The Joint Strategic Committee noted the increased cost of the extension to WADURS swimming pool and replacement boilers; approved the use of the following budgets allocated for 2 projects; roofing and glazing (£84,750.00) and electrical rewiring (£34,000.00) for Lancing Leisure Centre to be re-allocated in order to fund the changing room and M&E works project at WADURS; as a result of the failed bid to Veolia, approved the use of £40k of the current revenue budget underspend to ensure that the project progressed in the current financial year; noted that planning approval had been granted for the project at the September 2019 Adur Planning Committee. Call In: The call-in deadline for this decision will be 5.00pm on 20 September 2019.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1. Purpose 1.1 The purpose of this report is to seek approval to move funding from other approved Adur Community Leisure (ACL - known as Impulse Leisure) capital projects to fund the new changing room and M&E works at Wadurs Swimming Pool. This is due to an identified budget shortfall following a recent tender process for the project.
2. Recommendations 2.1 The Joint Strategic Committee is recommended to:
● Notes the increased cost of the extension to WADURS swimming pool and replacement boilers;
● Approves the use of the following budgets allocated for 2 projects; roofing and glazing (£84,750.00) and electrical rewiring (£34,000.00) for Lancing Leisure Centre to be re-allocated in order to fund the changing room and M&E works project at WADURS.
● Notes that Adur Community Leisure (ACL) have bid for £40,000 funding from Veolia to enable sufficient funding to be available for the project to proceed. ACL will not know the outcome of the bid until 3rd September 2019.
● Approves that if ACL are unsuccessful in their bid, that £40k of the current revenue budget underspend is utilised to ensure that the project progresses in the current financial year.
● Notes that the project is dependent upon planning approval being granted, as due to the imminent expiry of the current planning approval, a new planning application has had to be submitted. A decision is expected after the September 2019 Planning Committee.
3. Context
3.01Wadurs is one of three popular leisure sites, owned by Adur District Council, and managed by Adur Community Leisure, known as Impulse Leisure. Impulse Leisure is a charity that provides affordable, accessible, leisure opportunities to our communities. They not only provide traditional sporting and leisure activities, but are connected with the Councils health and wellbeing teams, providing activities for those referred via their GP and are one of the key providers of support for people of all ages wanting to increase activity levels and connect with other residents in their area. The Council has a formal funding and management arrangement with Impulse Leisure and is responsible for certain capital projects, which are subject to the same governance arrangements as any other scheme.
3.02Wadurs (a swimming facility) is benefiting from increased attendances and record delivery of swimming lessons, with over 900 pupils registered into the swim school. The facility suffers however, with small cramped changing facilities which cause logistical issues for staff and customers and does not provide a good customer experience. Overall there is a concern that this is unsustainable in the long term and will affect the current and future use of the pool.
3.03Currently staff have to walk through the existing changing rooms and across an access way, which is open to the elements, to a portacabin which is being used as an office and staff facilities. This is not ideal when classes and lessons are taking place.
3.04The proposal is to provide modern and enlarged changing room facilities including a ‘changing places’ facility.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.