Adur District Council / Worthing Borough Council
Joint Strategic Committee, Tuesday 1 December 2020 at 6.30pm

Carbon Neutral 2030 - Developing opportunities for solar

Approved Committee 1 paper

Joint Strategic Committee approved this item on Tuesday 1 December 2020. Below is the council's own wording, with the papers it was decided on.

ItemJSC/88/20-21

Resolved

The Joint Strategic Committee 1. approved the direction of travel proposed within the Solar Investment Strategy for investment in small, medium and large scale solar opportunities as set out at paragraph 8.1 in relation to rooftop solar PV and solar carports, to: a) note that a report would be presented to the Executive Members for Resources early in the New Year, with a post procurement business case to proceed with a first phase of rooftop solar PV installations; b) noted that a viability study for a solar carport at Pond Road car park would be produced; and that subject to a successful business case, a report would be brought before the Executive Members for Resources to approve proceeding with installation; c) recommended that Adur District Council create an invest-to-save budget within the HRA Investment Programme of £100,000 for carbon reduction schemes funded through borrowing which could be released on the submission of a business case to the Executive Member of Resources. 2. In relation to a 3MW solar farm on council land, to: a) approved the development of a feasibility study and business case from existing budgets; b) noted that a report would be presented to the Joint Strategic Committee in 2021, if a viable business case was identified. 3. In relation to the potential purchase of large ... view the full minutes text for item JSC/88/20-21
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

Investment in solar technology is a critical part of the Councils’ carbon strategy. The carbon reduction plan approved by Joint Strategic Committee in December 2019, sets out the importance of solar in reaching the carbon neutral target by 2030. This is particularly important as the Councils’ energy demands move away from gas and transport fuel towards increased electric use (with more electric heating systems and vehicles) and also as a way to offset residual carbon emissions.

This report sets out the strategy for delivering a significant increase in the use of solar energy through a number of work streams:

● Securing local renewable electricity supply for the councils’ use (5MW in total) ○ Rooftop solar, with a number of immediate opportunities identified ○ Solar carports at several locations ○ A 3MW solar farm on council owned land ● Carbon offsetting as set out in the carbon reduction plan ○ Potential large scale solar investment out of area (circa 15-20MW)

The report proposes that the Councils make immediate progress with rooftop solar installations, utilising capital funds allocated and supported by bids to the Public Sector Decarbonisation Fund.

Over the next 12 months, feasibility and invest-to-save business cases will be developed in each work stream, helping develop a pipeline of projects for delivery in the first phase of our 10 year programme to carbon neutrality by 2030. Dependent on financial modeling and due diligence, it is possible that a proposal for out of area investment could come forward to Joint Strategic Committee as early as January 2021.

With the Carbon Reduction Team now in place, the Councils have the capacity to build a high impact programme and deliver a major contribution to the carbon neutral target.

1. Purpose

1.1The councils have committed under the Climate Emergency Declaration, to work towards being carbon neutral by 2030. A Carbon Neutral Plan sets out pathways for the councils to achieve the target.

1.2Installing renewable energy technologies such as solar photovoltaics (PV) and the potential investment in large scale renewable energy generation are an important strand in the Carbon Neutral Plan to provide zero carbon power and to offset council emissions.

1.3A full review of solar investment opportunities has been undertaken on council owned sites and a solar investment strategy developed. The study identifies potential for up to 5MW of local renewable electricity generation, equivalent to a reduction of ​one third of the Councils’ carbon emissions​, (or enough to power 1,500 homes).

1.4Subject to full business cases this will be made up of proposals for roof mounted solar on council buildings, solar carports, and a 3MW solar farm locally. Further work will also be undertaken to investigate the benefits of investing out of area in large solar schemes, in consultation with the Executive Members for Resources, and with the support of the Major Projects team, with the aim of offsetting residual council carbon emissions, while delivering an acceptable financial return.

Recommendations

2.1The Joint Strategic Committee is recommended to:

2.1.1. Approve the direction of travel proposed within the Solar Investment Strategy for investment in small, medium and large scale solar opportunities as set out at paragraph 8.1.In relation to rooftop solar PV and solar carports, to:

a. Note that a report will be presented to the Executive Members for Resources early in the New Year, with a post procurement business case to proceed with a first phase of rooftop solar PV installations;

b. Note that a viability study for a solar carport at Pond Road car park will be produced; and that subject to a successful business case, a report will be brought before the Executive Member for Resources to approve proceeding with installation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Carbon Neutral 2030: Developing opportunities for solarReport 200 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 14 attended
NT
Neil TerrySecretary, present
DH
Councillor Daniel HumphreysWorthing Chairman, present
NP
Councillor Neil ParkinAdur Chair, present
AD
Councillor Angus DunnAdur Vice-Chair, present
KJ
Councillor Kevin JenkinsWorthing Vice-Chair, present
CA
Councillor Carson AlburyAdur Member, present
BB
Councillor Brian BoggisAdur Member, present
KB
Councillor Kevin BoramAdur Member, present
EC
Councillor Edward CrouchWorthing Member, present
EE
Councillor Emma EvansAdur Member, present
DH
Councillor Dr Heather MercerWorthing Member, present
DS
Councillor David SimmonsAdur Member, absent

All 14 on the meeting page

On this subject at Adur & Worthing

Search all
  1. Carbon Neutral 2030 - Developing opportunities for solarThis decision
  2. Carbon Neutral 2030: Worthing Heat Network Progress UpdateNoted
  3. Carbon Neutral 2030: Working towards the councils’ carbon neutral target: progress updateNoted
  4. Carbon Neutral 2030: Worthing Heat Network: progress updateNoted
  5. Carbon Neutral 2030 - Reporting on the success of funding applications to the Public Sector Decarbonisation SchemeNoted
  6. Working towards the 2030 target - Adur & Worthing Councils' Carbon Neutral PlanNoted

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies