Resolved
that the report be noted
Joint Overview & Scrutiny Committee noted this item on Thursday 14 July 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
that the report be noted
1. Purpose 1.1 This report outlines the revenue financial monitoring position for the end of the 2021/22 financial year for the Joint Strategic Committee, Adur District and Worthing Borough Councils. At the time of publication of this report, the Statements of Accounts are in progress, due to be completed by the end of June with the audit scheduled to commence in August 2022. Any adjustments that emerge as the audit proceeds will be reported to members later in the year.
1.2The final position for operational services were overspends in Adur District Council £208k and in Worthing Borough Council £2m. This is a variation to the projections reported at quarter 3 when operational outturns were predicted to be an overspend of £585k in Adur and £1.6m in Worthing.
1.3Overall outturn positions were an underspend of £183k in Adur District Council and an overspend of £196k in Worthing Borough Council. This represents a 2% underspend against the budget for Adur and 1% overspend in Worthing.
1.4The table at 4.6 below sets out the components contributing to the outturn positions in 2021/22. 1.5 There are no proposed budget carry forward requests for 2021/22.
1.6This outcome is an improvement overall for Adur District Council and a deterioration for Worthing Borough Council from that forecast in the quarter 3 monitoring report ‘3rd Revenue Budget Monitoring Report (Q3)’ when net overspends of £47,000 and £14,000 were being projected in Adur and Worthing respectively. The main movements in the last quarter are set out in appendix 5b.
1.7The following appendices have been attached to this report:
Appendix 1 Joint Summary of 2021/22 Outturn
Appendix 2 (a) Adur Summary of 2021/22 Outturn (b) Adur Use of Earmarked Reserves
Appendix 3 (a) Worthing Summary of 2021/22 Outturn (b) Worthing Use of Earmarked Reserves
Appendix 4 HRA Summary
Appendix 5 (a) Table of Outturn Variations to budget (b) Table of movements over £50,000 between quarter 3 and 4 (c) HRA Major Variations - Budget to Outturn 2. Recommendations
2.1The Joint Strategic Committee is asked to recommend that Adur District Council, at its meeting on 21st July 2022 and Worthing Borough Council at its meeting on 19th July 2022:-
(a) NOTE the overall final outturn for 2021/22.
(b) APPROVE the net appropriations from General Fund Reserves in the year as detailed in section 6 of the report totalling: Adur District Council £2,050,390 Worthing Borough Council £4,971,169.
2.2Joint Overview and Scrutiny Committee is recommended to note:
(i) the contents of the report and consider whether it needs to scrutinise any budget area in detail.
3. Context
3.1The Joint Strategic Committee considered the 5-year forecast for 2021/22 to 2025/26 on 1st December 2020. This report ‘Towards a sustainable financial position - Budget update’ outlined the financial context, and updated the outline 5 year forecast, the key budget pressures and the savings proposals for addressing the budget gap for Adur and Worthing Councils. The report built on the strategy first proposed in 2016/17 whose strategic aim was to ensure that the Councils would become community funded by 2020 reliant, by then, only on income from trading and commercial activities, council tax income and business rate income.
3.2The successful delivery of the strategy is fundamentally changing how the Councils are funded. The Councils are moving increasingly away from ever reducing government funding towards funding from the local community via Council Tax and Business Rates, becoming increasingly reliant on income from commercial activities although with this change comes more financial risk. 4. Issues for consideration
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Performance 2021/22: Revenue OutturnReport | 849 KB | DownloadRead as text |
Follow Joint Overview & Scrutiny Committee at Adur & Worthing and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Jun 2026 | JOSC Work Programme ConfirmationAgreed to move the date of the July JOSC meeting from July 2 nd to July 9 th 2026. · Agreed to continue the Budget Sc... | Agreed | Open |
| 5 Mar 2026 | Annual feedback report from meetings of the West Sussex Health & Adult Social Care Scrutiny Committee (HASC)The Joint Overview and Scrutiny Committee noted the report | Noted | Open |
| 5 Mar 2026 | JOSC Work Programme Setting 26/27The Joint Overview and Scrutiny Committee Noted the progress made in delivering the JOSC Work Programme for 2025/26; ... | Noted | Open |
| 27 Jan 2026 | Confirmation of MinutesThe minutes of the meeting of the 4th December 2025 were approved as a correct record and be signed by the Chairman | Approved | Open |
| 27 Jan 2026 | Budget update and scrutinyThe Joint Overview and Scrutiny Committee: Noted the work undertaken by the JOSC Budget Scrutiny Working Group and su... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.