Place Scrutiny Committee, Tuesday 21 July 2026 at 5.30pm

York Central Mayoral Development Zone (17:54)

Decided Scrutiny 5 papers

AI summaryThe Place Scrutiny Committee recommended that the Council make a request concerning York Central. [D] The report asks for three Mayoral Development Zones in principle, with £10m for regeneration and £500k for capacity. [P3] [P7] [P8]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedRelates to York Central MDZ proposal [D] [P52]
Money£10m and £500k [P7] [P8]Regeneration fund and Combined Authority capacity [P7] [P8]
What happens nextCombined Authority decision sought [P3]In principle designation and delegated launch [P3] [P5]
Who it affectsYork, Scarborough and Selby [13.1]Could deliver 3,000 new homes [P43]

What was decided

The committee recommended that the Council make a request concerning York Central. [D]

Why

York Central covers 45 hectares, has outline planning in place, an appointed joint venture partner and £135m of unlocking site infrastructure nearing completion. [4.16] Report 4.16

The completed development could deliver 3,000 new homes, 1.4m sq. ft of commercial and retail space and 10,000 new jobs. [P43] Report P43

A Mayoral Development Corporation is not required because the site has no land ownership or planning barriers. [4.20] An MDZ would signal regional priority and help align government commitments and funding. [4.20] [4.7] Report 4.20, 4.7

What happens next

Ask the Combined Authority Cabinet to approve all three designations in principle and delegate boundary approval, launch administration and any advisory board appointments. [P3] [P4] [P5] [P6] Report P3, P4, P5, P6

The Combined Authority and each relevant council would define the redline boundary, primary aims and governance before formal launch. [6.2] Report 6.2

Each funding allocation would need a detailed business case and appraisal, with final allocation decisions remaining with Cabinet. [5.5] [6.4] [P70] Report 5.5, 6.4, P70

The money

  • £10m Ringfenced capital fund for all three zones. Report P7, 5.5
  • £500k Capacity funding for development, administration and technical support. Report P8, 5.6, 6.5
  • £135m York Central site infrastructure nearing completion. Report 4.16
  • up to £8m Proposed Scarborough allocation based on scheme maturity and leverage. Report 7.1
  • £5m Remaining capital Mayoral Investment Funding contribution. Report 5.5, 7.1
  • £5m Local Growth Fund capital contribution. Report 5.5, 7.1
  • £22m Capital element of the Local Growth Fund. Report 5.5
  • £5m to £15m Typical establishment cost for an MDC. Report 4.4

Options considered

  • Chosen: York Central Mayoral Development Zone designation. The report recommends approval in principle. It would coordinate public and private investment, signal regional commitment and help align government commitments and funding. [P3] [4.7] [4.20] Report P3, 4.7, 4.20
  • Rejected: Mayoral Development Corporation for York Central. The report says one is not required at this stage because there are no land ownership or planning barriers. [4.20] Report 4.20

Implications

  • Financial: Only the region's MDZs can use the £10m fund, with allocations subject to business cases, appraisal and further Cabinet decisions. [5.5] [6.4] [P70] MDZs create no ongoing baseline revenue liabilities, so commitments will be considered for each scheme through the existing investment and assurance processes. [7.3] Report 5.5, 6.4, P70, 7.3
  • Legal: MDZs have no formal legal status, need no approval beyond the Combined Authority and do not change the legal status of the area. [6.1] [9.1] Report 6.1, 9.1
  • Legal: If priorities require procurement, all works or services must follow a compliant, open, transparent and fair process. [8.1] Commercial Procurement must be consulted before services begin. [8.2] Report 8.1, 8.2
  • Equalities: No specific equalities implications arise from designation in principle. [10.1] The proposed zones target deprived areas and aim to improve opportunities and life chances. [10.1] Report 10.1
  • Climate: The designation has no specific environmental considerations. [12.1] Future projects funded through the zones must have their environmental implications considered. [12.1] Report 12.1
  • Staffing: No immediate human resource implications are identified. [11.1] The £500k capacity funding is profiled over two years to cover a strategic programme manager, framework delivery partner and corporate support. [7.2] Report 11.1, 7.2
  • Risk: York Central still needs grant funding for its 40% affordable housing ambition, has viability gaps for the Innovation Hub and faces volatile commercial returns. [4.19] Report 4.19
  • Other: Any new MDZ Advisory Board would advise only, with Cabinet remaining the decision making body. [5.4] Meetings would not be public because of commercial sensitivities, but 6 monthly update reports would go to the Combined Authority. [6.3] Report 6.3

Who and where

  • City of York Council Report 5.2
  • North Yorkshire Council Report 5.2
  • Mayor and Combined Authority Cabinet Report P5, P6
  • York Central landowners and developers Report 4.20
  • Scarborough residents Report 4.9
  • Communities in York and Selby Report 3.3
  • Private sector developers and landowners Report 4.7, 5.3
  • Combined Authority staff Report 6.5, 7.2

Timeline

  • 2026-07-21: The Place Scrutiny Committee made its recommendation on item 13.
  • over a two year period: The £500k capacity funding will be profiled. Report 7.2
  • 6 monthly: Update reports on an MDZ Advisory Board would go to the Combined Authority. Report 6.3
  • early 2027: York Central development could start if detailed planning permission is secured and viability gaps are resolved. Report 4.16

Plain English for the jargon

  • Mayoral Development Zone: A Mayoral designation of a geographical area where regeneration is a priority. [4.1] It provides a framework for coordinated development and investment without statutory burdens. [4.7] It has no formal legal status. [9.1]
  • Mayoral Development Corporation: A statutory delivery body requiring Secretary of State approval under the Localism Act 2011. [4.2] It can assemble land and infrastructure and take on full planning powers. [4.2]
  • MDZ Regeneration Fund: An initial £10m capital fund for regeneration opportunities within the region's MDZs. [5.5] Allocations need detailed business cases, appraisal and further Cabinet decisions. [5.5] [6.4]
  • Redline boundary: The boundary of an MDZ and the key sites within it. [P62] It is agreed with the relevant local authority before launch. [6.2]
  • MDZ Advisory Board: A Mayor chaired group used where existing governance is insufficient. [5.4] It advises only and is not a formal Combined Authority committee or decision making body. [5.4] [6.3]
  • Mayoral Development Area: A designation that the Mayor may make after consultation and consent. [9.2] It can lead to a Mayoral Development Corporation through secondary legislation. [9.2]
  • Brownfield development: Development on former railway land, such as the York Central site. [4.16]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

i. To recommend that the Council request that York ... view the full minutes text for item 13.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Place Scrutiny Committee, 16 pages

Purpose of the report

1.1This report sets out the proposal to designate Scarborough, the Selby Growth Corridor and York Central as Mayoral Development Zones to accelerate and drive the regeneration of the region’s key development opportunities.

Recommendations

2.1It is recommended that the Combined Authority Cabinet:

2.1.1 Approve in principle the designation of Scarborough, Selby Growth Corridor and York Central as Mayoral Development Zones (MDZs)

2.1.2 Delegate to the Mayor, in agreement with the Lead Member of the relevant local authority, approval of the redline boundary of each MDZ

2.1.3 Delegate to the Director of Economy, in consultation with the Mayor, the administration of the processes required to designate and launch the three MDZs in agreement with the relevant local authorities

2.1.4 Delegate to the Mayor, in consultation with the Lead Member of the relevant local authority, the creation and appointments to any MDZ Advisory Board structures required where existing governance is not deemed sufficient

2.1.5 Approve the ringfencing of an initial £10m capital MDZ Regeneration Fund from Mayoral Investment Funding and Local Growth Funding

2.1.6 Approve the creation of £500k capacity fund to develop and administer the MDZs from Local Growth Fund revenue

OFFICIAL 3.0 Background

3.1In the last year the Combined Authority have undertaken significant appraisals of the range of regeneration and development opportunities across the region. This analysis has informed two significant submissions to government funding programmes – the Business Rates Retention Zone (BRRZ) submission and the Strategic Sites Accelerator submission.

3.2Through engagement with City of York Council and North Yorkshire Council, officers have identified York, Scarborough and Selby as key priority locations for the region. There are a number of reasons for this prioritisation, including:

The scale of investible propositions, particularly housing and commercial development, which were identified alongside partners as part of the development of an Investment Pitchbook (available here). The Combined Authority has a key strategic role in ensuring that these sites are unlocked and enable the region to achieve its growth potential. For example:

o York is home to York Central, one of the largest city centre regeneration schemes in the UK, with potential to deliver 2,500 new homes and a bold new Innovation Hub.

o Selby is part of a large-scale generation programme led by North Yorkshire Council, alongside major commercial development opportunities, such as Olympia Park which could create up to 3,250 new jobs and Gascoigne Interchange with potential for 4,500 FTE jobs, to name a few. Given the scale of brownfield land that could be unlocked, officers have also been in discussions with the Ministry of Housing, Communities and Local Government around the levers that could unlock this (such as a Business Rate Retention Zone).

o Scarborough has major brownfield redevelopment opportunities, including quality leisure and tourism developments and prime commercial space opportunities, residential and mix use proposals; alongside 1,000 new homes at Middle Deepdale. North Yorkshire

OFFICIAL Council have also flagged the emerging opportunities at Harrogate as being an area of priority, although not yet as advanced as Scarborough.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Agenda Supplement MDZ July 2026Agenda 7 pages Download
PDF
CA MDZ PaperReport 16 pages DownloadRead as text
PDF
View as HTML (13./3) 64 KBAgenda 64 KB Copy on its way
PDF
View item 13. as HTML 76 KBReport 76 KB Copy on its way
PDF
York Central Mayoral Development Zone (17:54)Report 11 pages Download

At this meeting

Whole meeting

Who was there

12 of 13 attended
DM
Councillor Danny MyersChair, present
TC
Councillor Tony ClarkeCommittee Member, present
SF
Councillor Stephen FentonCommittee Member, apologies, sent representative
PH
Councillor Paul HealeyVice-Chair, apologies, sent representative
AH
Councillor Anne HookCommittee Member, present
AP
Councillor Anna PerrettCommittee Member, present
KT
Councillor Kallum TaylorCommittee Member, present
CV
Councillor Christian VassieCommittee Member, present
CW
Councillor Conrad WhitcroftCommittee Member, apologies, sent representative
KO
Councillor Keith OrrellSubstitute, present as substitute
JR
Councillor Jason RoseSubstitute, present as substitute
AW
Councillor Andrew WallerSubstitute, present as substitute

All 13 on the meeting page

On this subject at York

Search all
  1. York Central Mayoral Development Zone (17:54)This decision
  2. York Central Mayoral Development Zone (5:02pm)Agreed
  3. York Central Land Disposal (5:20pm)Approved
  4. York Central Update (5.38 pm)Noted
  5. York Central Update (5.38 pm)Decided
  6. York Central Update (5.34 pm)Decided

More from York Place Scrutiny Committee

All decisions
MeetingDecisionOutcome
21 Jul 2026 Minutes (17:50)That the minutes of the Place Scrutiny Committee on 16 June 2026 be signed as a correct record of the meeting. Decided Open
21 Jul 2026 Work Plan (20:38)i. Noted the Committee work plan. Reason: To ensure the Committee maintains a programme of work. Noted Open
16 Jun 2026 Minutes (17:32)That the minutes of the Place Scrutiny Committee on 24 March 2026 and 19 May 2026 be signed as a correct record of th... Decided Open
16 Jun 2026 Work Plan (19:47)i. Noted that the Committee work plan. Reason: To ensure the Committee maintains a programme of work. Noted Open
19 May 2026 Minutes (17:37)That the minutes of the Place Scrutiny Committee on 26 Janaury 2026 be signed as a correct record of the meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies