Scrutiny Committee

All decisions
MeetingDecisionOutcome
9 Nov 2026 Minutes (5.41 pm)That the minutes be approved as a correct record for the meeting held on 7 September 2026. Approved Open
9 Nov 2026 Equity, Diversity and Inclusion (EDI) Strategy refresh (5.41 pm)That the report be noted and the comments of the Committee be included in the report to the Executive Member Decision... Noted Open
9 Nov 2026 Annual Complaints Performance and Service Improvement (6.16 pm)That the report be noted. Reason: To ensure scrutiny oversight of complaint handling performance and organisational l... Noted Open
9 Nov 2026 Council Motions (7.05 pm)That the contents of Annex A be noted and the motions listed above be closed. Reason: To ensure that the process for ... Noted Open
9 Nov 2026 Petitions Schedule (7.18 pm)That the schedule of petitions be noted, and those petitions listed above be closed. Reason: To ensure the Committee ... Noted Open