1st Quarter Capital Investment Programme & Projects Monitoring 2019/20

Noted Committee 1 paper

Joint Strategic Committee noted this item on Tuesday 10 September 2019. Below is the council's own wording, with the papers it was decided on.

ItemJSC2919-20

Resolved

The Joint Strategic Committee:- a) with respect to the Capital Investment Programme of Adur District Council i. noted the reprofiling of the Adur District Council capital schemes as advised in paragraphs 8.2.1 and Appendix 3; ii. noted that a virement of £50,000 from the DDA coastal footpath to the Southwick Leisure Centre outdoor all weather pitch, as detailed in paragraph 8.2.3, was approved by the Director of Communities to resolve a potential overspend against this budget; iii. noted the confirmation of £590,000 external funding from the Environment Agency towards the Coast Protection Works at Shoreham Western Harbour Arm as detailed in paragraph 8.2.5; iv. approved the addition of the purchase of Trade Refuse Bins to the 2019/20 and 2020/21 Capital Investment Programme funded from revenue contributions of £7,500 p.a.as detailed in paragraph 8.1.2; v. approved the inclusion of Play Area Improvements at Sompting Recreation Ground funded from a virement of £100,800 from the Middle Road Play Area Improvements as detailed in paragraph 8.2.4. b) with respect to the Capital Investment Programme of Worthing Borough Council i. noted the reprofiling of the Worthing Borough Council capital schemes as advised in paragraphs 8.3.1 and Appendix 4; ii. approved the virements from the budget provision for the Town Hall Asbestos Removal to support a re-prioritised scheme of asbestos management surveying and works, Seafront Fire Safety Works Budget and the Durrington Cemetery Extension for Additional Burial Spaces Budget as detailed in paragraph as detailed in paragraph 8.3.3 and 8.3.6; iii. approved the virements to amalgamate all the budgets in the Capital Investment Programme for ... view the full minutes text for item JSC2919-20
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1. PURPOSE 1.1 This report updates the Joint Strategic Committee on the progress made on the 2019/20 Capital Investment Programmes for Adur District Council, Worthing Borough Council. The programmes include schemes which support the delivery of services by the Joint Services Committee.

1.2The following appendices have been attached to this report: Appendix 1: Adur District Council Capital Monitoring Summary Appendix 2: Worthing Borough Council Capital Monitoring Summary Appendix 3: Adur District Council Reprofiled Budgets Appendix 4: Worthing Borough Council Reprofiled Budgets

2. RECOMMENDATIONS 2.1 The Joint Strategic Committee is asked: (a) With respect to the Capital Investment Programme of Adur District Council. i) To note the reprofiling of the Adur District Council capital schemes as advised in paragraphs 8.2.1 and Appendix 3. ii) To note that a virement of £50,000 from the DDA coastal footpath to the Southwick Leisure Centre outdoor all weather pitch as detailed in paragraph 8.2.3 was approved by the Director of Communities to resolve a potential overspend against this budget.

1 iii) To note the confirmation of £590,000 external funding from the Environment Agency towards the Coast Protection Works at Shoreham Western Harbour Arm as detailed in paragraph 8.2.5.

iv) To approve the addition of the purchase of Trade Refuse Bins to the 2019/20 and 2020/21 Capital Investment Programme funded from revenue contributions of £7,500 p.a.as detailed in paragraph 8.1.2.

v) To approve the inclusion of Play Area Improvements at Sompting Recreation Ground funded from a virement of £100,800 from the Middle Road Play Area Improvements as detailed in paragraph 8.2.4.

b) With respect to the Capital Investment Programme of Worthing Borough Council.

i) To note the reprofiling of the Worthing Borough Council capital schemes as advised in paragraphs 8.3.1 and Appendix 4.

ii) To approve the virements from the budget provision for the Town Hall Asbestos Removal to support a re-prioritised scheme of asbestos management surveying and works, Seafront Fire Safety Works Budget and the Durrington Cemetery Extension for Additional Burial Spaces Budget as detailed in paragraph as detailed in paragraph 8.3.3 and 8.3.6.

iii) To approve the virements to amalgamate all the budgets in the Capital Investment Programme for the Brooklands Park Development into one programme of works totalling £502,610 as detailed in paragraph 8.3.7.

iv) To approve the virement of £150,000 from the unallocated public convenience budget to the Highdown Gardens Infrastructure Scheme for the improvement to the Highdown Gardens public convenience detailed in paragraph 8.3.8.

v) To approve the ring-fencing of 2019/20 Capital Investment Programme Contingency as a provision for the internal works to the new Durrington Community Centre to ensure the building is ready for use by a new tenant detailed in paragraph 8.3.9.

vi) To approve the procurement of a cremulator and transfer table for the Crematorium be included in the 2019/20 Capital Investment Programme funded from the 2019/20 Capital Investment Programme General Contingency Budget as detailed in paragraph 8.3.4.

vii) To approve the inclusion of the development of the Crematorium Children’s Garden in the 2019/20 Capital Investment Programme funded from the unallocated Crematorium Improvements Budget in 2020/21 as detailed in paragraph 8.3.5.

viii) To agree to the addition of the purchase of Trade Refuse Bins to the 2019/20 and 2020/21 Capital Investment Programme funded from revenue contributions of £17,500 p.a.as detailed in paragraph 8.1.2.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1st Quarter Capital Investment Programme & Projects Monitoring 2019/20Report 904 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
DH
Councillor Daniel HumphreysChairman, present
NP
Councillor Neil ParkinCommittee Member, absent
AD
Councillor Angus DunnAdur Member, present
KJ
Councillor Kevin JenkinsWorthing Member, present
CA
Councillor Carson AlburyAdur Member, present
BB
Councillor Brian BoggisAdur Member, present
EC
Councillor Edward CrouchWorthing Member, present
EE
Councillor Emma EvansCommittee Member, absent
DH
Councillor Dr Heather MercerCommittee Member, absent
DS
Councillor David SimmonsAdur Member, present
ES
Councillor Elizabeth SparkesWorthing Member, present
VT
Councillor Val TurnerWorthing Member, present

On this subject at Adur & Worthing

Search all
  1. 1st Quarter Capital Investment Programme & Projects Monitoring 2019/20This decision
  2. Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27Approved
  3. Joint 3rd Quarter Capital Investment Programme & Projects Monitoring 2025/26Noted
  4. Joint 2nd Quarter Capital Investment Programme & Projects Monitoring 2025/26Noted
  5. Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2025/26Approved
  6. Joint 3rd Quarter Capital Investment Programme & Projects Monitoring 2024/25Noted

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open