Spelthorne's Corporate Policy and Resources Committee on 12 October 2026 rejected a procurement to modify the contract of the Head of LGR and Special Projects, while approving the disposal of 12 Hammersmith Grove for recommendation to full Council. The Committee also authorised £150,000 for new ICT servers, approved £52,026 in irrecoverable debt write-offs, and backed a Housing Delivery Plan from Inner Circle Consulting for the new West Surrey Authority.
The Committee rejected a procurement to modify the Head of LGR and Special Projects contract to support Spelthorne's transition into West Surrey, despite the post being funded within the current budget.
The Committee recommended to Council approval of the disposal of 12 Hammersmith Grove, delegating authority to officers to finalise terms and complete the transfer.
The Committee authorised procurement of new ICT servers up to a maximum of £150,000 as existing servers were past end-of-life and cloud storage was not economically viable.
The Committee approved write-offs of £52,026 in irrecoverable Sundry Debt and Housing Benefits, with all recovery avenues exhausted.
The Committee approved and ordered publication of the Annual Commercial Property Report for 2025/26, noting the Elmsleigh Shopping Centre achieved 100% occupancy.
The Committee approved procurement of Inner Circle Consulting to produce an evidence-led Housing Delivery Plan for the West Surrey Authority.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.