Decision The Joint Strategic Committee : 1. Noted the contents of the report including the progress being made against the three workstreams of the project; and 2. Noted the revised procurement and commercial strategy set out in paragraph 4.8 Call In: The call-in deadline for this decision will be 5.00pm on 23 July 2021.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
2.1Note the contents of the report including the progress being made against the three workstreams of the project.
2.2Note the revised procurement and commercial strategy set out in paragraph 4.8 3.0 Recovering Brooklands Park - Progress to Date
3.1Brooklands Park is a 29 ha open space, lake and leisure facility on the eastern edge of Worthing. Over recent years parks and open spaces have begun to be used differently by communities with a renewed emphasis on being attractive and welcoming for all; offering an important resource for people’s physical and mental health and wellbeing; and more recently in connecting people to their wider community as relationships to place and neighbourhood evolve as a result of lockdowns and Covid-19. To meet these new emphases Worthing Borough Council have been leading local stakeholders to deliver a project to recover and renew the park by redesigning the landscaping and infrastructure; improving Brooklands Lake; and delivering new leisure, hospitality, and play facilities to ensure that it continues to serve the needs of the local community, and the town more widely.
3.2The report below provides an update on each of the three workstreams of the project:
Workstream 1 Develop the detailed design of the Landscape, Playground and Cafe design to enable this to be tendered for delivery by the Council by entering into a construction contract.
Workstream 2 Deliver a development strategy for the Southwest Corner Leisure Opportunity by securing a partner investor who would build, own, and operate the facility. The leisure facility would need to be in line with the masterplan approved by the Committee, and contribute to the overall vitality and vibrancy of the park.
Workstream 3 Ongoing work of the Environment Service to improve maintenance and planting, and working with the Friends of Brooklands and other community groups to increase activity through events, and community projects in parallel with the major works planned. 4.1 Workstream 1 - Update on Landscape, Playground, and Cafe Project 4.2 The first workstream of the project focuses on increasing activity, repairing existing infrastructure, improving existing facilities and delivering a new café offer for visitors to the park. An annotated park masterplan is included below as Appendix 1 for reference.
4.3The initial step focused on addressing the environmental issues arising from the lake which was putting off people from visiting. Significant progress has been made with work being undertaken throughout 2019, 2020 and early 2021 on restoring and improving the lake which was causing odours and pollution to surrounding neighbours and visitors. Work has been undertaken to address the reed beds, repair an outflow pipe that connects the park to the sea, and the installation of windmills which will lead to improved aeration of the park preventing the significant algae bloom that had been a feature of the lake previously. This key first step was undertaken to ensure that the most significant challenges to the park's amenity are addressed and were no longer putting off people from visiting.
4.4The second step in this workstream is around addressing the core infrastructure of the park. This includes:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.