The Joint Strategic Committee:- (a) With respect to the Capital Investment Programme of Adur District Council i ) noted the reprofiling of the Adur District Council capital schemes as advised in paragraphs 7.2.1 and Appendix 3; ii) approved the use of ring-fenced capital receipts to fund the overspend of £16,300 on the Shoreham Air Crash Memorial Project as detailed in paragraph 7.2.3; iii) noted the confirmation of grant funding of £500,000 from the Shoreham Harbour Grant towards the Coast Protection Works at Shoreham Western Harbour Arm as detailed in paragraph 7.2.4; iv) noted the overspend on the purchase of wheeled bins for the new alternate weekly collection service and approved the funding as detailed in paragraph 7.1.2. (b) With respect to the Capital Investment Programme of Worthing Borough Council i ) noted the reprofiling of the Worthing Borough Council capital schemes as advised in paragraphs 7.3.1 and Appendix 4; ii) noted the overspend on the purchase of wheeled bins for the new alternate weekly collection service and approved the funding of the overspend as detailed in paragraph 7.1.2; iii) approved the transfer of funding for urgent health and safety works required to the Assembly Hall and Pavilion Theatre as detailed in paragraph 7.3.2. Call In: The call-in deadline for this decision will be 5.00pm on 13 December 2019.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1This report updates the Joint Strategic Committee on the progress made on the 2019/20 Capital Investment Programmes for Adur District Council, Worthing Borough Council. The programmes include schemes which support the delivery of services by the Joint Services Committee.
1.2The following appendices have been attached to this report:
Appendix 1: Adur District Council Capital Monitoring Summary Appendix 2: Worthing Borough Council Capital Monitoring Summary Appendix 3: Adur District Council Reprofiled Budgets Appendix 4: Worthing Borough Council Reprofiled Budgets
Recommendations
2.1The Joint Strategic Committee is asked: (a) With respect to the Capital Investment Programme of Adur District Council. i) To note the reprofiling of the Adur District Council capital schemes as advised in paragraphs 7.2.1 and Appendix 3.
ii) To approve the use of ring-fenced capital receipts to fund the overspend of £16,300 on the Shoreham Air Crash Memorial Project as detailed in paragraph 7.2.3. iii) To note the confirmation of grant funding of £500,000 from the Shoreham Harbour Grant towards the Coast Protection Works at Shoreham Western Harbour Arm as detailed in paragraph 7.2.4.
iv) To note the overspend on the purchase of wheeled bins for the new alternate weekly collection service and approve the funding as detailed in paragraph 7.1.2.
b) With respect to the Capital Investment Programme of Worthing Borough Council.
i) To note the reprofiling of the Worthing Borough Council capital schemes as advised in paragraphs 7.3.1 and Appendix 4.
ii) To note the overspend on the purchase of wheeled bins for the new alternate weekly collection service and approve the funding of the overspend as detailed in paragraph 7.1.2.
iii) To approve the transfer of funding for urgent health and safety works required to the Assembly Hall and Pavilion Theatre as detailed in paragraph 7.3.2.
3. CONTEXT
3.1In accordance with the Councils’ Capital Strategy, the Capital Working Group oversees the implementation and progress of both Councils’ Capital Investment Programmes.
3.2The Capital Working Group meets quarterly and monitors the programmes’ progress and finance, seeking to address any problems at an early stage in order for schemes to be completed within budget and timescales. Where problems are highlighted the Group considers possible remedies including virements between schemes, reprofiling of budgets between years and the withdrawal of schemes from the programme when schemes are unable to proceed. This could be due to resourcing problems, time delays or other factors beyond the Councils’ control.
3.3Full summaries of the progress of all the schemes in the 2019/20 Capital Investment Programmes are prepared each quarter highlighting: Schemes with significant challenges Red
Schemes where progress is being closely monitored Amber
Schemes progressing well Green
Schemes where progress is beyond officers’ control ◘
Schemes with financial issues £
Schemes where progress has improved ⇧
Schemes where progress has deteriorated ⇩
3.4The Capital Working Group also ensures that capital schemes are approved within financial regulations.
3.5Financial Regulations require officers to report each project on completion detailing the original estimate, tender estimate and the final outturn.
4. SUCCESSES AND CHALLENGES IN THE 2019/20 CAPITAL INVESTMENT PROGRAMMES
4.1The following schemes are progressing well:
4.1.1 Adur Homes Capital Investment Programme
The Adur Homes Capital Investment Programme for 2019/20 and 2020/21 was approved by the Joint Strategic Committee 9th October 2018.
Delivery of the Capital Improvement Programme continues to be shaped by guidance issued to local authorities by the Regulator of Social Housing in the aftermath of the Grenfell fire and better knowledge of our stock.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.