Decision The Joint Strategic Committee · noted the successful funding applications to the Public Sector Decarbonisation Scheme and Low Carbon Skills Fund; · approved a n amendment to the General Fund capital programme budgets as follows: o Adur : £466,000 funded by external funding of £364,970 and a contribution from the contingency budget £101,030; o Worthing: £103,850 funded by external funding; · approved the amendment of the Adur Homes Capital Programme to include schemes of £1.697m funded from external funding of £1,329,200 and by £367,950 from within the 2021/22 Housing Investment Capital Programme; · delegated to the Director of Digital, Sustainability & Resources the negotiation and letting of any contracts associated with this programme of works in consultation with the Executive Members for Resources providing the same were within the approved budget; · noted the delivery timescales, consultation proposals and works involved in delivering the carbon reduction projects that formed part of the successful bid and that further bids had been made to the Public Sector Decarbonisation Scheme, as set out in paragraph 4.2 and Appendix 1; and · agreed that the Councils adopt the new UK100 Pledge, as outlined in Section 8, along with other leading councils and in line with the enhanced ambition shown by central government, as part of its recognition of the responsibility to tackle the climate emergency and protect the environment. Call In : The call-in deadline for this decision will be 5.00pm on 19 February 2021.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
Adur & Worthing Councils have demonstrated leadership in tackling climate change through the declaration of a climate emergency; the setting a target to be carbon neutral by 2030; the adoption of an ambitious Carbon Neutral Plan; and by joining networks of ambitious local authorities, such as UK100.
The Carbon Neutral Plan i dentified a number of areas of carbon emissions that require intervention in order for the councils to meet the net zero carbon target. In order to fund some of these works, multiple funding bids were submitted to the Public Sector Decarbonisation Scheme, which opened to applications in September 2021. The councils have subsequently been awarded over £1.7m of capital funding to deliver multiple carbon reduction projects across the councils' estate. Requiring approximately £470,000 of match funding, these projects include installing low carbon heating systems at three sites; retrofitting multiple solar PV arrays; and improving the fabric efficiency of Worthing Town Hall. Should the recommendations outlined in the report be approved, it is proposed to begin procurement, design and building-user engagement, with a view to completing all projects by the autumn 2020.
In addition, the paper recommends that the councils formally adopt a new pledge made by the UK100 group of local authorities with ambitious climate change programmes. This pledge would amend the councils' area-wide target for carbon neutrality to 2045, 5 years ahead of the UK government's new national target.
1. Purpose
● JSC adopted the councils' Carbon Neutral Plan on 3 December 2019.
● This paper updates members on key progress that has been made in the delivery of the Carbon Neutral Plan, in particular: ○ Successful bids made to the Government's Public Sector Decarbonisation Scheme (PSDS) totalling in excess of £1.7m. ○ The development of a larger pipeline of projects through feasibility studies funded by the Government's Low Carbon Skills Fund (LCSF)
● Projects funded through both external funding and from within the existing capital programme are explained more fully in Appendix 1
● Proposed next steps are set out in Section 6. Approval is sought to create budgets to allow the programme to be delivered expediently and to procure contractors that enable project delivery.
● Additionally, JSC approved the joining of UK100, a network of ambitious local authorities tackling climate change on 6 November 2018.
● Reflecting the increased ambition of central government, UK100 has since created a new Pledge. The paper recommends formally making this pledge, which reaffirms the councils' ambitions to tackle climate change through the Carbon Neutral Plan and Platforms for Our Places.
Recommendations
1. To note the successful funding applications to the Public Sector Decarbonisation Scheme and Low Carbon Skills Fund. 2. To approve an amendment to the General Fund capital programme budgets as follows: Adur: £466,000 funded by external funding of £364,970 and a contribution from the contingency budget £101,030 Worthing: £103,850 funded by external funding
3. To approve the amendment of the Adur Homes Capital Programme to include schemes of £1.697m funded from external funding of £1,329,200 and by £367,950 from within the 2021/22 Housing Investment Capital Programme.
4. To delegate to the Director of Digital, Sustainability & Resources the negotiation and letting of any contracts associated with this programme of works in consultation with the Executive Members for Resources providing the same are within the approved budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.