2nd Quarter Capital Investment Programme & Projects Monitoring 2021/22

Noted Committee 1 paper

Joint Strategic Committee noted this item on Tuesday 7 December 2021. Below is the council's own wording, with the papers it was decided on.

ItemJSC/65/21-22

Resolved

Decision The Joint Strategic Committee: (a) With respect to the Capital Investment Programme of Adur District Council i ) noted the reprofiling of the Adur District Council capital schemes as advised in paragraphs 7.2.1 and Appendix 3; ii) approved the increase in the Disabled Facilities Budget in line with the forecast expenditure funded from Better Care Fund Grant as detailed in paragraph 7.2.3; iii) approved the virements totalling £45,000 to fund the anticipated overspend on the Lancing Manor Leisure Centre Car Park access reconstruction and security improvements as detailed in paragraph 7.2.4; iv) approved the virement of £32,600 to fund the anticipated overspend on the land drainage scheme to realign the ditch and stabilisation of banks in the vicinity of Larkfield playing field, Lancing as detailed in paragraph 7.2.5; v) approved the virement of £164,750 to fund budget pressures in the joint services ICT digital programme as detailed in paragraph 7.1.1; vi) approved the use of capital receipts to increase the 2021/22 Grounds Maintenance Equipment Replacements Budget to £147,100 as detailed in paragraph 7.1.2; vii) approved the use of the Section 106 receipts to fund recreational equipment at Buckingham Park as detailed in paragraph paragraph 7.2.6. (b) With respect to the Capital Investment Programme of Worthing Borough Council i ) noted the reprofiling of the Worthing Borough Council capital schemes as advised in paragraphs 7.3.1 and Appendix 4; ii) approved the increase in the Disabled Facilities Budget in line with the forecast expenditure funded from Better Care Fund Grant as detailed in paragraph 7.2.3; iii) approved the amendment to the Portland House replacement of windows and balcony doors and ancillary works budget to include the Salix funding and match funding as detailed in paragraph 7.3.3; iv) approved the virement of £164,750 ... view the full minutes text for item JSC/65/21-22
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1. PURPOSE 1.1 This report updates the Joint Strategic Committee on the progress made on the 2021/22 Capital Investment Programmes for Adur District Council, Worthing Borough Council. The programmes include schemes which support the delivery of services by the Joint Services Committee.

1.2The following appendices have been attached to this report: Appendix 1: Adur District Council Capital Monitoring Summary Appendix 2: Worthing Borough Council Capital Monitoring Summary Appendix 3: Adur District Council Reprofiled Budgets Appendix 4: Worthing Borough Council Reprofiled Budgets

2. RECOMMENDATIONS 2.1 The Joint Strategic Committee is asked: (a) With respect to the Capital Investment Programme of Adur District Council. i) To note the reprofiling of the Adur District Council capital schemes as advised in paragraphs 7.2.1 and Appendix 3. ii) To approve the increase in the Disabled Facilities Budget in line with the forecast expenditure funded from Better Care Fund Grant as detailed in paragraph 7.2.3.

iii) To approve the virements totalling £45,000 to fund the anticipated overspend on the Lancing Manor Leisure Centre Car Park access reconstruction and security improvements as detailed in paragraph 7.2.4.

iv) To approve the virement of £32,600 to fund the anticipated overspend on the land drainage scheme to realign the ditch and stabilisation of banks in the vicinity of Larkfield playing field, Lancing as detailed in paragraph 7.2.5.

v) To approve the virement of £164,750 to fund budget pressures in the joint services ICT digital programme as detailed in paragraph 7.1.1.

vi) To approve the use of capital receipts to increase the 2021/22 Grounds Maintenance Equipment Replacements Budget to £147,100 as detailed in paragraph 7.1.2.

vii) To approve the use of the Section 106 receipts to fund recreational equipment at Buckingham Park as detailed in paragraph paragraph 7.2.6.

b) With respect to the Capital Investment Programme of Worthing Borough Council.

i) To note the reprofiling of the Worthing Borough Council capital schemes as advised in paragraphs 7.3.1 and Appendix 4.

ii) To approve the increase in the Disabled Facilities Budget in line with the forecast expenditure funded from Better Care Fund Grant as detailed in paragraph 7.2.3.

iii) To approve the amendment to the Portland House replacement of windows and balcony doors and ancillary works budget to include the Salix funding and match funding as detailed in paragraph 7.3.3.

iv) To approve the virement of £164,750 to fund budget pressures in the joint services ICT digital programme as detailed in paragraph 7.1.1.

v) To approve the use of capital receipts to increase the 2021/22 Grounds Maintenance Equipment Replacements Budget to £147,100 as detailed in paragraph 7.1.2.

vi) To approve the use of the Section 106 receipts to fund recreational equipment at Bourne Close and Northbrook Recreation Ground and the amendment to the 2021/22 Capital Investment Programme to include the scheme as advised in paragraph 7.3.4. vii) To approve the use of the Building Maintenance Reserve to fund the urgent replacement of play equipment at Gull Island and the amendment to the 2021/22 Capital Investment Programme to include the scheme as detailed in paragraph 7.3.5

3. CONTEXT

3.1In accordance with the Councils’ Capital Strategy, the Capital Working Group oversees the implementation and progress of both Councils’ Capital Investment Programmes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2nd Quarter Capital Investment Programme & Projects Monitoring 2021/22Report 1.1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
NT
Neil TerrySecretary, expected
NP
Councillor Neil ParkinAdur Chair, present
AD
Councillor Angus DunnAdur Member, present
KJ
Councillor Kevin JenkinsWorthing Member, present
EC
Councillor Edward CrouchWorthing Member, present
CA
Councillor Carson AlburyAdur Member, present
BB
Councillor Brian BoggisAdur Member, absent
KB
Councillor Kevin BoramAdur Member, present
EE
Councillor Emma EvansAdur Member, present
SM
Councillor Sean McDonaldWorthing Member, present
DH
Councillor Dr Heather MercerWorthing Member, absent
ES
Councillor Elizabeth SparkesWorthing Member, present

On this subject at Adur & Worthing

Search all
  1. 2nd Quarter Capital Investment Programme & Projects Monitoring 2021/22This decision
  2. Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27Approved
  3. Joint 3rd Quarter Capital Investment Programme & Projects Monitoring 2025/26Noted
  4. Joint 2nd Quarter Capital Investment Programme & Projects Monitoring 2025/26Noted
  5. Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2025/26Approved
  6. Joint 3rd Quarter Capital Investment Programme & Projects Monitoring 2024/25Noted

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies