Decision The Joint Strategic Committee I. noted the update on access and meanwhile uses set out in Section 4; II. Delegated authority to the Head of Major Projects & Investment in consultation with the Leader of Worthing Borough Council and Executive Member for Regeneration, to enter into an Agreement, in accordance with the Heads of Terms set out in the Appendix C for the purpose of securing the development of the Teville Gate Site; III. Delegated authority to the Head of Major Projects & Investment to continue to negotiate terms of the draft Heads of Terms set out at the Appendix C and to make any required amendments; and IV. noted and agreed to the Development Strategy summarised in Section 6 and in full at Appendix D. Call In : The call-in deadline for decision will be 5.00pm on 17 December 2021.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1. Purpose ● To update the Committee on the financial implications of completing the purchase of the site. ● To update the Committee on a workstream to open up a footpath crossing the site, and to deliver meanwhile uses while the permanent development is being brought forward. ● To seek agreement to continue negotiations with London & Continental Railways Property for them to invest in the site and to jointly work with them on the development. ● To agree the proposed approach to delivering development on the site.
2. Recommendations 2.1 To note the update on access and meanwhile uses set out in Section 4
2.2To delegate to the Head of Major Projects & Investment in consultation with the Leader of Worthing Borough Council and Executive Member for Regeneration, the authority to enter into an Agreement, in accordance with the Heads of Terms set out in the Appendix C for the purpose of securing the development of the Teville Gate Site. 2.3 To delegate to the Head of Major Projects & Investment the authority to continue to negotiate terms of the draft Heads of Terms set out at the Appendix C and to make any required amendments.
2.4To note and agree to the Development Strategy summarised in Section 6 and in full at Appendix D.
3. Context
3.1The Teville Gate site is a key development site in Worthing and the delay in its development has been a prominent issue affecting residents and businesses in the town for a long period. The site is a cornerstone of the Council’s 2016 Investment Prospectus, is one of the most significant housing allocations in the Draft Local Plan for the town, and is a key commitment in the Council’s Platforms for our Places: Going Further Strategy. The site was successful in receiving funding from the Coast to Capital Local Enterprise Partnership in 2018 and the social, economic and environmental outputs that the funding agreement enables are required to be delivered by March 2025. The development of the site will fulfill important regeneration and housing objectives for the town and solve a significant blight in the town, providing confidence for further economic growth and investment.
3.2Members of the Joint Strategic Committee considered a report in July 2021 which set out the background and justification for intervening to purchase the site following years of market failure to develop the site.
3.3Having received approval and agreed the financial envelope for the transaction, officers continued to negotiate the purchase of the site. Section 7 of the July JSC report outlined the financial implications of purchasing the site which were anticipated at the time. These were:
● Maximum price £7,725,000 ● Stamp Duty Land Tax (SDLT) £381,750 ● Legal and other professional fees £15,000 ● Total Budget £8,121,750
3.4Following negotiation the Council successfully negotiated the land price to be reduced from £7,725,000 to £7,000,000. The final cost of purchasing the land by Worthing Borough Council was therefore as follows: ● Purchase price - £7,000,000 ● Stamp Duty Land Tax - £409,500 ● Legal fees - £40,410 ● Land Registry fees and search fees - £2,650
3.5The total cost to the Council was therefore: £7,452,560 and was £668,190 less than what was budgeted for in the Joint Strategic Committee Report.
4. Short Term Objectives: Improving Site Appearance; Access; and Meanwhile Uses
4.1Having purchased the site some key short term objectives have been identified to improve its physical appearance, reestablish the site as a place for people to go, and repair the north south route across the site that hampers access to Worthing Station.
Site Hoarding
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.