Investing for the future: Capital Programme 2020/21 to 2022/23

Approved Committee 1 paper

Joint Strategic Committee approved this item on Tuesday 3 December 2019. Below is the council's own wording, with the papers it was decided on.

ItemJSC7219-20

Resolved

The Joint Strategic Committee:- (a) considered the General Fund Capital Investment Programmes for 2021/22 and 2022/23 and confirmed the schemes to be included as detailed in Appendix 2, 3 and 4; (b) approved the changes to the General Fund Capital Investment Programme for 2020/21 as detailed in Appendix 2 and 3; (c) approved the Adur District Council Adur Homes Housing Renovation Programme 2021/22 - 2022/23 as detailed in Appendix 5; (d) agreed the amendments and additions to the reserve lists as detailed in Appendices 6 and 7; (e) recommended the 2021/22 and 2022/23 Programmes for approval by the Adur and Worthing Councils on the 19 December 2019 and 17 December 2019 respectively. Call In: The call-in deadline for decisions (a), (b), (c) and (d) will be 5.00pm on 13 December 2019. There is no call-in for recommendations to Council (e).
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1. Purpose

1.1The Councils annually approve a two year capital programme on a rolling basis. This time last year the Councils approved a programme for 2019/20 to 2020/21, members are now asked to approve the programme for 2020/21 - 2021/22 along with a further indicative year. This report recommends:

● changes to the currently approved 2020/21 Capital Investment Programme for Adur District Council, Worthing Borough Council and the Joint Strategic Committee;

● the schemes for inclusion in the overall Capital Investment Programmes for 2021/22; and

● an indicative list of schemes for 2022/23 which will be confirmed next year.

1.2The report also informs the Joint Strategic Committee of the resources available for future capital investment, and updates Members about the financing of the proposed programmes.

1.3The following appendices have been attached to the report:

(i) ​Appendix 1 ​The approved joint prioritisation system; (ii) ​Appendix 2 ​The proposed changes to the current 2020/21 Capital Investment Programme and proposed new schemes to be included for 2021/22 and 2022/23 in the ​Adur District Council General Fund Capital Investment Programmes which is recommended for approval;

(iii) ​ ppendix 3 ​The proposed changes to the current 2020/21 Capital A Investment Programme and proposed new schemes to be included for 2021/22 and 2022/23 in the ​Worthing Borough Council General Fund Capital Investment Programme which is recommended for approval;

(iv) ​Appendix 4 ​The Joint Strategic Committee proposed programme of new Adur District Council and Worthing Borough Council partnership schemes, which is recommended for approval;

(v) Appendix 5 The proposed Adur District Council Adur Homes Housing Renovation Programme 2021/22 - 2022/23, which is recommended for approval;

(vi) ​ ppendix 6 A Amendments and additions to the Adur District Council Reserve List.

(vii) Appendix 7 Amendments and additions to the Worthing Borough Council Reserve List.

2. Recommendations 2.1 The Joint Strategic Committee is recommended to:

(a) Consider the General Fund Capital Investment Programmes for 2021/22 and 2022/23 and confirm the schemes to be included as detailed in Appendix 2, 3 and 4;

(b) Approve the changes to the General Fund Capital Investment Programme for 2020/21 as detailed in Appendix 2 and 3;

(c) Approve the Adur District Council Adur Homes Housing Renovation Programme 2021/22 - 2022/23 as detailed in Appendix 5;

(d) Agree the amendments and additions to the reserve lists as detailed in Appendices 6 and 7;

(e) Recommend the 2021/22 and 2022/23 Programmes for approval by the respective Councils on the 19​th December 2019 (Adur) and 17​th December 2019 (Worthing). 3. Context

3.1The Adur and Worthing Capital Strategy 2020 - 23 was updated and agreed by the Joint Strategic Committee (JSC) on 9​th July, 2019. The financial impact of the proposed Capital Investment Programme was set out in the outline 5 year forecast included in the “Becoming financially Sustainable - Budget Strategy for 2020/21 and beyond” report which was agreed by JSC at the same meeting.

3.2The Capital and Budget Strategies set out the following:

(a) A maximum level of funding available per year for the next 5 years to fund new General Fund schemes:

Adur District Council £1.0m (plus £5.5m in 2020/21 increasing to £5.6m in 2022/22 for the Housing Investment Programme (excluding new developments which are considered separately)

Worthing Borough £2.5m Council:

(b) The Budget Strategy highlighted concerns about affordability in the medium term. Members of both Councils were made aware that the number, age and condition of both Councils’ assets continue to be a cause for concern. The funding of the programmes is to be comprised of prudential borrowing, capital grants, revenue/reserve funding and capital receipts.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Investing for the future: Capital Programme 2020/21 to 2022/23Report 894 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
NT
Neil TerrySecretary, expected
DH
Councillor Daniel HumphreysWorthing Member, present
NP
Councillor Neil ParkinChairman, present
AD
Councillor Angus DunnAdur Member, present
KJ
Councillor Kevin JenkinsWorthing Member, present
CA
Councillor Carson AlburyCommittee Member, absent
BB
Councillor Brian BoggisAdur Member, present
EC
Councillor Edward CrouchWorthing Member, present
EE
Councillor Emma EvansAdur Member, present
DH
Councillor Dr Heather MercerWorthing Member, present
DS
Councillor David SimmonsAdur Member, present
ES
Councillor Elizabeth SparkesWorthing Member, present

All 13 on the meeting page

On this subject at Adur & Worthing

Search all
  1. Investing for the future: Capital Programme 2020/21 to 2022/23This decision
  2. Investing for our future - Capital Strategy 2026-2031Approved
  3. Investing for our future - Capital Strategy 2025-2028Approved
  4. Investing for our future - Capital Strategy 2024/27Approved
  5. Investing for our future - Capital Strategy 2023/26Approved
  6. Investing for our future - Capital Strategy 2022/25Approved

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open