Financial Performance 2025/26 - Revenue outturn

Noted Committee 1 paper

AI summaryJoint committee notes Adur £325k underspend and Worthing £3,785k overspend for 2025/26, approves £75,000 transfer for Shoreham beach toilets, with Worthing's gap covered by Exceptional Funding Support from government.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedOutturn noted, £75,000 transfer approved
Money£3,785,000 overspend (Worthing); £325,000 underspend (Adur)Worthing offset by Exceptional Funding Support
What happens nextCall-in deadline 5pm 23 July 2026Audit due September 2026
Who it affectsAdur and Worthing residents and council services. Including homelessness, car parks, bereavement

What was decided

The committee noted the 2025/26 revenue outturn for Worthing Borough Council, an overspend of £3,785k, to be met from Exceptional Funding Support from MHCLG. Report P3, P23

The committee noted the 2025/26 revenue outturn for Adur District Council, an underspend of £325k after proposed transfers to reserves. Report P3, P22

The committee approved the transfer of £75,000 to the Capacity Issue reserve to fund improvements to Shoreham beach public conveniences. Report P7

Why

Worthing's overspend is driven mainly by homelessness (£3,402k), car parks (£918k) following the closure of Grafton MSCP, and bereavement services (£641k), partly offset by a treasury underspend of £1,715k. Report P3, P33, P38, P66, P75, P76, P80

Adur's underspend reflects an underspend in strategic property (£921k) and treasury, partly offset by homelessness pressures of £893k and a £134k utilities and rates overspend. Report P33, P38, P58, P86

Demand-led pressures in statutory homelessness services continue to grow: new approaches rose to 277 in Adur and 730 in Worthing, with Worthing's Homelessness Prevention Grant per household well below neighbouring councils. Report P39, P101, P103, P105

What happens next

Draft financial statements will be audited from September 2026, with any further adjustments reported to members later in the year. Report P2

Officers will continue spending controls, vacancy controls, and the organisational design programme to rebuild reserves and address future budget gaps. Report P14, P133, P135

Further MHCLG discussions on financial support and Homelessness Prevention Grant allocations are ongoing, with a Pan-Sussex Supported Housing Strategy in development. Report P52, P108, P127

The money

  • £325k Adur operational services underspend (3% of budget) Report P3, P22
  • £3,785k Worthing operational services overspend (21% of budget), met by Exceptional Funding Support Report P3, P22, P23
  • £75,000 Transfer to Capacity Issue reserve for Shoreham beach public conveniences Report P7
  • £1.008 million Adur 2025/26 budgeted savings Report 4.1
  • £1.86 million Worthing 2025/26 budgeted savings Report 4.1
  • £2.365 million Anticipated budget reductions from the organisational design programme Report 4.1
  • £3,402k Worthing homelessness overspend Report P38, P33
  • £893k Adur homelessness overspend Report P38
  • £918k Worthing car parks overspend after Grafton MSCP closure Report P33, P75, P76
  • £641k Worthing bereavement services overspend Report P33, P80
  • £1,715k Worthing treasury underspend Report P33, P66
  • £921k Adur strategic property underspend Report P33, P86
  • £1.167m Adur Housing Revenue Account overspend Report 9.2

Options considered

  • Chosen: Note Worthing outturn and proposed use of reserves. Recommended in officer report; reflects overspend of £3,785k covered by Exceptional Funding Support Report P5, P23
  • Chosen: Note Adur outturn and proposed use and contributions to reserves. Recommended in officer report; reflects underspend of £325k and reserve contributions Report P6, P89
  • Chosen: Approve £75,000 transfer to Capacity Issue reserve for Shoreham beach public conveniences. Recommended to fund improvement works Report P7

Implications

  • Financial: Worthing's £3,785k overspend is met by Exceptional Funding Support from MHCLG, with general reserves remaining low and a planned contribution to reserves not achieved. Report P23, P120, P123, P132
  • Financial: Adur's general fund working balance is held at 10% of net revenue expenditure, in the upper part of the 6 to 10% CIPFA range, while Worthing's is 8%. Report P126, P130
  • Legal: Councils have a statutory duty under the Local Government Act 2003 to monitor budgets and under the Local Government Finance Act 1992 to set a balanced budget and consider reserve levels. Report P145, P146, P147
  • Equalities: Equality, community safety and human rights issues were considered and none identified in the sustainability and risk assessment. Report 2.2, P160, P161
  • Risk: Homelessness demand and a shortage of move-on housing remain the most significant financial risk, with statutory duties limiting spending controls; Homelessness Prevention Grant allocations to Adur and Worthing are low compared with neighbouring councils. Report P39, P100, P101, P103, P105
  • Other: Closure of Grafton MSCP on 16 May caused a £674k income shortfall and £237k reactive maintenance overspend in Worthing car parks. Report P76, P180

Who and where

  • Worthing Borough Council taxpayers and service users, given the £3,785k overspend and reliance on Exceptional Funding Support Report P23, P120, P123
  • Adur District Council taxpayers and service users, with a £325k underspend and reserve contributions Report P3, P22, P130
  • Households presenting as homeless or in temporary accommodation across both councils Report P39, P100
  • Council staff subject to ongoing vacancy controls and the organisational design programme Report P135
  • Users of Shoreham beach public conveniences, with £75,000 ringfenced for improvements Report P7
  • Funeral directors and bereaved families using the crematorium and cemetery services Report P81, P185, P186
  • Adur Housing Revenue Account tenants, given the £1.167m HRA overspend driven by voids, repairs and disrepair claims Report 9.2, P140

Timeline

  • 2025/26 financial year: Revenue budget period reported on Report P2, P22
  • December 2025: Joint Strategic Committee last considered the 5-year forecast Report 3.1
  • 14 July 2026: Joint Strategic Committee meeting; outturn report considered
  • 5.00pm on 23 July 2026: Call-in deadline for decisions
  • September 2026: Audit of draft financial statements due to commence Report P2
  • 2027/28: Target date for supported housing strategy mitigations on exempt accommodation costs Report P52

Plain English for the jargon

  • Exceptional Funding Support: Central government financial support available to councils facing severe budget pressures, used by Worthing to cover its 2025/26 overspend.
  • Revenue outturn: The final spending and income position for a council's day-to-day budget at the end of the financial year, compared with the budget set.
  • Earmarked reserves: Money set aside for specific identified future spending or risks, rather than for general use.
  • General Fund Working Balance: Unearmarked reserves held to manage unexpected spending pressures; both councils aim to keep this between 6% and 10% of net revenue expenditure.
  • HRA (Housing Revenue Account): A ring-fenced account covering income and spending on council housing, kept separate from the general fund.
  • Homelessness Prevention Grant: Central government grant supporting councils to prevent and relieve homelessness; Adur and Worthing receive relatively low amounts per household.
  • MRP (Minimum Revenue Provision): The minimum amount a council must set aside from revenue each year to repay borrowing taken out for capital spending.
  • MSCP: Multi-storey car park, in this report referring to Grafton MSCP in Worthing, which closed on 16 May.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/18/26-27

Resolved

That the report and outturn position for Worthing Borough Council be noted against the approved revenue budgets and proposed use of reserves (Appendix 2b). 2. That the report and outturn position for Adur District Council be noted against the approved revenue budgets and proposed use of and contributions to reserves (Appendix 3b). 3. That the transfer of £75,000 to the Capacity Issue reserve to fund the improvements to Shoreham beach public conveniences be approved. Call In: The call-in deadline for decisions will be 5.00pm on 23 July 2026.
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1.​ Purpose

1.1.​ This report outlines the revenue financial monitoring position for the end of the 2025/26 financial year for the Joint Strategic Committee, Adur District and Worthing Borough Councils. At the time of publication of this report, the Draft Financial Statements have been completed and the audit is due to commence in September, any adjustments that emerge during the audit will be reported to members later in the year.

The final position for operational services was an underspend for Adur District Council of £325k and an overspend in Worthing Borough Council of £3,785k. This represents a 3% underspend against the budget for Adur and 21% overspend in Worthing. During the year there were significant in-year spend controls and savings processes implemented to mitigate against a much larger projected overspend identified earlier in the year. In Adur the projected underspend assumes that the budgeted contribution to rebuild reserves is transferred. A breakdown is set out in section 5.1 of the report.

1.2.​ The following appendices have been attached to this report: 1.3.​ (i) Appendix 1 Briefing Note on Service Performance (ii) Appendix 2 (a) Worthing Summary (b) Worthing Use of Earmarked Reserves iii) Appendix 3 (a) Adur Summary (b) Adur Use of Earmarked Reserves (iii) Appendix 4 (a) HRA Summary (b) HRA Major variances (c) HRA Briefing note (iv) Appendix 5 Table of Variances 2.​ Recommendations

2.1.​ The Joint Strategic Committee is asked to note the report and outturn position for Worthing Borough Council against the approved revenue budgets and proposed use of reserves (Appendix 2b).

2.2.​ The Joint Strategic Committee is asked to note the report and outturn position for Adur District Council against the approved revenue budgets and proposed use of and contributions to reserves (Appendix 3b).

2.3.​ The Joint Strategic Committee is asked to approve the transfer of £75,000 to the Capacity Issue reserve to fund the improvements to Shoreham beach public conveniences.

3.0​ Context

3.1​ The Joint Strategic Committee last considered the 5-year forecast for 2025/26 onwards at its meeting in December 2025.

3.2​ The report outlined the financial context, and updated the outline 5 year forecast, the key budget pressures and the savings proposals for addressing the budget gap for Adur and Worthing Councils. The report built on previous strategies whose aim was to ensure that the Councils would become community funded, reliant only on income from trading and commercial activities, council tax income and business rate income.

3.3​ The delivery of these strategies is directly linked to the financial sustainability of the Councils. The Councils are now actively operating within a model where non-staturory activities are reliant on securing external funding or generating a low risk commercial return. While the Councils continue to work on the delivery of these strategies, external macroeconomic factors outside of their municipal control continue to place pressure on the overall financial outlook.

4.0​ Issues for consideration - Revenue 2025/26 Outturn

4.1​ As part of the 2025/26 budget the Councils committed to savings of £1.008 million for Adur District Council and £1.86 million for Worthing Borough Council to produce a balanced budget. 4.2​ The savings include £2.365 million in anticipated budget reductions from the organisational design programme. This programme has two core objectives: implementing a design aligned with the principles and framework of the councils’ delivery plan, and repositioning the council financially to achieve a more resilient and sustainable budget position

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial Performance 2025/26: Revenue outturnReport 979 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 11 attended
JG
Councillor Jeremy GardnerChair, present
BA
Councillor Becky AllinsonVice-Chair, present
LC
Councillor Lee CowenAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present
SJ
Councillor Saffa JanAdur Member, present
AL
Councillor Adrienne LoweAdur Member, present
CB
Councillor Caroline BaxterWorthing Member, present
JT
Councillor John TurleyWorthing Member, present
SC
Councillor Sophie CoxWorthing Member, absent
DF
Councillor Dom FordWorthing Member, present
MM
Councillor Martin McCabeWorthing Member, present

On this subject at Adur & Worthing

Search all
  1. Financial Performance 2025/26 - Revenue outturnThis decision
  2. Financial Performance 2025/26 - Capital and Projects OutturnNoted
  3. Financial Performance 2024/25 - Revenue outturnNoted
  4. Financial Performance 2024/25 - Capital and Projects OutturnNoted
  5. Financial Performance 2023/24 - Revenue OutturnApproved
  6. Financial Performance 2023/24 - Capital and Projects OutturnNoted

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies