The Joint Strategic Committee noted the events and progress to date outlined within the report; approved the creation of a budget of £353,000 to take forward the project as outlined in paragraph 6; approved the use of Government Covid 19 Emergency Funding for this purpose; delegated authority to the Director for the Economy in consultation with the Leader and the Executive Member for the Environment to award an Adur Leisure Service Provision Contract if the opportunity arose prior to the November meeting of JSC; delegated authority to the Director for the Economy to negotiate the purchase of ACL assets (including any potential lease arrangements) to enable ongoing service delivery; noted that a further report would be presented to the committee in November updating members on progress, whether or not a new provider had been identified, and/or the Director for the Economy, in consultation with the Leader and Executive Member, had exercised his delegated authority, as above.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1The purpose of this report is to update members of the Committee on the leisure services in Adur following the insolvency of Adur Community Leisure and to agree a way forward for the reopening of leisure facilities in Adur District.
2. Recommendations 2.1 The Joint Strategic Committee is recommended to: ● Note the events and progress to date outlined within the report ● Approves the creation of a budget of £353,000 to take forward the project as outlined in paragraph 6. ● Approves the use of Government Covid 19 Emergency Funding for this purpose. ● If the opportunity arises, delegate authority to the Director for the Economy in consultation with the Leader and the Executive Member for the Environment to award an Adur Leisure Service Provision Contract. ● Further to paragraph 3.7.3 delegate authority to the Director for the Economy to negotiate the purchase of ACL assets (including any potential lease arrangements) to enable ongoing service delivery. ● Note that a further report will be presented to the committee in November updating members on progress, whether or not a new provider has been identified, and/or the Leader and Executive Member have exercised their authority above.
3. Context
3.1Adur District Council owns 3 leisure facilities and until recently, these have been operated and maintained by a charitable Trust, Adur Community Leisure (ACL) operating as a subsidiary company of Impulse Leisure. These facilities are:
● Lancing Manor Leisure Centre – a dry side leisure centre in Lancing, built in 1971 ● Southwick Leisure Centre – a dry side leisure centre in Southwick, built in 1972 ● Wadurs Community Pool – a 25m 5 lane swimming pool in Shoreham, built in 1993
3.2Following lockdown in March, and in common with many leisure operators across the country, ACL made a request for financial support from the Council to help manage immediate cash flow pressures resulting from the closure of the facilities. On April 28th officers agreed under delegated authority (and under the terms of the existing budget) to support ACL with an advance payment of the Annual Service Fee for the period 1st April 2020 – 31 March 2021 (£125k), much of this sum went towards paying their staff for the pre-furlough period.
3.3A subsequent request for further funding was to be the subject of a report to the 7th July Joint Strategic Committee. This report benefited from detailed advice from a specialist leisure consultant and was part funded by Sport England as part of a national programme.
3.4At the meeting of 7th July, members of the Joint Strategic Committee, members were informed that following a dialogue with Sport England, a revised proposal had been received on the 6th July from Adur Community Leisure, setting out an alternative way forward for the leisure facilities in Adur. Mindful of the late notice and time needed to properly assess the proposal, members of the Committee were advised that it would be inappropriate to discuss the item at that time. 3.5 Accordingly, following a proposal by the Leader of Adur District Council, it was agreed that owing to the urgent nature of the decision and the new proposal put forward by ACL, the Joint Strategic Committee delegated authority to the Leader of Adur District Council, in consultation with the Executive Member for the Environment, for a decision on this matter, following a full report and update from Officers outlining the options.
3.6Update since July
3.6.1 The Council was notified that Adur Community Leisure had declared insolvency following a Board Meeting on 16th July 2020. Sadly, this meant that the ACL staff were issued with redundancy notices and each of the facilities closed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.