Adur District Council / Worthing Borough Council
Joint Strategic Committee, Tuesday 9 February 2021 at 6.30pm

Carbon Neutral 2030 - Reporting on the success of funding applications to the Public Sector Decarbonisation Scheme

Noted Committee 2 papers

Joint Strategic Committee noted this item on Tuesday 9 February 2021. Below is the council's own wording, with the papers it was decided on.

ItemJSC/115/20-21

Resolved

Decision The Joint Strategic Committee · noted the successful funding applications to the Public Sector Decarbonisation Scheme and Low Carbon Skills Fund; · approved a n amendment to the General Fund capital programme budgets as follows: o Adur : £466,000 funded by external funding of £364,970 and a contribution from the contingency budget £101,030; o Worthing: £103,850 funded by external funding; · approved the amendment of the Adur Homes Capital Programme to include schemes of £1.697m funded from external funding of £1,329,200 and by £367,950 from within the 2021/22 Housing Investment Capital Programme; · delegated to the Director of Digital, Sustainability & Resources the negotiation and letting of any contracts associated with this programme of works in consultation with the Executive Members for Resources providing the same were within the approved budget; · noted the delivery timescales, consultation proposals and works involved in delivering the carbon reduction projects that formed part of the successful bid and that further bids had been made to the Public Sector Decarbonisation Scheme, as set out in paragraph 4.2 and Appendix 1; and · agreed that the Councils adopt the new UK100 Pledge, as outlined in Section 8, along with other leading councils and in line with the enhanced ambition shown by central government, as part of its recognition of the responsibility to tackle the climate emergency and protect the environment. Call In : The call-in deadline for this decision will be 5.00pm on 19 February 2021.
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

Adur & Worthing Councils have demonstrated leadership in tackling climate change through the declaration of a climate emergency; the setting a target to be carbon neutral by 2030; the adoption of an ambitious ​Carbon Neutral Plan​; and by joining networks of ambitious local authorities, such as UK100.

The ​Carbon Neutral Plan i​ dentified a number of areas of carbon emissions that require intervention in order for the councils to meet the net zero carbon target. In order to fund some of these works, multiple funding bids were submitted to the Public Sector Decarbonisation Scheme, which opened to applications in September 2021. The councils have subsequently been awarded over £1.7m of capital funding to deliver multiple carbon reduction projects across the councils' estate. Requiring approximately £470,000 of match funding, these projects include installing low carbon heating systems at three sites; retrofitting multiple solar PV arrays; and improving the fabric efficiency of Worthing Town Hall. Should the recommendations outlined in the report be approved, it is proposed to begin procurement, design and building-user engagement, with a view to completing all projects by the autumn 2020.

In addition, the paper recommends that the councils formally adopt a new pledge made by the UK100 group of local authorities with ambitious climate change programmes. This pledge would amend the councils' area-wide target for carbon neutrality to 2045, 5 years ahead of the UK government's new national target.

1. Purpose

● JSC adopted the councils' ​Carbon Neutral Plan ​on 3 December 2019.

● This paper updates members on key progress that has been made in the delivery of the ​Carbon Neutral Plan, ​in particular: ○ Successful bids made to the Government's Public Sector Decarbonisation Scheme (PSDS) totalling in excess of £1.7m. ○ The development of a larger pipeline of projects through feasibility studies funded by the Government's Low Carbon Skills Fund (LCSF)

● Projects funded through both external funding and from within the existing capital programme are explained more fully in Appendix 1

● Proposed next steps are set out in Section 6. Approval is sought to create budgets to allow the programme to be delivered expediently and to procure contractors that enable project delivery.

● Additionally, JSC approved the joining of UK100, a network of ambitious local authorities tackling climate change on 6 November 2018.

● Reflecting the increased ambition of central government, UK100 has since created a new Pledge. The paper recommends formally making this pledge, which reaffirms the councils' ambitions to tackle climate change through the ​Carbon Neutral Plan ​and ​Platforms for Our Places​.

Recommendations

1. To note the successful funding applications to the Public Sector Decarbonisation Scheme and Low Carbon Skills Fund. 2. To approve an amendment to the General Fund capital programme budgets as follows: Adur: £466,000 funded by external funding of £364,970 and a contribution from the contingency budget £101,030 Worthing: £103,850 funded by external funding

3. To approve the amendment of the Adur Homes Capital Programme to include schemes of £1.697m funded from external funding of £1,329,200 and by £367,950 from within the 2021/22 Housing Investment Capital Programme.

4. To delegate to the Director of Digital, Sustainability & Resources the negotiation and letting of any contracts associated with this programme of works in consultation with the Executive Members for Resources providing the same are within the approved budget.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Carbon Neutral 2030: Reporting on the success of funding applications to the Public Sector Decarbonisation SchemeAgenda 267 KB Download
PDF
Item 8: Reporting on the success of funding applications to the Public Sector Decarbonisation Scheme /115/20-21Report 184 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 14 attended
NT
Neil TerrySecretary, expected
DH
Councillor Daniel HumphreysWorthing Chairman, present
NP
Councillor Neil ParkinAdur Chair, present
AD
Councillor Angus DunnAdur Vice-Chair, present
KJ
Councillor Kevin JenkinsWorthing Vice-Chair, present
CA
Councillor Carson AlburyAdur Member, present
BB
Councillor Brian BoggisAdur Member, present
KB
Councillor Kevin BoramAdur Member, present
EC
Councillor Edward CrouchWorthing Member, present
EE
Councillor Emma EvansAdur Member, present
DH
Councillor Dr Heather MercerWorthing Member, present
DS
Councillor David SimmonsAdur Member, absent

All 14 on the meeting page

On this subject at Adur & Worthing

Search all
  1. Carbon Neutral 2030 - Reporting on the success of funding applications to the Public Sector Decarbonisation SchemeThis decision
  2. Carbon Neutral 2030: Worthing Heat Network Progress UpdateNoted
  3. Carbon Neutral 2030: Working towards the councils’ carbon neutral target: progress updateNoted
  4. Carbon Neutral 2030: Worthing Heat Network: progress updateNoted
  5. Carbon Neutral 2030 - Developing opportunities for solarApproved
  6. Working towards the 2030 target - Adur & Worthing Councils' Carbon Neutral PlanNoted

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies