Decision The Joint Strategic Committee:- i ) noted the outturn position for 2021/22; ii) recommended that Adur District Council at its Council meeting on 21st July 2022: a) Note the overall capital final outturn for 2021/22; b) Agree the net carry over of General Fund Capital underspends for Adur District Council as detailed in paragraphs 5.3 of the report; c) Approve the financing of the Adur District Council 2020/21 Capital Investment Programme, including the use of capital receipts as set out in paragraphs 5.1 and 5.2 of the report; and d) Approve the carry forward of Council resources underspends to fund budget pressures as detailed in paragraph 4.2.2. and summarised in paragraph 5.6 of the report. iii) recommended that Worthing Borough Council at its Council meeting on 19th July 2022: a) Note the overall capital final outturn for 2021/22; b) Agree the net carry over of General Fund Capital underspends for Worthing Borough Council as detailed in paragraph 5.10 of the report; c) Approve the financing of the Worthing Borough Council 2021/22 Capital Investment Programme, including the use of capital receipts as set out in paragraphs 5.7 and 5.8 of the report; and d) Approve the carry forward of Council resources underspends to fund budget pressures as detailed in paragraph 4.2.2. and summarised in paragraph 5.15 of the report. iv) noted the additional external funding awarded by Homes England towards housing schemes as set out in paragraph 7.1 and delegated authority to the Head of Major Projects to enter into the associated funding agreement; v ) noted the final projected benefit from completed invest to save schemes as ... view the full minutes text for item JSC/14/22-23
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1This report outlines the financial monitoring position for the end of the 2021/22 financial year for capital schemes included in the capital programmes of the Joint Strategic Committee, Adur District Council and Worthing Borough Council.
1.2Information is also provided in respect of capital receipts for the 2 constituent authorities.
1.3The following appendices have been attached to this report:
Appendix 1: Adur District Council Outturn Summary Appendix 2: Worthing Borough Council Outturn Summary Appendix 3: Adur District Council Sale Proceeds Appendix 4: Worthing Borough Council Sale Proceeds
Recommendations
2.1The Joint Strategic Committee is asked:
i) Note the outturn position for 2021/22 ii) To recommend that Adur District Council at its Council meeting on 21st July 2022: (a) To note the overall capital final outturn for 2021/22. (b) Agree the net carry over of General Fund Capital underspends for Adur District Council as detailed in paragraphs 5.3. (c) Approve the financing of the Adur District Council 2020/21 Capital Investment Programme, including the use of capital receipts as set out in paragraphs 5.1 and 5.2. (d) Approve the carry forward of Council resources underspends to fund budget pressures as detailed in paragraph 4.2.2. and summarised in paragraph 5.6.
iii) To recommend that Worthing Borough Council at its Council meeting on 19th July 2022: (a) Note the overall capital final outturn for 2021/22. (b) Agree the net carry over of General Fund Capital underspends for Worthing Borough Council as detailed in paragraph 5.10. (c) Approve the financing of the Worthing Borough Council 2021/22 Capital Investment Programme, including the use of capital receipts as set out in paragraphs 5.7 and 5.8. (d) Approve the carry forward of Council resources underspends to fund budget pressures as detailed in paragraph 4.2.2. and summarised in paragraph 5.15. iv) Note the additional external funding awarded by Homes England towards housing schemes as set out in paragraph 7.1 and delegate to the Head of Major Projects the ability to enter into the associated funding agreement;
v) To note the final projected benefit from completed invest to save schemes as outlined in Appendix 5.
3. CONTEXT
3.1The monitoring of capital budgets has been reported to the Joint Strategic Committee three times during the year.
3.2In accordance with the Councils’ Capital Strategy, the Joint Capital Working Group oversees the development, implementation and progress of both Councils’ Capital Investment Programmes. 3.3 Full summaries of the outturn of all the schemes in the 2021/22 Capital Investment Programmes are available from the Councils’ Joint Intranet and highlight:
Schemes not progressing satisfactorily or where there are Red financial issues Schemes where progress is being closely monitored Amber Schemes progressing well Green Schemes where progress is beyond officers’ control ◘ Schemes with financial issues £ Schemes where progress has improved ⇧ Schemes where progress has deteriorated ⇩
4. 2021/22 Outturn
4.1Overall performance against the programme can be summarised as follows:
Capital Outturn - Summary of Progress: Adur Worthing Status
Schemes where the Councils have experienced significant challenges or where Red financial issues have been identified 2 -
Schemes where progress is being closely 15 23 Amber monitored Schemes progressing well 35 49 Schemes completed Green 20 34 Total Schemes: 72 106
4.2Successes and challenges in the 2021/22 programme
4.2.1 A number of significant schemes have been delivered this year, with real and visible impact across our area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.