The Joint Strategic Committee: 1. agreed to release further budget for Cecil Norris House of £378,000 to fund the increased costs associated with the Cecil Norris House development which was to be funded from borrowing; 2. recommended that Adur District Council release a budget of £2.8m to fund the Albion Street development funded by prudential borrowing; 3. delegated authority to the Director of Communities in consultation with the Executive Member for Customer Services, that if required, to appropriate for planning purposes the Albion Street Land under section 122 of the Local Government Act 1972 and the use of powers under section 203 of the Housing and Planning Act 2016, subject to obtaining the necessary Secretary of State consents. Call In: The call-in deadline for decisions 1 and 3 will be 5.00pm on 21 February 2020. There is no call-in for decision 2 which is a recommendation to Adur District Council.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1To provide Adur District Council Executive Members with an update on the Housing Revenue Account development programme, and in particular the Cecil Norris House and Albion Street projects.
1.2To seek approval for the release of the sum of £378,000 from the unallocated capital budget for the Cecil Norris House Development to meet affordable housing needs.
1.3To confirm the final scheme budget for Albion Street and seek approval for the the release of the sum of £2.8 million from the capital budget to meet affordable housing needs.
Recommendations
2.1The Joint Strategic Committee is recommended to: i) To release further budget for Cecil Norris House of £378,000 to fund the increased costs associated with the Cecil Norris House development which is to be funded from borrowing.
ii) To recommend to Adur District Council release budget of £2.8m to fund the Albion Street development funded by prudential borrowing.
iii) To delegate authority to the Director of Communities in consultation with the Executive Member for Customer Services, that if required, to appropriate for planning purposes the Albion Street Land under section 122 of the Local Government Act 1972 and the use of powers under section 203 of the Housing and Planning Act 2016, subject to obtaining the necessary Secretary of State consents.
3. Context
3.1As part of ‘Platforms for Our Places - Going Further’ adopted by Adur District Council (ADC) in December 2019, Members have committed to the ongoing focus on delivering new affordable homes across the District as part of the Housing Revenue Account (HRA) development programme. Two of the current projects within this programme are Cecil Norris House which will deliver 15 affordable homes and Albion Street, which following a further planning application to deliver an additional 5 units (if approved) will deliver a total of 55 new council homes.
3.2It is well documented that across the Adur District and indeed across the South of England, there is a pressing and urgent need for more truly affordable accommodation. The Council has responded proactively by identifying a number of opportunities to develop new homes on Council owned lands. Cecil Norris House and Albion Street are the two schemes that were identified for delivery first and an update on each scheme is considered separately below. In addition to these two projects, ADC has identified a number of other sites through a “small sites” programme as outlined in the report to the Joint Strategic Committee in January 2020.
3.3Cecil Norris House
3.3.1. The Joint Strategic Committee previously considered a report on the development at Cecil Norris House on 19th July 2018. This report agreed a cost estimate for the development of £3.3 million and provided delegate authority to the Director for Communities to enter into a construction contract following a procurement process. Adur District Council (ADC) entered into contract with Pilbeam Construction in July 2019.
3.3.2. Demolition of the existing building has concluded, however works have been halted twice, firstly due to the discovery of previously unknown asbestos in the floor during demolition. Secondly, due to the need to demolish a party wall which was discovered as being structurally unsound following a professional assessment from a structural engineer.
3.3.3. Both of the above have had an estimated impact on the timing of the construction programme totalling c.19 weeks. The appointed Employers Agent for the scheme (RLF) who act as contract administrators have confirmed that ADC are responsible for these costs (and this is accepted) as both items were highlighted as provisional sums within the contract.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.