The Joint Strategic Committee (a) with respect to the Capital Investment Programme of Adur District Council i. noted the reprofiling of the Adur District Council capital schemes as advised in paragraphs 7.2.1 and Appendix 3; ii. approved the transfer of funding within the Adur Homes Capital Investment Programme to include the Fire Safety Inner Rooms Project within the 2020/21 Capital Investment Programme as detailed in paragraph 7.2.3; iii. approved the virement of £13,200 to fund urgent Disability Discrimination Act access works at Commerce Way as detailed in paragraph 7.2.4; iv. approved the virement to fund the current overspend on the purchase of wheeled bins for the alternate weekly collection as detailed in paragraph 7.1.2; v. noted the award of external funding of £50,000 from Sompting BIG Local toward play area improvements at Sompting Recreation Ground as detailed in paragraph 7.2.5. (b) with respect to the Capital Investment Programme of Worthing Borough Council i. noted the reprofiling of the Worthing Borough Council capital schemes as advised in paragraphs 7.3.1 and Appendix 4; ii. approved the virement to fund the overspend on the purchase of wheeled bins for the alternate weekly collection service as detailed in paragraph 7.1.2; iii. noted the award of £100,000 from Sussex Community Foundation towards the new cafe in Brooklands Park as detailed in paragraph 7.3.2; iv. approved the virement of £72,000 to fund emergency works at Worthing Crematorium as detailed in paragraph 7.3.3; v. approved the addition of the urgent replacement of the audio and visual equipment at Worthing Crematorium to the 2020/21 Capital Investment Programme as detailed in paragraph 7.3.4; vi. approved the addition of the Fish Sculpture Waste Bin to the 2020/21 Capital Investment Programme as detailed in paragraph 7.3.5.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1This report updates the Joint Strategic Committee on the progress made on the 2020/21 Capital Investment Programmes for Adur District Council, Worthing Borough Council. The programmes include schemes which support the delivery of services by the Joint Services Committee.
1.2The following appendices have been attached to this report:
Appendix 1: Adur District Council Capital Monitoring Summary Appendix 2: Worthing Borough Council Capital Monitoring Summary Appendix 3: Adur District Council Reprofiled Budgets Appendix 4: Worthing Borough Council Reprofiled Budgets
Recommendations
2.1The Joint Strategic Committee is asked: (a) With respect to the Capital Investment Programme of Adur District Council. i) To note the reprofiling of the Adur District Council capital schemes as advised in paragraphs 7.2.1 and Appendix 3.
ii) To approve the transfer of funding within the Adur Homes Capital Investment Programme to include the Fire Safety Inner Rooms Project within the 2020/21 Capital Investment Programme as detailed in paragraph 7.2.3. iii) To approve the virement of £13,200 to fund urgent Disability Discrimination Act access works at Commerce Way as detailed in paragraph 7.2.4.
iv) To approve the virement to fund the current overspend on the purchase of wheeled bins for the alternate weekly collection as detailed in paragraph 7.1.2.
v) To note the award of external funding of £50,000 from Sompting BIG Local toward play area improvements at Sompting Recreation Ground as detailed in paragraph 7.2.5.
b) With respect to the Capital Investment Programme of Worthing Borough Council.
i) To note the reprofiling of the Worthing Borough Council capital schemes as advised in paragraphs 7.3.1 and Appendix 4.
ii) To approve the virement to fund the overspend on the purchase of wheeled bins for the alternate weekly collection service as detailed in paragraph 7.1.2.
iii) To note the award of £100,000 from Sussex Community Foundation towards the new cafe in Brooklands Park as detailed in paragraph 7.3.2.
iv) To approve the virement of £72,000 to fund emergency works at Worthing Crematorium as detailed in paragraph 7.3.3.
v) To approve the addition of the urgent replacement of the audio and visual equipment at Worthing Crematorium to the 2020/21 Capital Investment Programme as detailed in paragraph 7.3.4.
vi) To approve the addition of the Fish Sculpture Waste Bin to the 2020/21 Capital Investment Programme as detailed in paragraph 7.3.5.
3. CONTEXT
3.1In accordance with the Councils’ Capital Strategy, the Capital Working Group oversees the implementation and progress of both Councils’ Capital Investment Programmes.
3.2The Capital Working Group meets quarterly and monitors the programmes’ progress and finance, seeking to address any problems at an early stage in order for schemes to be completed within budget and timescales. Where problems are highlighted the Group considers possible remedies including virements between schemes, reprofiling of budgets between years and the withdrawal of schemes from the programme when schemes are unable to proceed. This could be due to resourcing problems, time delays or other factors beyond the Councils’ control.
3.3Full summaries of the progress of all the schemes in the 2020/21 Capital Investment Programmes are prepared each quarter highlighting:
Schemes with significant challenges Red
Schemes where progress is being closely monitored Amber
Schemes progressing well Green
Schemes where progress is beyond officers’ control ◘
Schemes with financial issues £
Schemes where progress has improved ⇧
Schemes where progress has deteriorated ⇩
3.4The Capital Working Group also ensures that capital schemes are approved within financial regulations.
3.5Financial Regulations require officers to report each project on completion.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.