AI summaryCity of York Council's Audit and Governance Committee noted the draft 2025/26 Annual Governance Statement, which found governance arrangements fit for purpose but flagged a major capital project control weakness, and directed that Accounts and treasury Management training be organised for members.
Written from the decision and the officer reportPDF Pro
OutcomeNotedArrangements met their purpose, with a capital project weakness.
MoneyNot stated
What happens nextOrganise committee accounts trainingTraining will cover Accounts and treasury Management.
Who it affectsCommittee membersMembers will have an opportunity to review the draft.
What was decided
The Committee noted the draft Annual Governance Statement for the financial year ended 31 March 2026.
Training will be organised for the Committee on Accounts and treasury Management.
Why
The stated reason for the training was to ensure Members had the opportunity to review the draft Annual Governance Statement.
The draft concludes that governance arrangements met their purpose by supporting lawful and open operation, proper control of public money, risk management and continuous improvement. Report P7, P8
Internal Audit gave Reasonable Assurance, but identified one significant control weakness in the governance and management of major capital projects. Report P91, P93, P94
What happens next
Training will be organised for the Committee on Accounts and treasury Management.
Action in the coming financial year will cover project cost monitoring, staff resource impacts and better use of scrutiny, with success reflected in the 26/27 AGS. Report P15, P16
Officers are developing a capital programme resource plan to secure the right skills and capacity, and the major project action plan is monitored through Audit and Governance Committee. Report P118
Implications
Risk: Major capital project governance has a significant control weakness, and External Audit found a significant weakness in the 24/25 value for money arrangements. Report P94, P102
Financial: Weak oversight before delivery has led to contracts at risk and additional costs during delivery. Report P95
Staffing: Major projects also face a lack of skills and support capacity and over reliance on external expertise. Report P95
Financial: Funding reductions, cost pressures and Adult Social Care overspend risk remain significant, while resizing could leave the Council with insufficient resources. Report P114, P117
Legal: The Yorhome legal review remains ongoing, with active steps in place to resolve outstanding legal and liability issues. Report P120
Equalities: Historic equal pay matters remain unresolved and have both financial and equality impacts. Report P119
Other: Potential and actual personal data breaches increased during the financial year, and the Information Commissioners Office required no further action on the one significant breach reported. Report P105, P106
Other: The Housing Regulator's C2 grade confirms standards overall but requires improvement for consistent, high quality services for all tenants. Report P14
Who and where
Audit and Governance Committee members
City of York Council
Council staff and officers Report P72, P73
Residents, service users and communities Report P8, P65
Major capital project teams and external advisers Report P71, P95
February 2026: The Housing Regulator gave the Council's Housing service a C2 grade and required further improvement. Report P14
31 March 2026: The financial year covered by the draft Annual Governance Statement ended.
coming financial year: Project cost monitoring, staff resource impacts and better scrutiny were targeted for action. Report P15, P16
26/27 AGS: Success in strengthening the three governance areas was to be reflected. Report P16
6 May 2026: The Internal Audit Annual Report for 2025/26 was presented to Audit and Governance Committee. Report P97
September/ October 2026: The external audit of the 2025/26 accounts was due to commence. Report P101
before September 2028: Veritau was due to receive an external assessment against the UK public sector internal audit standards. Report P99
2027: The next inspection of the Council's use of investigatory powers and covert surveillance was due. Report P108
Plain English for the jargon
Annual Governance Statement: Statement showing how the Council complied with its local code and reviewed the effectiveness of governance arrangements.
CIPFA/SOLACE Framework: Good practice framework setting out seven principles for delivering governance in local government.
Local Code of Corporate Governance: Council code aimed at directing resources properly, supporting inclusive decisions and ensuring accountability.
Internal control: System for managing risk to a reasonable level, not removing every risk of failure.
Reasonable Assurance: Head of Internal Audit's overall opinion on the Council's governance, risk management and control framework.
Section 151 Officer: Statutory finance officer involved in financial control, reporting, decision making and compliance with codes.
Capital Programme Delivery Board: Board providing monthly review of capital programme assurance.
Medium Term Financial Plan: Plan aligning available resources with Council Plan activities and setting financial plans for the next 3 to 4 years.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
i. Noted the draft Annual Governance Statement for the financial year ended 31 March 2026. ii. That training be organised for the Committee on the Accounts and treasury Management. Reason: To ensure that Members have had the opportunity to review the draft Annual Governance Statement.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Audit and Governance Committee, 39 pages
Executive summary
What are our Governance arrangements and are they fit for purpose?
Our governance arrangements are the systems and processes which enable us to make sound decisions with high-quality information, and a good understanding of risk. Those systems rely on strong leadership, engagement with communities and stakeholders and a laser focus on the public interest.
Alongside many Councils, City of York Council (“the Council”) continues to experience pressure on financial resources. The Council is determined, despite its financial challenges, to continuously improve1. This requires innovative approaches to service delivery and taking difficult decisions. Our governance arrangements are crucial in getting those difficult decisions right.
The Council has adopted a Local Code of Corporate Governance which is consistent with the seven principles set out in “proper practice” for the public sector, namely Delivering Good Governance in Local Government: Framework published by CIPFA/SOLACE 2016 (the Framework”).2
The overall aim of the Local Code of Corporate Governance is to ensure that: • Resources are directed in accordance with agreed policy and according to priorities; • There is sound and inclusive decision making; • There is clear accountability for the use of those resources in order to achieve desired outcomes for service users and communities.
A copy of our Local Code is available on our website at www.york.gov.uk/CorporateGovernance
This Annual Governance Statement (“AGS”) for 2025-2026 demonstrates how we have complied with our local code and reviews its effectiveness. The conclusion of this AGS is that our governance arrangements have, during the past year, met their purpose in ensuring we:.
• operate in a lawful, open, inclusive, and honest manner; • make sure public money is safeguarded, properly accounted for, and spent wisely; • have effective arrangements in place to manage and control risk; • secure continuous improvements in the way we operate.
Governance Outlook and areas for action
1 The Council has a duty under the Local Government Act 1999 to make arrangements to secure continuous improvement in the way in which its functions are exercised, having regard to a combination of economy, efficiency, and effectiveness. 2 An addendum to the Framework was published in January 2025. Authorities should ensure that the AGS for 2025/26 onwards comply with this amended guidance, and they are encouraged to consider it for 2024/25.
2 The Council is satisfied the current arrangements have adequately supported the purpose of guiding decision making which focuses on achievement of the authority’s aims and manages risk. We strive however to maintain a self awareness which facilitates continuous improvement.
The Council continues to respond positively when areas for improvement come to light. During the year, where issues have been identified these have been dealt with in an open and transparent way, often including public reports to Executive. This enables the Council to learn from any mistakes and embed lessons into future planning.
During March 2025, Children’s Services was inspected by Ofsted and rated as outstanding in all areas. Ofsted particularly praised the council’s “relentless drive”, strong leadership and commitment to putting children first.
In February 2026, the Housing service was inspected by the Housing Regulator and gave a C2 grade for the Council. A C2 grade confirms that the Council is meeting the regulators standards overall but that improvements are required to ensure consistent, high quality services for all tenants.
Our annual review process identified areas for development around: • Monitoring and reporting of project costs to allow for timely escalation and intervention • Understanding the impact of staff resources on the ability to deliver projects and services • Making better use of scrutiny.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.