Disposal of Ashcroft, 100 Kingston Lane, to Worthing Homes, and entry into a Development Agreement with Worthing Homes to secure the redevelopment of the site to provide sheltered accommodation.
ApprovedCommittee1 paper
Joint Strategic Committee approved this item on Tuesday 12 November 2024. Below is the council's own wording, with the papers it was decided on.
That the release of land at Ashcroft (the vacant sheltered housing site at 100 Kingston Lane, Southwick), from the HRA be approved. 2. That the outcome of a marketing exercise to secure the redevelopment of the former Ashcroft site be noted. 3. That authority be delegated to the Assistant Director for Housing and Homelessness Prevention, to grant a 250 year development lease of the former Ashcroft site to Worthing Homes (Housing Association), subject to Heads of Terms being agreed and secured via a contract between Adur District Council and Worthing Homes, and subject to receipt of a valuation report confirming best consideration has been achieved by the Council together with any other associated legal documentation. Call In: The call-in deadline for decisions will be 5.00pm on 22 November 2024
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1The report seeks approval to grant Worthing Homes a 250 year lease of Ashcroft, the vacant sheltered housing site, located at 100 Kingston Lane, Shoreham-by-Sea, to Worthing Homes. This is pursuant to a marketing exercise where three suitable Registered Providers were invited to bid competitively.
1.2The granting of the lease is subject to Worthing Homes obtaining planning permission for 56 units of Sheltered Accommodation, and subject to securing Homes England grant funding.
1.3Adur District Council would enter into a contract with Worthing Homes, to grant them the 250 year lease subject to planning and grant funding. The contract would contain obligations requiring Worthing Homes to procure a contractor to deliver the site in a timely manner in line with the obtained planning consent, and to enter into a nominations agreement ahead of practical completion. 1.4. This report sets out the options that have been considered for the site, and the reasons why granting a lease to Worthing Homes is the recommended option. Draft Heads of Terms are included in Exempt Appendix A, which will form the basis of the terms of the contract with Worthing Homes.
Recommendations
2.1To approve the release of land at Ashcroft (the vacant sheltered housing site at 100 Kingston Lane, Southwick), from the HRA.
2.2Note the outcome of a marketing exercise to secure the redevelopment of the former Ashcroft site.
2.3To delegate authority to the Assistant Director for Housing and Homelessness Prevention, to grant a 250 year development lease of the former Ashcroft site to Worthing Homes (Housing Association), subject to Heads of Terms being agreed and secured via a contract between Adur District Council and Worthing Homes, and subject to receipt of a valuation report confirming best consideration has been achieved by the Council together with any other associated legal documentation.
Context
1.1Ashcroft is a former sheltered housing site located at 100 Kingston Lane in Southwick. The site previously accommodated 21 flats, and 8 bungalows which had offered sheltered housing to Council tenants since 1982.
1.2The site is currently vacant, with demolition works underway. A Type 1 Fire Risk Assessment and subsequent technical notes provided by Potter Raper to Adur Homes Fire Officers indicated serious issues with Ashcroft’s evacuation strategy and compartmentation of the building in 2019. 1.3. As a result, in early 2020 residents were decanted to allow an intrusive Type 4 Fire Risk Assessment. As well as upgrades to fire doors and escape stairs, recommendations included a number of intrusive actions such as ensuring fire resistance of the steel structure, ceilings, inner skin of external walls and soil pipes, firestopping roof cavities and walls and installing cavity barriers around window openings.
1.4Alongside the above, many flats would require their layout and services adjusting to ensure that residents would have a safe exit in event of a fire. The report concluded that risk to life from fire at these premises was substantial. The building also did not meet the requirements of the Homes (Fitness for Human Habitation) Act 2018. As a result, the building could not be occupied.
1.5For the above reasons, in July 2021 the Adur Joint Strategic Sub-Committee (AJSSC) approved the preferred option set out in the committee report, for the demolition of the main block and construction of a modern, larger block.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Disposal of Ashcroft, 100 Kingston Lane, to Worthing Homes, and entry into a Development Agreement with Worthing Homes to secure the redevelopment of the site to provide sheltered accommodation.Report
JSC/51/23-24Disposal of Ashcroft, 100 Kingston Lane, to Worthing Homes, and entry into a Development Agreement with Worthing Homes to secure the redevelopment of the site to provide sheltered accommodation.This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.