Resolved

The Joint Strategic Committee noted the increased cost of the extension to WADURS swimming pool and replacement boilers; approved the use of the following budgets allocated for 2 projects; roofing and glazing (£84,750.00) and electrical rewiring (£34,000.00) for Lancing Leisure Centre to be re-allocated in order to fund the changing room and M&E works project at WADURS; as a result of the failed bid to Veolia, approved the use of £40k of the current revenue budget underspend to ensure that the project progressed in the current financial year; noted that planning approval had been granted for the project at the September 2019 Adur Planning Committee. Call In: The call-in deadline for this decision will be 5.00pm on 20 September 2019.
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1. Purpose 1.1 The purpose of this report is to seek approval to move funding from other approved Adur Community Leisure (ACL - known as Impulse Leisure) capital projects to fund the new changing room and M&E works at Wadurs Swimming Pool. This is due to an identified budget shortfall following a recent tender process for the project.

2. Recommendations 2.1 The Joint Strategic Committee is recommended to:

● Notes the increased cost of the extension to WADURS swimming pool and replacement boilers;

● Approves the use of the following budgets allocated for 2 projects; roofing and glazing (£84,750.00) and electrical rewiring (£34,000.00) for Lancing Leisure Centre to be re-allocated in order to fund the changing room and M&E works project at WADURS.

● Notes that Adur Community Leisure (ACL) have bid for £40,000 funding from Veolia to enable sufficient funding to be available for the project to proceed. ACL will not know the outcome of the bid until 3rd September 2019.

● Approves that if ACL are unsuccessful in their bid, that £40k of the current revenue budget underspend is utilised to ensure that the project progresses in the current financial year.

● Notes that the project is dependent upon planning approval being granted, as due to the imminent expiry of the current planning approval, a new planning application has had to be submitted. A decision is expected after the September 2019 Planning Committee.

3. Context

3.01Wadurs is one of three popular leisure sites, owned by Adur District Council, and managed by Adur Community Leisure, known as Impulse Leisure. Impulse Leisure is a charity that provides affordable, accessible, leisure opportunities to our communities. They not only provide traditional sporting and leisure activities, but are connected with the Councils health and wellbeing teams, providing activities for those referred via their GP and are one of the key providers of support for people of all ages wanting to increase activity levels and connect with other residents in their area. The Council has a formal funding and management arrangement with Impulse Leisure and is responsible for certain capital projects, which are subject to the same governance arrangements as any other scheme.

3.02Wadurs (a swimming facility) is benefiting from increased attendances and record delivery of swimming lessons, with over 900 pupils registered into the swim school. The facility suffers however, with small cramped changing facilities which cause logistical issues for staff and customers and does not provide a good customer experience. Overall there is a concern that this is unsustainable in the long term and will affect the current and future use of the pool.

3.03Currently staff have to walk through the existing changing rooms and across an access way, which is open to the elements, to a portacabin which is being used as an office and staff facilities. This is not ideal when classes and lessons are taking place.

3.04The proposal is to provide modern and enlarged changing room facilities including a ‘changing places’ facility.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Wadurs: Changing Room extension and M&E WorksReport 174 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
DH
Councillor Daniel HumphreysChairman, present
NP
Councillor Neil ParkinCommittee Member, absent
AD
Councillor Angus DunnAdur Member, present
KJ
Councillor Kevin JenkinsWorthing Member, present
CA
Councillor Carson AlburyAdur Member, present
BB
Councillor Brian BoggisAdur Member, present
EC
Councillor Edward CrouchWorthing Member, present
EE
Councillor Emma EvansCommittee Member, absent
DH
Councillor Dr Heather MercerCommittee Member, absent
DS
Councillor David SimmonsAdur Member, present
ES
Councillor Elizabeth SparkesWorthing Member, present
VT
Councillor Val TurnerWorthing Member, present

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies