Matter journeys/Medway/Planning application

Elmsleigh Lodge development

Medway5 meetings since 21 September 2016MC/16/2653Decided 10 May 2017
231 daysto decision, typical 49
2 deferralsalong the way
10 Maydecided

Every meeting Pro

Planning Committee21 Sep 2016Deferred
Planning Committee16 Nov 2016Deferred
56 days after the step before
Planning Committee14 Dec 2016Withdrawn
28 days after the step before
Planning Committee18 Jan 2017Withdrawn
35 days after the step before
Planning Committee10 May 2017Approved
112 days after the step before

Read what each meeting decided, in its own words, and get an email when this matter is next on an agenda.