Decision The Joint Strategic Committee 1. Agreed to WBC taking on the project management and design responsibility of Montague Place Public Realm work, supported by WSCC and if required to enter into a collaboration agreement to support that relationship; 2. Delegated authority to the Director for the Economy, in consultation with the Executive Member for Regeneration, the authority to procure and award all contracts necessary to complete the Phase 1 temporary works and main public realm design schemes, within the approved budgets; 3. Approved the creation of a budget of £163k within the Worthing Borough Council revenue budget fully funded by the Welcome Back Fund to complete the temporary works (Phase 1); and 4. Approved the creation of a budget of £200k within the Worthing Borough Council capital programme, fully funded by Community Infrastructure Levy (CIL), to complete the main design works (Phase 2). Call In: The call-in deadline for this decision will be 5.00pm on 23 July 2021.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1The purpose of this report is to update Members on the approach to the Montague Place public realm scheme and outline that Worthing Borough Council (WBC) will act as the lead design agency for West Sussex County Council (WSCC) under the terms set out in this report.
1.2To present the rationale for WBC designing the project and the approach being undertaken to deliver temporary works to help inform the long term design of Montague Place.
1.3To release budget to cater for the temporary works and main public realm design works to enable WBC to have a fully consulted, designed and costed scheme.
Recommendations
2.1To agree to WBC taking on the project management and design responsibility of Montague Place Public Realm work, supported by WSCC and if required to enter into a collaboration agreement to support that relationship.
2.2To delegate authority to the Director for the Economy, in consultation with the Executive Member for Regeneration, the authority to procure and award all contracts necessary to complete the Phase 1 temporary works and main public realm design schemes, within the approved budgets.
2.3To approve the creation of a budget of £163k within the Worthing Borough Council revenue budget fully funded by the Welcome Back Fund to complete the temporary works (Phase 1).
2.4To approve the creation of a budget of £200k within the Worthing Borough Council capital programme fully funded by Community Infrastructure Levy (CIL) to complete the main design works (Phase 2). 3. Background
3.1The Adur and Worthing Growth (A&WG) Deal signed in March 2017 identified up to 8 public realm schemes aimed at supporting the regeneration of Worthing town centre. The agreed programme included initial funding from WSCC Capital Programme (£5m) with the remainder being sourced through developer contributions, to include Community Infrastructure Levy (CIL); planning obligations (Section 106) and grants to support delivery of later phases of the programme.
3.2The delivery of the Worthing Public Realm programme is overseen by an Officer Group, namely the Public Realm Board. The Public Realm Board is a joint WBC and WSCC Board.
3.3Portland Road (in construction) and Railway Approach (in preliminary design) were the initial phases agreed by the Public Realm Board. These schemes are being funded by a combination of the WSCC Capital Programme (£5m allocation) and Coast to Capital LEP. In March 2021, the Board agreed that Montague Place, due to its location and significance in the heart of the town centre, would be the next phase to be designed as part of the overall public realm improvement programme.
3.4The Worthing Public Realm programme provides a significant and exciting opportunity to revitalise the public spaces through a people-centred design approach. As with Portland Road and Railway Approach, Montague Place will deliver a number of social and economic benefits, including:
● Establishing a new destination, arrival zone and meeting point ● Alignment and enhancement of routes to create town centre circuits ● Ability to design inclusive and welcoming spaces ● Improving and enhancing sustainable travel options ● Responding to key stakeholders through direct consultation ● Improving place activation by providing improved outdoor spaces
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.